1: Introduction Central Kitsap County Wastewater Facility Plan<br />
1.2 General Planning Area Definition<br />
A vicinity map showing the general Central Kitsap planning area is provided in Figure 1-1. The planning area<br />
is narrowed in scope as physical, regulatory, and jurisdictional considerations are taken into account; this is<br />
described in Chapter 2. This modified area becomes the study area for which specific recommendations are<br />
made.<br />
1.3 Description of Scope of Work<br />
This Facility Plan presents a through analysis of the factors that affect the selection of project alternatives<br />
over a 20-year period (2005–2025):<br />
• planning area characteristics and population projections<br />
• estimated wastewater flows and loadings<br />
• condition of existing wastewater infrastructure<br />
• current regulations<br />
Based on these factors, a methodology is established by which capital projects for wastewater collection,<br />
treatment, and reuse are identified, evaluated against relevant criteria, and ranked. The key criteria that most<br />
heavily influence the selection of future projects for further consideration are shown in Table 1-1. By<br />
systematically screening all project alternatives against these criteria, the field of alternatives is narrowed and<br />
the optimal combination of technologies emerges. Resultant project recommendations are provided—both<br />
with and without reuse alternatives—and cost estimates are provided.<br />
Table 1-1. Key Criteria Affecting Wastewater Capital Projects<br />
Key criterion<br />
Facility Plan chapters where discussed<br />
1. Correct known wastewater system deficiencies 4, 7<br />
2. Repair and replace aged assets 4<br />
3. Provide wastewater service capacity for planning period growth<br />
3<br />
(serving wastewater flow and load projections)<br />
4. Regulatory compliance (present and future) 4, 5<br />
5. Land use 2, 7, 8<br />
6. Accepted engineering design criteria 6, 7, 8<br />
7. Best available technologies 8<br />
8. System operational considerations 8<br />
9. Flexibility for future expansion 7, 8<br />
10. Reclaimed water utilization 8<br />
11. Energy usage 8<br />
12. Biosolids utilization 8<br />
13. Environmental and sensitive area concerns 2, 7, 8<br />
14. Community considerations 7, 8<br />
15. Planning-level costs 6, 7, 8, 9<br />
1-2<br />
DRAFT for review purposes only.<br />
Use of contents on this sheet is subject to the limitations specified at the end of this document.<br />