1: Introduction Central Kitsap County Wastewater Facility Plan<br />

1.2 General Planning Area Definition<br />

A vicinity map showing the general Central Kitsap planning area is provided in Figure 1-1. The planning area<br />

is narrowed in scope as physical, regulatory, and jurisdictional considerations are taken into account; this is<br />

described in Chapter 2. This modified area becomes the study area for which specific recommendations are<br />

made.<br />

1.3 Description of Scope of Work<br />

This Facility Plan presents a through analysis of the factors that affect the selection of project alternatives<br />

over a 20-year period (2005–2025):<br />

• planning area characteristics and population projections<br />

• estimated wastewater flows and loadings<br />

• condition of existing wastewater infrastructure<br />

• current regulations<br />

Based on these factors, a methodology is established by which capital projects for wastewater collection,<br />

treatment, and reuse are identified, evaluated against relevant criteria, and ranked. The key criteria that most<br />

heavily influence the selection of future projects for further consideration are shown in Table 1-1. By<br />

systematically screening all project alternatives against these criteria, the field of alternatives is narrowed and<br />

the optimal combination of technologies emerges. Resultant project recommendations are provided—both<br />

with and without reuse alternatives—and cost estimates are provided.<br />

Table 1-1. Key Criteria Affecting Wastewater Capital Projects<br />

Key criterion<br />

Facility Plan chapters where discussed<br />

1. Correct known wastewater system deficiencies 4, 7<br />

2. Repair and replace aged assets 4<br />

3. Provide wastewater service capacity for planning period growth<br />

3<br />

(serving wastewater flow and load projections)<br />

4. Regulatory compliance (present and future) 4, 5<br />

5. Land use 2, 7, 8<br />

6. Accepted engineering design criteria 6, 7, 8<br />

7. Best available technologies 8<br />

8. System operational considerations 8<br />

9. Flexibility for future expansion 7, 8<br />

10. Reclaimed water utilization 8<br />

11. Energy usage 8<br />

12. Biosolids utilization 8<br />

13. Environmental and sensitive area concerns 2, 7, 8<br />

14. Community considerations 7, 8<br />

15. Planning-level costs 6, 7, 8, 9<br />

1-2<br />

DRAFT for review purposes only.<br />

Use of contents on this sheet is subject to the limitations specified at the end of this document.<br />

P:\132857 Kitsap WW Facility Plan Ph II\600 Facility Plan\Revision 3 Draft Final Facility Plan\Chapter 1\Chapter 1_draft.doc

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!