assessment have been proposed to be completed. The topographical survey for<br />

command area <strong>of</strong> irrigation has been proposed to be completed 40% <strong>of</strong> the total<br />

works. The canal alignment survey have been targeted as 68%. The seismic data<br />

collection has been proposed during 205-06 as 23%, target for navigational survey<br />

as 56%. The target for topographical survey till December 2005 was 63% and<br />

achievement is 15%. The targets for Saptakosi and Kamla dam in respect <strong>of</strong><br />

geological investigation till December 2005 were 15% and 58% respectively, the<br />

achievement being 5% and 50%. The target for EIA studies till December 2005<br />

was fixed as 43% against which nil progress has been made as the works have<br />

not been awarded till date. The targets for topographical survey <strong>of</strong> command area<br />

and canal alignment survey till December 2005 were 25% and 32% with nil<br />

progress so far as these are to be taken up by consultants. The target for seismic<br />

data collection till December 2005 was zero. The target for field work related to<br />

navigational survey till December 2005 was 41% with 25% achievement.<br />

Upper Karnali & Burhi Gandaki Hydro Electric Projects:<br />

1.50 HMG Nepal also desired India to take up implementation <strong>of</strong> 300 MW Upper<br />

Karnali Hydro Electric Project and preparation <strong>of</strong> Detailed Project Report in<br />

respect <strong>of</strong> 600 MW Burhi Gandaki Hydro Electric Project which are under<br />

discussion. An Inter-Ministerial Team was set up in the <strong>Ministry</strong> <strong>of</strong> <strong>Water</strong><br />

<strong>Resources</strong> to discuss the modalities for taking up the above projects by<br />

Government <strong>of</strong> India. It was decided that NHPC will take up implementation <strong>of</strong><br />

Upper Karnali H.E. Project including upgradation <strong>of</strong> the Detailed Project Report.<br />

As regards Burhi Gandaki Hydroelectric project in order to discuss the modalities<br />

for taking up field investigations and studies and preparation <strong>of</strong> Detailed Project<br />

Report, a technical team from the <strong>Ministry</strong> <strong>of</strong> <strong>Water</strong> <strong>Resources</strong> visited Nepal in<br />

October 2003. In the 2 nd meeting <strong>of</strong> Joint Committee <strong>of</strong> <strong>Water</strong> <strong>Resources</strong> held in<br />

October, 2004 at New Delhi, it has been agreed to take up the field investigations<br />

and preparation <strong>of</strong> Detailed Project Report by an agency <strong>of</strong> Government <strong>of</strong> India<br />

for which a MOU is to be signed between the two Governments to undertake the<br />

work.<br />

Indo-Nepal Joint Committee on <strong>Water</strong> <strong>Resources</strong> (JCWR)<br />

1.51 The Indo-Nepal Joint Committee on <strong>Water</strong> <strong>Resources</strong> (JCWR) was<br />

constituted in pursuance <strong>of</strong> the decisions taken by the Prime Ministers <strong>of</strong> Nepal<br />

and India during the visit <strong>of</strong> the Hon’ble Prime Minister <strong>of</strong> Nepal to India from 31<br />

July - 6 August 2000. The JCWR has been constituted to discuss and take<br />

decisions on important issues pertaining to cooperation in the water resources<br />

sector including implementation <strong>of</strong> the existing agreements and understandings.<br />

The JCWR shall oversee the work <strong>of</strong> all the Technical and Expert Level<br />

Committees and Groups in the field <strong>of</strong> water resources. It acts as an Umbrella<br />

Committee <strong>of</strong> the committees and groups. The 2 nd meeting <strong>of</strong> this Committee i.e.<br />

<strong>of</strong> JCWR was held in Delhi on 7-8 October, 2004 wherein the progress made in<br />

the various bilateral committees / meetings were discussed concerning to mutual<br />

interest in the water resources sector to both the countries.<br />