Safety manual<br />
Concrete delivery and placing machines<br />
2.6.4 Opening delivery lines<br />
You must not open or tap delivery lines while these are<br />
pressurized. Concrete exiting under pressure can cause injury.<br />
The concrete column must be depressurized by reverse pumping<br />
before the delivery line is opened. Never work bending directly over<br />
the coupling.<br />
wz0075<br />
2.6.5 Clearance to delivery<br />
lines<br />
2.6.6 Fastening delivery<br />
lines<br />
2.6.7 Continuation delivery<br />
lines<br />
No–one should remain in the vicinity of separate delivery lines<br />
during pumping operations. Cordon off the danger zone. If it is not<br />
possible to place a large enough cordon around the danger zone,<br />
the delivery line must be covered by suitable means.<br />
Delivery lines, in particular riser lines which are not laid along<br />
placing booms, must be securely fastened in order to transfer the<br />
forces generated in them into the structure or other structural<br />
members. The lines must be laid so as to avoid kinks, sharp bends,<br />
stresses and damage during pumping operations.<br />
A continuation delivery line connected to the placing boom must<br />
not exert a load on the boom.<br />