02.01.2014 Views

fixed unit price simulation for disposal of spent fuel ... - Greenpeace UK

fixed unit price simulation for disposal of spent fuel ... - Greenpeace UK

fixed unit price simulation for disposal of spent fuel ... - Greenpeace UK

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Research Report<br />

Model Parameter Initial Value Technical Comment<br />

NDA Contingency Cost<br />

<strong>for</strong> Hotter Spent Fuel<br />

0% Depending on their storage period, high burn-up EPR<br />

and AP1000 <strong>spent</strong> <strong>fuel</strong> assemblies radiate more heat than<br />

standard burn-up AGR <strong>spent</strong> <strong>fuel</strong>s, and so may need<br />

physically spacing wider apart inside repository tunnels.<br />

In order to accommodate high burn-up <strong>spent</strong> <strong>fuel</strong>s,<br />

greater spacing <strong>of</strong> tunnels or fewer <strong>fuel</strong> assemblies per<br />

storage canister might be necessary. The marginal cost <strong>of</strong><br />

disposing <strong>of</strong> EPR <strong>spent</strong> <strong>fuel</strong>s is likely to be slightly larger<br />

than AGR <strong>spent</strong> <strong>fuel</strong>s because the tunnels need to be<br />

longer to accommodate this extra spacing. These longer<br />

tunnels will cost more (per tU) to excavate than standard<br />

AGR tunnels. To correct <strong>for</strong> this, FUPSIM can add a<br />

contingency cost to the scaled-up cost <strong>of</strong> the extra repository<br />

space needed <strong>for</strong> new build <strong>spent</strong> <strong>fuel</strong>. For example,<br />

if the EPR tunnels need to be twice as long as<br />

standard AGR tunnels then FUPSIM could add a 100%<br />

cost increase. However this correction factor should be<br />

used cautiously depending on expert judgement by a<br />

mining engineer. FUPSIM sets the default correction<br />

factor to zero %, meaning that the cost <strong>of</strong> disposing <strong>of</strong><br />

EPR <strong>fuel</strong> is the same as AGR <strong>fuel</strong>. However FUPSIM<br />

allows a contingency cost correction <strong>of</strong> up to 300% if this<br />

is judged necessary. The correction factor is not likely to<br />

be needed if the EPR <strong>spent</strong> <strong>fuel</strong> cooling and storage time<br />

is greater than 75 years. NDA Disposability Assessment<br />

concludes that 100 years cooling would be needed <strong>for</strong><br />

65,000 MWd/tU burn-up EPR <strong>spent</strong> <strong>fuel</strong> to maintain a<br />

repository temperature limit <strong>of</strong> 100 o C. For lower burnups,<br />

75 years cooling would be needed <strong>for</strong> 50,000<br />

MWd/tU burn-up EPR <strong>fuel</strong>, to meet the same repository<br />

temperature limit <strong>of</strong> 100 o C. A correction factor is only<br />

likely to be needed <strong>for</strong> early <strong>disposal</strong> <strong>of</strong> high burn-up<br />

<strong>spent</strong> <strong>fuel</strong>s with less than 75 years cooling, but the % is a<br />

matter <strong>of</strong> judgement. The authors are grateful to Mr<br />

Hugh Richards <strong>for</strong> discussions on this issue.<br />

Jackson Consulting 24

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!