fixed unit price simulation for disposal of spent fuel ... - Greenpeace UK
fixed unit price simulation for disposal of spent fuel ... - Greenpeace UK
fixed unit price simulation for disposal of spent fuel ... - Greenpeace UK
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Research Report<br />
Model Parameter Initial Value Technical Comment<br />
NDA Contingency Cost<br />
<strong>for</strong> Hotter Spent Fuel<br />
0% Depending on their storage period, high burn-up EPR<br />
and AP1000 <strong>spent</strong> <strong>fuel</strong> assemblies radiate more heat than<br />
standard burn-up AGR <strong>spent</strong> <strong>fuel</strong>s, and so may need<br />
physically spacing wider apart inside repository tunnels.<br />
In order to accommodate high burn-up <strong>spent</strong> <strong>fuel</strong>s,<br />
greater spacing <strong>of</strong> tunnels or fewer <strong>fuel</strong> assemblies per<br />
storage canister might be necessary. The marginal cost <strong>of</strong><br />
disposing <strong>of</strong> EPR <strong>spent</strong> <strong>fuel</strong>s is likely to be slightly larger<br />
than AGR <strong>spent</strong> <strong>fuel</strong>s because the tunnels need to be<br />
longer to accommodate this extra spacing. These longer<br />
tunnels will cost more (per tU) to excavate than standard<br />
AGR tunnels. To correct <strong>for</strong> this, FUPSIM can add a<br />
contingency cost to the scaled-up cost <strong>of</strong> the extra repository<br />
space needed <strong>for</strong> new build <strong>spent</strong> <strong>fuel</strong>. For example,<br />
if the EPR tunnels need to be twice as long as<br />
standard AGR tunnels then FUPSIM could add a 100%<br />
cost increase. However this correction factor should be<br />
used cautiously depending on expert judgement by a<br />
mining engineer. FUPSIM sets the default correction<br />
factor to zero %, meaning that the cost <strong>of</strong> disposing <strong>of</strong><br />
EPR <strong>fuel</strong> is the same as AGR <strong>fuel</strong>. However FUPSIM<br />
allows a contingency cost correction <strong>of</strong> up to 300% if this<br />
is judged necessary. The correction factor is not likely to<br />
be needed if the EPR <strong>spent</strong> <strong>fuel</strong> cooling and storage time<br />
is greater than 75 years. NDA Disposability Assessment<br />
concludes that 100 years cooling would be needed <strong>for</strong><br />
65,000 MWd/tU burn-up EPR <strong>spent</strong> <strong>fuel</strong> to maintain a<br />
repository temperature limit <strong>of</strong> 100 o C. For lower burnups,<br />
75 years cooling would be needed <strong>for</strong> 50,000<br />
MWd/tU burn-up EPR <strong>fuel</strong>, to meet the same repository<br />
temperature limit <strong>of</strong> 100 o C. A correction factor is only<br />
likely to be needed <strong>for</strong> early <strong>disposal</strong> <strong>of</strong> high burn-up<br />
<strong>spent</strong> <strong>fuel</strong>s with less than 75 years cooling, but the % is a<br />
matter <strong>of</strong> judgement. The authors are grateful to Mr<br />
Hugh Richards <strong>for</strong> discussions on this issue.<br />
Jackson Consulting 24