26.05.2014 Views

DSM Terminal-Area-Concept-Plan-Technical-Report - FINAL

DSM Terminal-Area-Concept-Plan-Technical-Report - FINAL

DSM Terminal-Area-Concept-Plan-Technical-Report - FINAL

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Foth Infrastructure & Environment<br />

CONNICO<br />

Des Moines International Airport<br />

<strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong> <strong>Technical</strong> <strong>Report</strong><br />

Prepared for<br />

Des Moines Airport Authority<br />

Des Moines, Iowa<br />

April 2014<br />

Aerial Source: Google Earth


Table of Contents<br />

1. Executive Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3<br />

2. Existing Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6<br />

• Airport Overview<br />

• Airfield Facilities<br />

• Passenger <strong>Terminal</strong> Complex<br />

• Ground Transportation Facilities and Conditions<br />

• Air Cargo Facilities<br />

• General Aviation and Support Facilities<br />

• Iowa Air National Guard Facilities<br />

3. Aviation Demand Forecast . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24<br />

• Forecast Approach<br />

• Forecast Summary<br />

• Economic Basis for Airline Traffic<br />

• Historical Aviation Activity<br />

• Aviation Activity Forecasts<br />

5. <strong>Concept</strong> Alternatives Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59<br />

• Land Use Alternatives<br />

• <strong>Terminal</strong> Alternatives<br />

6. Preferred Alternatives Refinements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74<br />

• Preferred Land Use Alternative Refinements<br />

• Preferred <strong>Terminal</strong> Alternative Refinements<br />

• Project Implementation <strong>Plan</strong><br />

7. Preliminary Financial Capacity Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . .82<br />

• Key Drivers<br />

• Industry Benchmarks<br />

• Preliminary <strong>Plan</strong> of Finance<br />

• Sensitivity Analyses and Financial Conclusions<br />

4. Demand/Capacity and Facilities Requirements Analyses . . . . . . . . . . . . . . 35<br />

• Passenger <strong>Terminal</strong> Requirements<br />

• Ground Transportation Requirements<br />

• Airfield Requirements<br />

• Cargo, General Aviation, and Support Facility Requirements<br />

2<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Executive Summary<br />

<strong>Plan</strong> is needed to address obsolescence of existing passenger terminal and general aviation expansion<br />

KEY POINTS<br />

• Airport is growing and<br />

needs to replace its<br />

terminal.<br />

• A workshop approach<br />

was used to guide the<br />

Advisory Committee.<br />

The Des Moines Airport Authority (the Authority)<br />

undertook the preparation of this <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong><br />

<strong>Plan</strong> in support of needed improvements to the Des<br />

Moines International Airport (the Airport) terminal<br />

complex. The existing terminal building was first built in<br />

1948 and, although it has been subject to upgrades and<br />

improvements over the years, it has reached the end of its<br />

useful economic life. The Authority seeks a solution to the<br />

problems with the terminal complex, and wants to do so<br />

with a full understanding of the context of the Airport and<br />

the long-term needs of the other functional airport<br />

components (such as air cargo, the Iowa Air National<br />

Guard, corporate aviation, general aviation and airport<br />

support functions). In this sense, this document closely<br />

resembles an airport master plan. The planning effort<br />

includes key elements of a master plan, but with a distinct<br />

focus on the terminal area.<br />

Figure B shows enplanement projections rising at 3.4%<br />

annual until 2032.<br />

Figure A<br />

Passenger Congestion and Overflow at Peak<br />

The <strong>Plan</strong>ning Study<br />

The <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong> includes all of the elements of<br />

a classic master plan: inventory, forecasts, facility requirements<br />

analysis, alternatives analysis, financial capacity analysis, an<br />

environmental overview, and an airport layout plan (ALP)<br />

update. The study was overseen by an Advisory Committee,<br />

which met with Airport staff and the consultant team four<br />

times over a seven month period, in a workshop setting. The<br />

four workshops were organized as follows:<br />

Workshop #1 established the shortcomings of the existing<br />

terminal complex, presented long range demand forecasts,<br />

and described the preliminary financial capacity analysis.<br />

Figure C indicates shortcomings of the major functional<br />

components of the existing passenger terminal. Passenger<br />

activity levels are described as Million Annual Passengers<br />

(MAP), which reflects both enplanements and deplanements.<br />

The Situation<br />

The Authority operates the busiest and most successful<br />

airport in Iowa; and its activities are growing. The airfield<br />

system is effective in accommodating operational demand<br />

and supporting the Airport’s users. However, the<br />

passenger terminal building is inadequate. In 2013, pieces<br />

of the building structure literally fell from the ceiling to the<br />

floor. Major functional components of the terminal<br />

complex are beyond capacity, or near it. With passenger<br />

traffic increasing and airlines adding routes, the timing was<br />

right for the Authority to address the situation within the<br />

context of a long-range plan.<br />

Source: <strong>DSM</strong> Operations.<br />

Figure B<br />

Historical and Forecast Enplaned Passengers<br />

Figure C<br />

Existing <strong>Terminal</strong> Stress Chart<br />

The goal of plan was to:<br />

• Develop a long-term solution to the obsolescence of the<br />

existing passenger terminal complex and its lack of<br />

capacity expansion potential<br />

• Take a comprehensive look at each of the Airport’s<br />

functional components to ensure they could each grow<br />

and meet projected demands<br />

• Develop a terminal plan must be functional, affordable,<br />

and improve the passenger experience<br />

Illustrated on Figure A is a photo showing passenger<br />

congestion and overflow at the existing passenger terminal<br />

during peak.<br />

3<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Executive Summary<br />

<strong>Terminal</strong> plan considered long term needs of all airport functions<br />

KEY POINTS<br />

• <strong>Plan</strong> reviewed all Airport<br />

functional needs;<br />

including highest and<br />

best use in each<br />

quadrant.<br />

Workshop #2 presented long range facility requirements for<br />

the primary functional components of the Airport (including<br />

passenger terminal building, roadways, corporate aviation,<br />

military, air cargo, airfield, etc.) and explored at a high level<br />

alternative ways to meet those demands as shown in the<br />

summary in Table ES-1. The review was narrowed to the two<br />

top land use concepts (showing terminal development in the<br />

south or east “quadrants” of the Airport), each of which<br />

allows for compatible future development.<br />

A. Passenger terminal<br />

(square feet)<br />

B. Ground transportation<br />

Table ES-1<br />

Facility Requirements Summary<br />

Existing<br />

Facilities<br />

2.5<br />

MAP<br />

3.0<br />

MAP<br />

4.0<br />

MAP<br />

272,900 207,300 236,000 315,500<br />

Public parking (spaces) 4,258 4,220 5,100 6,800<br />

Employee parking (spaces) 273 280 300 340<br />

Rental car facilities (spaces) 370 350 420 570<br />

Quick turnaround (acres) 8.6 5.5 6.5 8.8<br />

C. Air cargo facilities (acres) 50.0 10.0 10.6 11.7<br />

D. General aviation<br />

Aircraft parking apron<br />

(positions)<br />

Aircraft storage facilities<br />

(square feet)<br />

E. Airline Support<br />

50.0 65.0 65.0 66.0<br />

294,000 286,000 326,100 428,200<br />

Fuel storage (gallons) 440,000 439,300 485,400 599,200<br />

Land <strong>Area</strong> (acres) 1.7 1.7 1.8 2.3<br />

GSE equipment parking<br />

areas (square feet)<br />

n.a. 32,300 37,800 49,200<br />

GSE gross land area (acres) 0.5 0.9 0.9<br />

Workshop #3 explored alternative passenger terminal<br />

development schemes for the two short-listed land use<br />

alternatives and presented results of the technical analyses<br />

conducted. This helped the Advisory Committee in their<br />

deliberations to select a preferred terminal alternative, which<br />

would then be further refined.<br />

Workshop #4 presented information on the refinement of<br />

the preferred terminal area concept, including project costs,<br />

financial capacity and an implementation plan.<br />

The Solution<br />

The <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong> Advisory Committee selected<br />

an alternative that would build a new terminal complex<br />

(terminal building, auto parking, roadways, etc.) in the south<br />

quadrant of the Airport. This is currently the site of air cargo<br />

operations. Following are some of the key reasons for<br />

selecting this site for a new terminal development area:<br />

• Site is currently underutilized, as a result of fundamental<br />

shifts in the air cargo industry.<br />

• The heavy apron built to support air cargo operations is an<br />

asset that can be more fully used to support commercial<br />

passenger airline operations<br />

• Compared to the alternative of replacing the terminal<br />

building at its current site, developing a new terminal<br />

building on the south site can be done without<br />

affecting passengers during construction.<br />

• The south site has greater expansion capabilities<br />

beyond the planning timeframe and as such was<br />

viewed as a better long range investment.<br />

The preferred terminal alternative is shown graphically<br />

on Figure D. It would be developed in two major phases,<br />

with initial build-out having 14 gates, and full build-out<br />

with four additional gates for a total of 18 gates.<br />

Additionally, as mentioned above, this site has capacity<br />

to expand with more gates as demand may dictate<br />

beyond the projected demand identified in this study.<br />

The initial phase includes a new loop roadway system for<br />

automobile access, a new parking garage (although the<br />

existing garage would continue to be used for long term<br />

parking), a central processor building (housing ticketing,<br />

bag claim, etc.) and a linear concourse with double<br />

loaded end caps. This is a very efficient layout and will<br />

serve the Airport well for decades.<br />

Figure D<br />

Preferred <strong>Terminal</strong> Alternative<br />

4<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Executive Summary<br />

Funding and implementation plans developed<br />

KEY POINTS<br />

• Phase 1 (14) gates<br />

estimated to cost $420<br />

million in 2014 dollars.<br />

• Inflation will increase<br />

construction costs to<br />

$538 million by 2024<br />

completion.<br />

Enabling projects that are needed in order to make the<br />

preferred alternative work are described as follows:<br />

• Negotiate agreement with Iowa Air National Guard<br />

(IANG) regarding property<br />

and facilities they need to support their new mission<br />

• Relocate Signature Flight Support and FedEx to the<br />

IANG site<br />

• Demolish select buildings in the south quadrant<br />

• Build new parallel taxiway on the southwest side of<br />

Runway 13-31<br />

The cost of this alternative (in 2014 dollars) is shown in<br />

Table ES-2 below. This includes hard construction costs as<br />

well as soft costs such as design, project management, and<br />

contingencies.<br />

The schedule for implementing the terminal program is<br />

shown in Figure E below, with a date of beneficial occupancy<br />

(opening date) of 2024.<br />

Figure E<br />

Project Implementation Schedule<br />

Conclusions<br />

• The Des Moines Airport Authority has developed a<br />

plan for a modern, fully functional passenger terminal<br />

complex to replace its aging and obsolete terminal<br />

infrastructure. Once completed, it will provide a high<br />

level of service to its passengers and serve the region<br />

effectively for decades. Implementing the plan<br />

requires many steps and there are challenges the<br />

Authority will face. Following are some conclusions<br />

and recommendations for moving the project forward.<br />

• The Authority should continue refining the plan<br />

through a programming effort, which will provide<br />

greater detail and clarity to the plan. This will likely<br />

reduce the magnitude of some of the contingencies<br />

included in the cost estimate.<br />

Table ES-2<br />

Refined Order of Magnitude Cost Summary<br />

• It is important to work with the airlines on this plan<br />

and seek alignment with them.<br />

The timeline for building the terminal and support facilities was<br />

established to take into account other priorities for Airport<br />

funding, especially the airfield which requires major<br />

rehabilitation. With inflation adjustments made for construction<br />

costs, and considering the implementation timeline, a<br />

conceptual funding plan for the $538 million project was<br />

developed, as shown on Figure F.<br />

Figure F<br />

<strong>Concept</strong>ual Funding <strong>Plan</strong><br />

• The conceptual funding plan includes a $200 million<br />

plug for non-AIP grants. The Airport will need to get<br />

creative in finding these additional sources of monies<br />

in order to make the plan viable.<br />

• Negotiations with the IANG are an important element<br />

of moving the plan forward. A portion of the property<br />

that has been used by the IANG to support its<br />

previous mission is needed for key plan elements,<br />

especially corporate general aviation.<br />

5<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


EXISTING CONDITIONS<br />

• Airport Overview<br />

• Airfield Facilities<br />

• Passenger <strong>Terminal</strong> Complex<br />

• Ground Transportation Facilities and Conditions<br />

• Air Cargo Facilities<br />

• General Aviation and Support Facilities<br />

• Iowa Air National Guard Facilities


Introduction and Airport Overview<br />

Key regional airport with strong local traffic base<br />

KEY POINTS<br />

• Most important Airport<br />

in Iowa<br />

• Over two million<br />

passengers served in<br />

2013<br />

Airport setting<br />

Des Moines International Airport (the Airport) is a civilmilitary<br />

public airport located three miles southwest of<br />

downtown Des Moines, in the southern portion of Polk<br />

County (Figure 1). It was opened in 1933 and has since<br />

served residents and visitors of the Des Moines Metropolitan<br />

Statistical <strong>Area</strong> (MSA) consisting of Polk, Dallas, Warren, Des<br />

Moines and Guthrie counties in Iowa. It is classified in the<br />

National <strong>Plan</strong> of Integrated Airport Systems as a primary<br />

commercial service airport and has an important role in the<br />

national, state, and local air transportation systems.<br />

Des Moines International Airport is a small air traffic hub and<br />

ranked as the 86 th largest passenger airport in the United<br />

States in 2012. It is primarily an Origin and Destination (O&D)<br />

airport with 96% of its passengers originating from the<br />

Airport and the remaining 4% connecting.<br />

This large O&D passenger base reflects the strength of the<br />

Des Moines MSA’s economy and its role as a business, trade,<br />

manufacturing, and government center. In August 2013, the<br />

Airport was served by four mainline passenger airlines, three<br />

low-cost carrier airlines, and seven regional affiliates, which<br />

together provided 49 daily nonstop departures to 15<br />

destinations. The Airport was also served by two national allcargo<br />

airlines – FedEx and UPS – as well as regional feeder<br />

cargo airlines.<br />

Figure 1<br />

Airport Vicinity Map<br />

Des Moines International Airport<br />

7<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Airport Overview<br />

Airport setting and site overview<br />

Airport site overview<br />

The Airport occupies over 2,600 acres of land bounded by<br />

residential neighborhoods to the north; Fleur Drive to the<br />

east; Highway 5 to the south; and Highway 28 to the west.<br />

The main entrance to the passenger terminal is on Fleur<br />

Drive.<br />

Figure 2 presents the overall Airport site, which consists of<br />

the following primary components:<br />

• Airfield – The airfield takes up a majority of the total<br />

Airport land area, and includes two runways and<br />

associated taxiways, aprons, and other safety-related<br />

protection zones.<br />

• Passenger terminal building – The passenger terminal<br />

building is located in the east quadrant of the Airport and<br />

includes the terminal building, an intermediate connector,<br />

and the concourse to accommodate 11 aircraft gates.<br />

• Air cargo – The majority of 2 of cargo operations take<br />

place in the south cargo area. Two all-cargo carriers –<br />

United Parcel Service (UPS) and FedEx - operate their<br />

regional hub and express freight service out of these<br />

facilities. A small cargo operation also exists immediately<br />

south of the passenger terminal building. An East Air<br />

Cargo Building (Building 5) located on the south portion of<br />

the east quadrant is used by the commercial carriers for<br />

air cargo carried on commercial passenger flights.<br />

• General aviation – General aviation activities are scattered<br />

around the Airport. Elliott Aviation, a fixed-based<br />

operator (FBO), leases land to the north, east of the Iowa<br />

Air National Guard. Occupying portion of the east<br />

quadrant, north of the passenger terminal, is another FBO,<br />

Signature Flight Support. Aircraft storage facilities are<br />

located in the north, east, and south quadrants of the<br />

Airport.<br />

• Parking and ground transportation – Two 4-level parking<br />

garages are located in front of the passenger terminal<br />

building along with 5 surface parking lots distributed along<br />

Fleur Drive. Rental car lots are close-in to the terminal<br />

building , served by Cowles Drive and Duck Pond Road.<br />

The Quick Turn-Around (QTA) facility for wash, fuel, light<br />

maintenance and short-term storage of rental cars is<br />

located on South Airport Frontage Road adjacent to the<br />

rental car surface lot.<br />

• Support facilities – Primary support facilities include: airline maintenance<br />

facilities; fuel farm; Federal Aviation Administration (FAA) air traffic control<br />

facilities; employee parking; Aircraft Rescue and Firefighting (ARFF); and<br />

airfield / airport maintenance support facilities.<br />

LEGEND<br />

Figure 2<br />

Airport Site Overview<br />

Des Moines International Airport<br />

8<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Airfield Facilities<br />

Runway and Taxiway System<br />

The airfield is depicted on Figure 3, and consists of runways,<br />

taxiways, apron areas, and other facilities. Airfield facilities<br />

meet Airport Reference Code (ARC) D-IV criteria – meaning<br />

the runways and taxiways can accommodate air carrier<br />

aircraft with approach speeds up to 165 knots and<br />

wingspans of up to 170 feet. Airplane Design Group (ADG)<br />

IV aircraft include the Boeing 757-200/300 and Boeing 767-<br />

400, among others.<br />

Figure 3<br />

Airfield Facilities Map<br />

Des Moines International Airport<br />

Runways<br />

The airfield currently consists of two runways and<br />

associated taxiways in a cross configuration. Runway data,<br />

including key airfield dimensions and navigational aids, are<br />

summarized in Table 1.<br />

Runway 5-23, running in the southwest - northeast<br />

orientation, is 9,003 feet long by 150 feet wide. The runway<br />

has both concrete and asphalt surfaces and is used for both<br />

arrivals and departures. A full-length parallel taxiway,<br />

Taxiway P, is located 400 feet south of Runway 5-23, while a<br />

partial parallel taxiway, Taxiway R, is located 400 feet north<br />

of the runway.<br />

Runway 13-31, running in the northwest - southeast<br />

orientation, is 9,001 feet long by 150 feet wide. The runway<br />

has an asphalt surface and is used for both arrivals and<br />

departures. A full-length parallel taxiway, Taxiway D, is<br />

located 400 feet north of Runway 13-31.<br />

Taxiways<br />

Figure 3 shows the taxiways that connect the runway<br />

system to the aircraft parking aprons. All taxiways at the<br />

Airport are at least 75 feet wide. Taxiway shoulders are 25<br />

feet wide, which meets the FAA design guidelines for<br />

Taxiway Design Group (TDG) 5 aircraft – equivalent to the<br />

Boeing 757-200/300 and Boeing 767-400 aircraft.<br />

Taxiways are designated with a single letter and includes the<br />

following:<br />

• Taxiway A connects the terminal ramp area to Taxiway P<br />

• Taxiway B connects the terminal ramp to Runway 5-23<br />

and the general aviation ramp to both Runway 5-23 and<br />

Taxiway D<br />

• Taxiway C connects the terminal ramp to Taxiway D<br />

9<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Airfield Facilities<br />

Runway and Taxiway System<br />

• Taxiway D is the full-length parallel taxiway north of Runway<br />

13-31. Taxiways D-1, D-2, D-4, D-5, and D-6 serve as<br />

connectors from the runway to the general aviation, Iowa Air<br />

National Guard (IANG), and terminal ramp areas<br />

• Taxiway P is the full-length parallel taxiway south of Runway<br />

5-23. Taxiways P-1, P-3, P-4, P-5, P-6, and P-7 serve as<br />

connectors from the runway to the terminal and south cargo<br />

ramp areas<br />

• Taxiway R is the partial parallel taxiway north of Runway 5-<br />

23. Taxiways R-1, and R-3 serve as connectors from the<br />

runway to the general aviation ramp area<br />

Navigational Aids and Approach Minimums<br />

Navigational aids enable the Airport to accommodate air traffic,<br />

especially during periods of low cloud cover and reduced<br />

visibility. The navigational aids installed at the Airport enable<br />

aircraft to operate under most weather conditions. In addition<br />

to these navigational aids, the FAA Airport Traffic Control Tower<br />

(ATCT) is located on the north quadrant of the Airport (Building<br />

73), directly west of the Elliott Aviation hangar and east of the<br />

Iowa Air National Guard, see Figure 14. The ATCT operates 24-<br />

hours a day.<br />

Airport runways include precision instrument approach<br />

procedures to allow continuous aircraft operations during<br />

periods of low visibility. A precision approach utilizes groundor<br />

satellite-based navigational aids to provide pilots with<br />

definitive guidance on the horizontal and vertical position of<br />

the aircraft.<br />

Runways 5 and 13 are equipped with a Category I ILS, which<br />

allows aircraft approaches to a decision height of 200 feet<br />

above ground level (AGL), with visibility minimums of 2400 RVR<br />

(0.5 miles) and 1800 RVR (0.38 miles) respectively.<br />

Runway 31 is equipped with Category IIIB ILS approaches to<br />

allow aircraft to land in even the most challenging of visibility<br />

conditions. Execution of these approaches requires aircraft to<br />

be equipped with specific avionics and pilots to receive<br />

additional training. Pilots flying the Category IIIB approach are<br />

able to land with a zero-foot cloud ceiling with visibility as low<br />

as 600 feet.<br />

Table 1<br />

Runway Data<br />

Des Moines International Airport<br />

Runway 13 Runway 31 Runway 5 Runway 23<br />

Airport Reference Code D-IV D-IV D-IV D-IV<br />

Runway length (feet) 9,001 9,001 9,003 9,003<br />

Runway width (feet) 150 150 150 150<br />

Runway end elevation (feet AMSL) 912.2 957.5 915.6 934.5<br />

Instrument approach procedures<br />

ILS CAT I<br />

RNAV(GPS)<br />

ILS CAT IIIB<br />

RNAV(GPS)<br />

ILS CAT I<br />

RNAV(GPS)<br />

VOR/DME<br />

RNAV(GPS)<br />

Runway approach slope 50:1 50:1 50:1 34:1<br />

Runway lighting HIRL HIRL HIRL HIRL<br />

Runway marking Precision Precision Precision Non-precision<br />

Pavement material Asphalt Asphalt<br />

Pavement strength (thousand lbs)<br />

Single gear<br />

Dual gear<br />

Dual tandem gear<br />

Approach aids<br />

133 (S)<br />

180 (D)<br />

340 (2D)<br />

VASI-4, MALSR, LOC,<br />

GS<br />

133 (S)<br />

180 (D)<br />

340 (2D)<br />

PAPI, ALSF2,<br />

Centerline Lights, TDZ<br />

Lights, LOC, GS<br />

Portland<br />

Cement/Asphalt<br />

133 (S)<br />

180 (D)<br />

340 (2D)<br />

PAPI, MALSR, LOC, GS<br />

Portland<br />

Cement/Asphalt<br />

133 (S)<br />

180 (D)<br />

340 (2D)<br />

PAPI, REIL<br />

Approach visibility minimums 1800 RVR 600 RVR 2400 RVR 1 mi<br />

ALSF-2 = High-intensity approach light system with centerline<br />

sequenced flasher<br />

AMSL = Above Mean Sea Level<br />

CAT = Category<br />

DME = Distance measuring equipment<br />

GPS = Global positioning system<br />

GS = Glideslope<br />

HIRL = High-intensity runway lights<br />

ILS = Instrument landing system<br />

LOC = Localizer<br />

MALSR = Medium-intensity approach light system<br />

with runway alignment indicator lights<br />

PAPI = Precision approach path indicator<br />

REIL = Runway end identifier lights<br />

RNAV = <strong>Area</strong> navigation<br />

RVR = Runway visual range<br />

VASI = Visual approach slope indicator<br />

VOR = Very high frequency omnidirectional range<br />

Sources: Airport Layout <strong>Plan</strong>, Des Moines International Airport, 2011.<br />

Airport Master <strong>Plan</strong>, Des Moines International Airport, 2007.<br />

10<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Passenger <strong>Terminal</strong> Complex<br />

<strong>Terminal</strong> Complex Overview<br />

The Airport’s passenger terminal complex is located in the east<br />

quadrant of the Airport marked by Runway 23 to the north,<br />

Runway 31 to the south, and Fleur Drive to the east. It<br />

occupies approximately 90 acres of land, providing a home for<br />

the passenger terminal building, aircraft parking apron, east<br />

cargo facilities, Signature Flight Support, entrance / circulation<br />

roadways, and automobile parking areas – see Table 2.<br />

Figure 4<br />

East Quadrant Overview<br />

Des Moines International Airport<br />

Passenger <strong>Terminal</strong> Building<br />

The original passenger terminal building was built in 1948 with<br />

an open concourse. In the late 1950s, the ground-load<br />

concourse was enclosed to provide shelter for the passengers.<br />

Then, in the late 1960s, a concourse was added on the second<br />

level to accommodate larger size aircraft and provide improved<br />

passenger level of service. The existing baggage system and<br />

passenger loading bridges were added in the 1980s.<br />

An overview of the existing terminal complex is shown on<br />

Figure 4. Floor plans of the terminal building are shown on<br />

Figures 5 through 7.<br />

Airport<br />

Building<br />

Number<br />

Table 2<br />

Existing East Quadrant Facilities<br />

Building Description<br />

Building <strong>Area</strong><br />

(square feet)<br />

1 Passenger <strong>Terminal</strong> and Concourse 273,000<br />

2 Federal Inspection Facility (Customs) 5,335<br />

4 Deicer Storage Building 180<br />

5 East Air Cargo Building 7,150<br />

6 Parking Office 1,800<br />

7 Des Moines Flying Services Hangar 12,840<br />

8 Signature Maintenance Hangar 24,000<br />

9 Signature Storage Hangar 15,000<br />

10 Signature East Office / Hangar 30,620<br />

11 Storm Water Control Building 200<br />

Sources: 2011 Airport Layout <strong>Plan</strong>, Foth Infrastructure & Environment.<br />

2007 Master <strong>Plan</strong> report.<br />

11<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Passenger <strong>Terminal</strong> Complex<br />

Existing Passenger <strong>Terminal</strong> Building<br />

The existing passenger terminal has 11 aircraft gates and<br />

consists of three primary levels, totaling approximately<br />

273,000 square feet. Concession support, airport support,<br />

maintenance, storage and mechanical spaces are located on<br />

the basement level. There’s a loading dock on the ground<br />

level located to the north of the existing passenger terminal<br />

where service items are received.<br />

On the first level are primary passenger processing areas:<br />

airline ticket counters and offices, baggage sorting and<br />

makeup devices, baggage claim, bag storage offices, rental car<br />

counters, concessions, meeter/greeter space, and airline<br />

operations spaces. The second level currently houses a<br />

staggered 6-lane security screening checkpoint, a central<br />

concessions node, and passenger holdrooms on the airside -<br />

Concourse A (5 gates) to the south, and Concourse C (6 gates)<br />

to the north. The airport administration offices are located<br />

landside on the second level. An approximately 1,600 sf<br />

Emergency Operations Center (EOC) is located on the third<br />

level, accessible from the airport administration area. The<br />

fourth level houses the original airport control tower and is<br />

not currently used.<br />

Table 3 summarizes the existing terminal space allocation.<br />

Figure 5<br />

Existing <strong>Terminal</strong> – Basement Level<br />

Des Moines International Airport<br />

12<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Passenger <strong>Terminal</strong> Complex<br />

Existing Passenger <strong>Terminal</strong> Building<br />

Figure 6<br />

Existing <strong>Terminal</strong> – First Level<br />

Des Moines International Airport<br />

13<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Passenger <strong>Terminal</strong> Complex<br />

Existing Passenger <strong>Terminal</strong><br />

Figure 7<br />

Existing <strong>Terminal</strong> – Second, Third and Fourth Levels<br />

Des Moines International Airport<br />

14<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Passenger <strong>Terminal</strong> Complex<br />

Existing Passenger <strong>Terminal</strong><br />

Table 3<br />

Existing <strong>Terminal</strong> Space Allocation Summary (in square feet)<br />

Des Moines International Airport<br />

First Level<br />

Second Level<br />

<strong>Terminal</strong> Functions<br />

Basement Level<br />

Airline Ops/Apron<br />

Ticketing/ Bag<br />

Claim<br />

Airport<br />

Administration<br />

Concourse<br />

TOTAL<br />

Ticketing / Airline ticket offices 0.0 0.0 11,720.0 0.0 0.0 11,720.0<br />

Outbound baggage makeup area 0.0 0.0 16,955.0 0.0 0.0 16,955.0<br />

Inbound baggage delivery area 0.0 0.0 4,060.0 0.0 0.0 4,060.0<br />

Baggage claim area 0.0 0.0 7,440.0 0.0 0.0 7,440.0<br />

Security screening / TSA offices 84.6 0.0 1,965.0 0.0 12,160.0 14,209.6<br />

Concessions 0.0 0.0 4,240.0 0.0 9,406.0 13,646.0<br />

Holdrooms 0.0 3,595.0 0.0 0.0 18,411.0 22,006.0<br />

Restrooms 0.0 310.0 2,120.0 527.0 2,928.0 5,885.0<br />

Public circulation 6,860.4 1,005.0 32,010.0 6,310.0 17,985.0 64,170.4<br />

Bag storage office / Airline support 0.0 10,928.0 805.0 715.0 0.0 12,448.0<br />

Airport support 22,366.5 25,360.0 5,915.0 24,712.0 5,008.0 83,361.5<br />

Concessions support 3,669.2 1,790.0 3,685.0 0.0 0.0 9,144.2<br />

Rental car / Ground transportation 0.0 0.0 3,600.0 0.0 0.0 3,600.0<br />

Miscellaneous/others 702.7 186.0 0.0 3,613.0 0.0 4,501.7<br />

Subtotal 33,683.3 43,174.0 94,515.0 35,877.0 65,898.0 273,147.3<br />

Total Floor <strong>Area</strong> 33,683.3 137,689.0 101,775.0 273,147.3<br />

15<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Passenger <strong>Terminal</strong> Complex<br />

Existing Passenger <strong>Terminal</strong> Situation<br />

KEY POINTS<br />

• Key terminal functional<br />

areas exceed their<br />

capacity during peak<br />

periods<br />

• The customer<br />

experience continues to<br />

erode<br />

Issues with an Aging Passenger <strong>Terminal</strong> Facility<br />

Throughout the past 65+ years, the existing terminal building<br />

had gone through many physical transformations, ranging from<br />

expansions, renovations, and modernizations, to address<br />

immediate issues and passenger demands. However, the<br />

existing structure and building systems remain original, have<br />

literally fallen apart and are beyond its useful lives. The<br />

existing structural column grid, designed to handle much lower<br />

passenger volumes, is inadequate to provide expansion and<br />

flexibilities to accommodate modern demands. Some<br />

outdated uses and functions, such as airline ticket offices, and<br />

the original airport control tower on the fourth level, are<br />

currently unused and not in optimal locations to attract<br />

leaseholds; therefore, have been non-revenue generators to<br />

the Airport.<br />

There’s also limited airside concessions to capitalize on<br />

passengers with longer airside dwell times due to current<br />

security protocols. With airlines trending towards flying larger<br />

and more fuel efficient aircraft, larger holdrooms that provide<br />

maximum exposure to concessions are in high demand.<br />

Restrooms also quickly become undersized with increased<br />

passenger traffic.<br />

The photos below provide a graphic illustration of the existing<br />

passenger terminal conditions, showing congestions at the<br />

existing terminal curbside, check-in/ticketing, security screening<br />

checkpoint, holdrooms, and baggage claim areas.<br />

Doubled parked vehicles during morning peak<br />

<strong>Terminal</strong> Curbside<br />

Check-in passenger queue overflow<br />

Check-in / Ticketing<br />

Overflow at security checkpoint queue<br />

Security Screening Checkpoint<br />

Passenger seating & staging overflow into circulation corridor<br />

Holdrooms<br />

Check-in overflow at Ticketing Lobby<br />

Check-in / Ticketing<br />

Baggage claim overflow into circulation corridor<br />

Baggage Claim<br />

16<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Ground Transportation Facilities<br />

Overview and Parking<br />

KEY POINTS<br />

• 2,073 spaces are<br />

currently available for<br />

close-in public parking,<br />

divided into short-term<br />

parking and long-term<br />

parking<br />

• 2,185 spaces are<br />

currently available for<br />

remote/economy<br />

parking and are served<br />

by an Airport shuttle<br />

• Employee parking is<br />

provided in a lot north<br />

of the terminal complex<br />

(273 spaces)<br />

• Three off-airport parking<br />

competitors operate<br />

approximately 800<br />

spaces<br />

• Hold areas for taxicabs<br />

(8 spaces) and<br />

limousines (3 spaces)<br />

are provided along the<br />

inbound roadways<br />

Existing ground transportation facilities are shown in Figure 8.<br />

There are four categories of ground transportation facilities :<br />

• Parking – two garages, five surface lots, and hold lots<br />

• Roadways – Cowles Drive and Duck Pond Road<br />

• Curbsides – two pick-up/drop-off areas at terminal<br />

• Rental Cars – close-in lots and a remote service area<br />

Parking<br />

A summary of the available parking facilities are shown in Table<br />

4. Two facilities are available for close-in short-term public<br />

parking (341 spaces). Three facilities, including two parking<br />

garages and their connectors, are available for close-in longterm<br />

public parking (1,732 spaces). Four economy surface lots<br />

are available for public parking (2,185 spaces) and are served<br />

by an Airport shuttle bus. Additionally, three off-airport parking<br />

companies operate approximately 800 spaces for public<br />

parking. A 273 space lot, north of the terminal complex, is<br />

provided for employee parking. Lastly, separate hold areas<br />

along the inbound roadways are reserved for taxicabs queuing<br />

(8 spaces) and limousines waiting for passengers (3 spaces).<br />

Table 4<br />

Overview of Parking Facilities<br />

Des Moines International Airport<br />

Short-Term Parking Spaces<br />

North Garage Level 1 243<br />

Short-Term Surface Lot 98<br />

Total 341<br />

Long-Term Parking Spaces<br />

North Garage Levels 2-4 699<br />

Long-Term Surface Lot 280<br />

South Garage Lvls 1-4* 675<br />

Garage Connectors 78<br />

Total 1,732<br />

*The majority of Level 1 of the<br />

South Garage is dedicated to<br />

rental cars, with 18 spaces<br />

dedicated to public parking<br />

Economy Parking Spaces<br />

Lot #1 848<br />

Lot #2 658<br />

Lot #3 379<br />

Lot #4 300<br />

Total 2,185<br />

Employee Parking Spaces<br />

Total 273<br />

Off-Airport Parking Spaces<br />

Keck Lot 500<br />

Jet Parking 150<br />

1st Class Lot 150<br />

Total 800<br />

Figure 8<br />

Ground Transportation Facilities Overview<br />

Des Moines International Airport<br />

17<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Ground Transportation Facilities and Conditions<br />

Roadways<br />

KEY POINTS<br />

• <strong>Terminal</strong> access is via<br />

Cowles Drive<br />

• Access to Cowles drive is<br />

primarily via Fleur Drive<br />

and secondary access is<br />

via Duck Pond Road<br />

• The existing roadways<br />

do not have capacity<br />

constraints, however,<br />

there are a variety of<br />

operational and safety<br />

concerns:<br />

— Two Lane Roads<br />

— Intersections<br />

— Decision Distances<br />

— Two-Way Decision<br />

Points<br />

— Channelization<br />

— Prioritized Access<br />

Route<br />

The roadway network for the terminal complex is shown in Figure 9. The<br />

passenger terminal is accessed via a roadway loop, Cowles Drive, accessed<br />

primarily via Fleur Drive, a major north-south arterial. There are two<br />

entrances , a channelized right turn and an un-signalized left turn off Fleur<br />

Drive. The Airport exit intersection with Fleur Drive is signalized.<br />

Secondary access to Cowles Drive is provided via Duck Pond Road, which<br />

parallels Fleur Drive from McKinley Drive on the north to Army Post Road<br />

on the South. To the South, the road becomes South Frontage road, wraps<br />

around the Runway 31 threshold, and provides access to Economy Lot #4<br />

and the Rental Car QTA. On the north side, the road wraps around the<br />

Runway 23 threshold and provides access to the general aviation complex.<br />

Cowles Drive does not have any capacity constraints. However, several<br />

airport roadway planning, operational, and safety considerations are<br />

discussed below. These issues are also identified in Figure 9.<br />

Maintain two lanes on inbound/outbound roadways – Primary access<br />

roadways should be at least two-lanes wide to avoid a single point of<br />

failure due to a traffic incident or similar event.<br />

Avoid intersections in final vehicular approach and exit – Drivers at<br />

airports are often unfamiliar with the roadways and can be distracted.<br />

Intersections on the Airport’s primary access road become safety hazards<br />

and congestion points. Cowles Drive has two intersections.<br />

Provide appropriate distances between ‘decision points’ – Airports should<br />

be particularly careful to provide appropriate distances between decision<br />

points. Short decision distances become safety hazards and congestion<br />

points. At three locations within the Cowles Drive loop, decision distances<br />

are sub-standard.<br />

Decision points should be limited to two options/routes – Decision points<br />

should be limited to two-way decisions, where drivers only choose<br />

between two options/routes. After the curbsides on Cowles Drive, there is<br />

a four-way decision point between two rental car lots, Economy Lot #3,<br />

and the main exit route.<br />

Create well defined channelization from toll booths and merges – At toll<br />

plazas and merging lanes there should be a well defined channelization.<br />

The existing public parking exit plaza has six lanes simultaneously merging<br />

into a single lane at Cowles Drive.<br />

Prioritize access route – Airport entrances should have prioritized access.<br />

The northbound entrance to the Airport does not have a signal; entering<br />

traffic must continually yield to southbound traffic on the busy Fleur Drive.<br />

Figure 9<br />

Airport Roadway Operational Issues<br />

Des Moines International Airport<br />

18<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Ground Transportation Facilities and Conditions<br />

Curbsides<br />

KEY POINTS<br />

• The inner curbside is 545<br />

linear feet and is<br />

dedicated to private<br />

vehicles<br />

• The outer curbside is<br />

571 linear feet and is<br />

allocated for use among<br />

commercial vehicles<br />

• Vehicular traffic counts<br />

were collected in April<br />

2013 and serve as the<br />

basis for traffic analysis<br />

in the study<br />

There are two curbsides running parallel to the face of the<br />

terminal building. Their allocation is shown in Figure 10:<br />

Inner Curbside is dedicated to use by private (non-commercial)<br />

vehicles. The length of the inner curbside is 545 linear feet.<br />

The front half of the curbside runs parallel to the ticketing<br />

lobby, and as such, is typically used for drop-offs. The second<br />

half of the inner curbside runs parallel to the baggage claim<br />

hall, and as such, is typically used for pick-ups.<br />

Outer Curbside is used for commercial vehicle drop-off and<br />

pickup. It is used by charter buses, taxi cabs, limousines,<br />

courtesy (hotel off-airport parking) shuttles, and the Airport<br />

parking shuttle. The total length of the outer curbside is 571<br />

linear feet. The outer curbside is accessed to/from the<br />

terminal building via four crosswalks.<br />

Traffic Volumes are shown in Table 5. This data was collected<br />

in April 2013. The Inner and Outer curbsides are analyzed<br />

separately. The peak daily volume was 692 vehicles for the<br />

inner curbside (Sunday) and 684 vehicles for the outer<br />

curbside (Monday).<br />

Hotel Van/<br />

Off Airport Airport<br />

Daily Commercial Daily Private<br />

Day Taxi<br />

Limo<br />

Other<br />

Shuttle<br />

Parking Shuttle Shuttle<br />

Vehicle Total Total<br />

Mon 262 139 16 79 177 11 684 571<br />

Tues 189 168 11 77 171 11 627 489<br />

Wed 186 156 27 90 171 4 634 527<br />

Thu 214 146 13 80 177 10 640 626<br />

Fri 228 154 4 68 172 9 635 626<br />

Sat 135 122 7 70 161 9 504 477<br />

Sun 194 113 14 78 169 8 576 692<br />

TOTAL 1,408 998 92 542 1,198 62 4,300 4,008<br />

Avg. per Day 201 143 13 77 171 9 614 573<br />

Source: Des Moines International Airport, April 2013<br />

Table 5<br />

Vehicle Traffic Counts<br />

Des Moines International Airport<br />

Figure 10<br />

Curbside Allocation<br />

Des Moines International Airport<br />

Source: Des Moines International Airport, 2013<br />

19<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Ground Transportation Facilities<br />

Rental Cars<br />

KEY POINTS<br />

• Rental car facilities are<br />

divided into three<br />

distinct components:<br />

(A) customer service<br />

area, (B) ready-return<br />

facilities, and (C) the<br />

quick-turnaround (QTA)<br />

facility<br />

• Seven rental car brands<br />

are currently located on-<br />

Airport<br />

• The existing customer<br />

service area is 3,345 sq.<br />

ft. in the passenger<br />

terminal<br />

• There are three parking<br />

lots used for readyreturn<br />

in the terminal<br />

complex, providing 370<br />

standard parking spaces<br />

• The QTA is 4 acres and<br />

includes wash bays, light<br />

maintenance bays, fuel<br />

pumps, and stacking /<br />

storage space<br />

• 700 spaces in Economy<br />

Lot #4 are leased to the<br />

rental car companies to<br />

supplement their<br />

stacking / storage needs<br />

The rental car operation can be divided into three primary components: (A) customer service<br />

area, (B) ready-return spaces, and (C) the quick-turnaround (QTA) facility. While each of the<br />

facilities is evaluated separately, the facilities operate in unison and the demand/capacity on one<br />

facility can greatly impact the demand/capacity of its counterparts.<br />

There are currently seven rental car brands located on-Airport. Hertz, Enterprise, and National-<br />

Alamo control nearly 70% of the market between them. Dollar-Thrifty, Avis, Advantage, and<br />

Budget make up the remaining 30% of the market (ordered from largest market share to lowest).<br />

Customer Service <strong>Area</strong><br />

The rental car customer service area is located in the terminal building, adjacent to the baggage<br />

claim carousels. The three largest brands (by revenue market share) lease 400 square feet suites<br />

while the four smaller brands lease 290 square feet suites. The suites are comprised of a<br />

ticketing counter area and a back office. A queuing area is provided for each suite. The total<br />

area in the terminal building designated to the rental car customer service function is 3,345<br />

square feet.<br />

Ready-Return Facilities<br />

Ready stalls are where vehicles are parked to await pick-up by a customer. Ready stalls are<br />

designed similar to public parking stalls. Return stalls are where customers return their vehicles.<br />

The Airport has three ready-return facilities, which are shown in Figure 11. Rental Lot #1 (104<br />

spaces) is adjacent to the south side of the terminal. Rental Lot #2 (98 spaces) is immediately<br />

south of the South Garage. Level 1 of the South Garage (168 spaces) is also leased to the rental<br />

cars. There are a total of 370 standard parking stalls leased to the rental car companies.<br />

Quick-Turn Around Facility<br />

The QTA is located approximately ½ mile south of the passenger terminal complex. The QTA<br />

contains five car wash bays, seven light maintenance bays, 20 fuel pumps, and approximately<br />

95,000 sq. ft. of stacking and storage space (see Figure 12). Each brand is assigned a light service<br />

bay. The car washes and fuel pumps are common-use facilities. The stacking/storage space is<br />

allocated in accordance with revenue market share. Combined, the QTA complex is<br />

approximately four acres.<br />

The new Economy Lot #4 is adjacent to the QTA. Currently, the rental car companies lease 700 of<br />

the 1,000 spaces in the lot. For storage, the brands stack vehicles nose-to-tail, allowing for the<br />

storage of more than 1,100 vehicles in this area.<br />

Figure 11<br />

Existing Rental Car Ready-Return Facilities<br />

Des Moines International Airport<br />

Figure 12<br />

Existing Rental Car Quick-Turn Around Facility<br />

Des Moines International Airport<br />

20<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Air Cargo Facilities<br />

Main Cargo <strong>Area</strong> in South Quadrant<br />

The Airport currently operates a split air cargo operation. On<br />

the east quadrant (see Figure 4), and located to the south of<br />

the existing passenger terminal are the original air cargo<br />

facilities including belly cargo. The remaining air cargo<br />

operations are located in the south air cargo area, to the south<br />

of the runway intersection, shown on Figure 13.<br />

Table 6 tabulates facility data, including building number,<br />

descriptions and building square footage for air cargo and other<br />

airport facilities.<br />

Airport<br />

Building<br />

Number<br />

South Cargo <strong>Area</strong><br />

The existing air cargo apron occupies approximately 43 acres<br />

of pavement area. Two major all-cargo carriers, (UPS) and<br />

FedEx, operate out of this facility. UPS currently operates out<br />

of buildings 31 and 32 with their sorting facility in Building 35.<br />

FedEx handles its express freight service and air mail through<br />

an exclusive contract with the United States Postal Service.<br />

Table 6<br />

Existing South Quadrant Facilities<br />

Des Moines International Airport Figure 13<br />

Building Description<br />

Sources: 2011 Airport Layout <strong>Plan</strong>, Foth Infrastructure & Environment.<br />

2007 Master <strong>Plan</strong> report.<br />

Building <strong>Area</strong><br />

(square feet)<br />

28 Consolidated Rental Car Facility 19,700<br />

29 Aircraft Maintenance Building 79,250<br />

30 ALSF Substation Building 1,630<br />

31 South Cargo Building 12,300<br />

32 South Cargo Building 28,000<br />

33 Small Office / Hangar 9,720<br />

34 Multi Tenant Hangar 16,250<br />

35 Cargo Air Sort & Office Building (UPS) 27,350<br />

36 South Executive "T" Hangar 12,150<br />

37 South GA "T" Hangar 21,000<br />

38 South GA Pilot <strong>Plan</strong>ning Building 150<br />

39 South GA "T" Hangar 21,000<br />

40 South GA Corporate Hangar 7,800<br />

43 Airport Sand/Salt Storage Facility 10,430<br />

44 Airport Snow Equipment Storage Building 23,250<br />

45 Fuel Farm Facility<br />

46 Aircraft Maintenance Building 15,900<br />

46A Pole Barn (Temporary) 1,640<br />

46B Pole Barn Sand Storage (Temporary) 7,180<br />

46C Pole Barn (Temporary) 4,600<br />

46D Garage (Temporary) 1,250<br />

47 Field Maintenance Storage Building 17,530<br />

49 Airport South IDF Building 270<br />

50 Ag / Chemical Storage Building 390<br />

51 Airport Carpentry Shop 1,340<br />

52 Storm Water Control Building 65<br />

53 Deicer / Water Metering Building 65<br />

54 UPS Deicer Building 130<br />

East Cargo <strong>Area</strong><br />

South Quadrant Overview<br />

Des Moines International Airport<br />

The east cargo apron area is approximately 8 acres, located<br />

directly south of the existing passenger terminal complex, as<br />

shown on Figure 4. United Airlines currently leases a portion of<br />

Building 5 to handle their belly cargo operation. The Federal<br />

Inspection Facility occupies Building 2. Its primary function is to<br />

perform inspections on cargo merchandises. No international<br />

commercial passenger screening is currently performed.<br />

21<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


General Aviation and Support Facilities<br />

General Aviation Spread Out Over Three Quadrants<br />

General aviation (GA) facilities are spread out across three<br />

different quadrants on the Airport. Figure 14 and Table 7<br />

shows data and facilities located in the north quadrant. Figure<br />

4 shows general aviation facilities located in the east quadrant,<br />

and Figure 13 shows hangar facilities in the south quadrant.<br />

North Quadrant<br />

The biggest GA tenant on the north quadrant, located<br />

northwest of Runway 23, is Elliott Aviation. Elliott operates<br />

several commercial hangars with adjoining office spaces within<br />

the central complex. It occupies approximately nine acres of<br />

ramp area.<br />

Meredith Corporation, Principal Financial, and Mid America Jet<br />

Center also occupy a portion of the general aviation facilities<br />

located east of Elliott Aviation.<br />

To the west of Elliott Aviation is the Federal Aviation<br />

Administration’s (FAA) Airport Traffic Control Tower (ATCT),<br />

accessible from McKinley Avenue. On the north side of<br />

McKinley Avenue is the FAA Airway Facility Sector Office. The<br />

Aircraft Rescue and Fire Fighting (ARFF) facility is located south<br />

of Elliott Aviation.<br />

Table 7<br />

Existing North Quadrant Facilities<br />

Des Moines International Airport<br />

East Quadrant<br />

North of the existing passenger terminal complex are FBOs<br />

Signature Flight Support, and Des Moines Flying Services.<br />

Cowles Drive, the main terminal access roadway, serves as the<br />

public access ways to these tenants.<br />

Figure 14<br />

North Quadrant Overview<br />

Des Moines International Airport<br />

South Quadrant<br />

Located to the west of the UPS sorting facility (Building 35) are<br />

aircraft storage facilities. There are currently two 21,000 square<br />

feet T-hangars (Buildings 37 & 39), one 7,800 square feet<br />

corporate hangar (Building 40), and one 12,150 square feet<br />

executive hangar, served by a surface parking lot, accessible via<br />

South West 28 th Street.<br />

Airport<br />

Building<br />

Number<br />

Building Description<br />

Building<br />

<strong>Area</strong><br />

(square feet)<br />

60 Principal Hangar 19,650<br />

61 Airport North IDF Building 300<br />

62 Meredith Flight Center 22,700<br />

63 Airport Surveillance Radar (FAA Radar Tower) 1,920<br />

64 Jet Center Hangar 22,500<br />

65 Des Moines Schools Aviation Lab 14,400<br />

66 Elliott Flying Service Executive Hangar 32,500<br />

67 Elliott Flying Service FBO Hangars 23,310<br />

69 Elliott Flying Service Hangar 24,200<br />

70 Aircraft Rescue Fire Fighting Facility (ARFF) 15,000<br />

71 Elliott Aviation 37,170<br />

72 FAA Airway Facility Sector 10,200<br />

73 FAA Airport Traffic Control Tower 7,600<br />

Sources: 2011 Airport Layout <strong>Plan</strong>, Foth Infrastructure & Environment .<br />

2007 Master <strong>Plan</strong> report.<br />

22<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Existing Iowa Air National Guard (IANG) Facilities<br />

The Iowa Air National Guard’s Mission Changed in 2013<br />

KEY POINTS<br />

• Facilities needed to<br />

support the previous<br />

F-16 mission are being<br />

re-examined by the<br />

Airport and Department<br />

of Defense<br />

Airport Building<br />

Number<br />

Table 8<br />

Existing Iowa Air National Guard Facilities<br />

Des Moines International Airport<br />

Building Description<br />

100 Iowa Air National Guard Administration Building<br />

101 IANG Supply<br />

102 IANG Main Gate House<br />

103 IANG Supply<br />

105 IANG Vehicle Transportation<br />

110 IANG Facility<br />

124 IANG Squadron Operations<br />

125 IANG A/C Fuel Systems Maintenance<br />

132 IANG Civil Engineering<br />

160 IANG Propulsion Shop<br />

180 IANG Avionics Element<br />

228 IANG Engine Test Pad<br />

229 IANG Test Cell and Propulsion Storage<br />

231 IANG Disaster Preparedness<br />

240 Unknown<br />

251 IANG LIN<br />

252 IANG LOX<br />

270 IANG POL OPS Facility<br />

272 IANG Vehicle Check Point<br />

274 IANG LOX Maintenance<br />

276 IANG Jet Fuel Pumphouse<br />

277 IANG Jet Fuel Pump #1<br />

278 IANG Jet Fuel Pump #2<br />

302 IANG North Gatehouse<br />

310 IANG Security Police Storage<br />

312 IANG Security Police Storage<br />

313 IANG Security / Storage Corrosion Control<br />

314 IANG AGE Shop<br />

315 IANG A/C Corrosion Control<br />

316 IANG Heating <strong>Plan</strong>t Building<br />

319 IANG Pump House for Fire Suppression<br />

320 IANG Munitions Administration & Trailer Maintenance<br />

322 IANG Munitions Maintenance & Inspection<br />

324 IANG Munitions Maintenance<br />

326 IANG Munitions Seg. Magazine Storage<br />

410 IANG Civil Engineering<br />

430 IANG Base Supply<br />

440 IANG Vehicle Maintenance / AGE<br />

Source: 2011 Airport Layout <strong>Plan</strong>, Foth Infrastructure & Environment .<br />

Iowa Air National Guard<br />

The 132 nd Tactical Fighter Wing of the Iowa Air National Guard<br />

(IANG) currently leases approximately 170 acres of airport<br />

property on the north side of the Airport. Their mission<br />

changed in 2013 from F-16 jets to drone operation.<br />

Figure 15<br />

Iowa Air National Guard (IANG) Overview<br />

Des Moines International Airport<br />

The Airport is currently discussing with the IANG which facilities<br />

they will need moving forward, to support their mission.<br />

Figure 15 below and Table 8 to the left indicates land and<br />

facilities that are currently leased to the IANG.<br />

23<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


AVIATION DEMAND FORECAST<br />

• Forecast Approach<br />

• Forecast Summary<br />

• Economic Basis for Airline Traffic<br />

• Historical Aviation Activity<br />

• Aviation Activity Forecasts


Aviation Demand Forecast<br />

Forecast Approach – Summary<br />

KEY POINTS<br />

• Passenger forecasts<br />

were developed using a<br />

variety of analytical<br />

tools to address key<br />

components of aviation<br />

activity.<br />

• Air cargo forecast were<br />

developed based on<br />

recent trends and key<br />

components of air cargo<br />

activity.<br />

• Developed forecasts are<br />

“unconstrained”, i.e., do<br />

not include specific<br />

assumptions of<br />

impediments to aviation<br />

activity growth.<br />

Forecast Approach<br />

• Passenger forecasts were developed using a variety of analytical tools, including trend analysis,<br />

regression models, and market share analysis, to address the key components of aviation activity (i.e.<br />

mainline and regional affiliate, originating and connecting passengers). In addition, recent trends in<br />

airline services in the Des Moines Metropolitan Statistical <strong>Area</strong> (MSA), particularly for low cost carrier<br />

services, were considered in the preparation of the passenger forecast.<br />

• As shown in Figure 16, the forecast approach incorporated a multi-tiered approach to evaluate<br />

passenger traffic in the Des Moines MSA. It was recognized that no one approach would provide input<br />

on all of the key factors that affect passenger and cargo activity in the Des Moines MSA. For example, an<br />

econometric analysis would provide input on the relationships between historical passengers and<br />

regional economic conditions but little to no input on such factors as (1) the role of individual markets in<br />

airline scheduling and service decisions, (2) recent trends in the airline industry that have affected an<br />

airline’s decisions in route planning and aircraft acquisition, and (3) new service development at the<br />

Airport. Input on these factors is important to the development of reliable forecasts that can serve as<br />

the basis for planning efforts at the Airport.<br />

• The air cargo forecasts were developed based on a review of the recent trends, an evaluation of key<br />

components of air cargo activity (i.e. enplaned and deplaned cargo [ freight and mail] for all-cargo and<br />

passenger airlines).<br />

• The aircraft operations forecast were derived from the forecasts of passenger and cargo activity for the<br />

Airport. Forecasts of aircraft operations were developed by (1) disaggregating the total demand into the<br />

components (i.e. mainline and regional affiliate) and (2) making assumptions about average aircraft size<br />

in terms of seats per departure and average enplaned passenger load factors (percentage of seats<br />

occupied, on average) for future years. In addition, the future aircraft fleet plans of the airlines serving<br />

<strong>DSM</strong> were also considered based on available information.<br />

• The forecasts are “unconstrained” and, therefore, do not include specific assumptions about physical,<br />

regulatory, environmental, or other impediments to aviation activity growth.<br />

Figure 16<br />

Multi-Tiered Forecast Approach<br />

Des Moines International Airport<br />

25<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Forecast Approach – Air Service Region<br />

KEY POINTS<br />

• Future airline traffic<br />

trends at the Airport<br />

were based on statistics<br />

for the Des Moines<br />

MSA.<br />

• <strong>DSM</strong>’s overall catchment<br />

area is estimated to<br />

include 2.7 million<br />

people, averaging 0.59<br />

passengers trips per<br />

person in 2012.<br />

• As shown on Figure 17, a 50-mile radius centered at the Airport encircles the Des Moines<br />

MSA consisting of Polk, Dallas, Warren, Des Moines and Guthrie counties in Iowa. Because<br />

economic growth and activity within this area stimulate a significant portion of passenger<br />

demand at the Airport, statistics for the Des Moines MSA were used to evaluate certain<br />

long-term and future airline traffic trends at the Airport.<br />

• The secondary area served by the Airport, which includes many of the counties<br />

surrounding the Des Moines MSA, is defined by the location of and driving distance to<br />

other air carrier airports, as well as by the availability, price, and quality of airline service at<br />

those other airports. The overall catchment area for the Airport, as shown by the reddashed<br />

line on Figure 17, is defined by the Omaha International Airport, the northwest<br />

boundary of Highway 71, the Mason City Municipal Airport, Dubuque Regional Airport,<br />

and Kirksville Regional Airport.<br />

• <strong>DSM</strong>’s overall catchment area is estimated to include 2.7 million people (see Table 9). In<br />

2012, a total of 1.6 million passengers were enplaned at the airports in the <strong>DSM</strong>’s overall<br />

catchment area, average 0.59 passengers trips per person in 2012.<br />

Figure 17<br />

Airports Service Region<br />

Des Moines International Airport – September 2013<br />

Table 9<br />

Enplaned Passengers at Commercial Service Airports in <strong>DSM</strong> Catchment <strong>Area</strong><br />

26<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Economic Basis for Airline Traffic – Historical and Forecast Economic Activity<br />

KEY POINTS<br />

• Economic activity in the<br />

Des Moines MSA is<br />

directly linked to the<br />

production of goods and<br />

services in the world,<br />

State, and nation. Both<br />

airline travel and the<br />

movement of cargo<br />

through the Airport<br />

depend on the economic<br />

linkages between and<br />

among the regional,<br />

national, and<br />

international<br />

economies. The Des<br />

Moines MSA is a major<br />

business and<br />

government center in<br />

Iowa.<br />

Figure 18<br />

Trends in Nonagricultural Employment<br />

Figure 19<br />

Non-agricultural Employment<br />

Figure 20<br />

Monthly Unemployment Trends<br />

Population The population of the Des Moines MSA<br />

increased an average of 1.5% per year between 1990 and<br />

2000 and 1.7% per year between 2000 and 2012, faster than<br />

population growth for the State and nation. Population in<br />

the Des Moines MSA is projected by Woods & Poole to<br />

increase an average of 1.1% per year between 2012 and<br />

2032, faster than growth forecast for the State (an average<br />

increase of 0.4% per year) and the nation (an average<br />

increase of 1.0% per year) during the same period.<br />

Nonagricultural Employment Since 1990, nonagricultural<br />

employment in the Des Moines MSA increased at average<br />

annual growth rates higher than those for the State and<br />

nation, as shown on Figure 18. Nonagricultural employment<br />

in the Des Moines MSA expanded during the 1990s,<br />

increasing an average of 2.2% per year between 1990 and<br />

2000, compared with slower growth between 2000 and<br />

2012 (an average of 0.9% per year). During the most recent<br />

recession, nonagricultural employment in the Des Moines<br />

MSA was less affected than in the State and the nation as a<br />

whole. In 2012, nonagricultural employment in the Des<br />

Moines MSA increased 2.2%, faster than that for the State<br />

(1.5%), and the nation (1.7%). Nonagricultural employment<br />

in the Des Moines MSA and the nation is projected by<br />

Woods & Poole to increase an average of 1.5% per year<br />

between 2012 and 2032, faster than growth forecast for the<br />

State (an average increase of 1.0% per year) and the nation<br />

(an average increase of 1.3% per year) during this period.<br />

Per Capita Personal Income From 2000 to 2011 (the most<br />

recent year for which data are available), per capita personal<br />

income (in 2005 constant dollars) in the Des Moines MSA<br />

increased an average of 0.6% per year, following strong<br />

growth between 1990 and 2000 (an average increase of<br />

1.7% per year), as shown in Table A-2 in the Appendix. In<br />

2011, the Des Moines MSA’s per capita personal income<br />

was 9.3% and 8.2% higher, respectively, than that for the<br />

State and the nation. Per capita personal income in the Des<br />

Moines MSA is projected by Woods & Poole to increase an<br />

average of 1.4% per year between 2011 and 2032.<br />

Nonagricultural Employment by Industry Sector<br />

Figure 19 shows a comparative distribution of<br />

nonagricultural employment by industry sector for the<br />

Des Moines MSA in 2000 and in 2012, and for the State<br />

and the nation in 2012. Employment in services<br />

(53.3%)—including business, education, health, and<br />

other services, such as leisure and hospitality—and<br />

trade (16.7%) accounted for 70.0% of total<br />

nonagricultural employment in the Des Moines MSA in<br />

2012. The government sector accounted for 13.0% of<br />

Des Moines MSA nonagricultural employment in 2012,<br />

reflecting the role of Des Moines as the capital of the<br />

State of Iowa.<br />

Unemployment Rates In addition to the employment<br />

trends cited above, the unemployment rate is also<br />

indicative of the general economic climate. Figure 20<br />

shows comparative annual unemployment rates in the<br />

Des Moines MSA, the State, and the nation as a whole<br />

for 2000 through 2012. Unemployment rates in the Des<br />

Moines MSA and the State have historically remained<br />

lower than national rates. In 2012, the unemployment<br />

rate in the Des Moines MSA and the State was 5.3%<br />

and 5.2%, respectively, lower than that for the nation<br />

(8.1%).<br />

Since the end of the current recession in June 2009,<br />

monthly unemployment rates in the Des Moines MSA,<br />

the State, and the United States have generally<br />

decreased, with month to month variations, as shown<br />

on Figure 3. In July 2013, the Des Moines MSA<br />

unemployment rate was 4.6%, less than that for the<br />

State (4.7%), and lower than the nation (7.7%).<br />

27<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Economic Basis for Airline Traffic – Industry Clusters and Tourism<br />

KEY POINTS<br />

• The economies of the<br />

Des Moines MSA and<br />

Iowa as a whole are<br />

driven by companies<br />

that export goods and<br />

services nationally and<br />

globally, bringing in new<br />

investment and jobs<br />

that support economic<br />

growth as well as air<br />

service development.<br />

Bioscience<br />

Logistics<br />

Financial Services<br />

Data Centers<br />

Table 10<br />

Greater Des Moines Region<br />

Top 20 Largest Employers in 2013<br />

Industry Clusters<br />

Companies that make up industry clusters, also referred to as the "traded<br />

sector", tend to cluster because they draw competitive advantage from<br />

their proximity to competitors, to a skilled workforce, to specialized<br />

suppliers, and to a shared base of sophisticated knowledge about their<br />

industry.<br />

According to the Greater Des Moines Partnership*, there are four industry<br />

clusters in the Des Moines MSA:<br />

Bioscience. Iowa State University (ISU), located 30 miles north of Des<br />

Moines in Ames, anchors the northern end of the Iowa innovation and<br />

bioeconomy corridor (between Ames and Des Moines). ISU is home to four<br />

major bioscience research centers. In addition to ISU’s research centers,<br />

the National Animal Disease Center located in Ames, Iowa, is the largest<br />

federal animal disease center in the United States. The Center conducts<br />

research to solve animal health and food safety problems faced by<br />

livestock producers and the public.<br />

Logistics. Located at the crossroads of Interstates 80 and 35, Des Moines is<br />

centrally located with easy access to the coasts and borders. Des Moines’<br />

Foreign Trade Zone (#107) is located near Interstate 80 and 35, just a few<br />

miles from the Airport, and provides the facilities for importing, assembling<br />

with other components, repackaging, and exporting without going through<br />

formal customs procedures. The Des Moines MSA is served by Burlington<br />

Northern Santa Fe, Iowa Interstate, Norfolk Southern, and Union Pacific<br />

Railroads and is home to 60 national and regional trucking companies.<br />

Financial Services. According to the Iowa Economic Development<br />

Authority*, the city of Des Moines has the highest concentration of<br />

employment in financial services in the United States. As shown on<br />

Table 10, financial services and insurance companies are among the largest<br />

employers in the Des Moines MSA, including Wells Fargo and Company,<br />

Principal Financial Group, Nationwide/Allied Insurance, Marsh, and Aviva.<br />

Tourism<br />

According to the U.S. Travel Association**, domestic<br />

traveler spending in Iowa totaled $7.6 billion in 2012,<br />

representing an increase of 5.6% from 2011. Polk County,<br />

including the city of Des Moines, led all counties in<br />

domestic traveler expenditures, payroll income and jobs<br />

directly generated by these expenditures in 2012.<br />

Domestic traveler expenditures in Polk County reached<br />

over $1.7 billion in 2012, accounting for 22.8% of the<br />

state total. These expenditures generated $308.9 million<br />

in payroll income and 15,600 jobs for Polk County<br />

residents.<br />

The Iowa Events Center is located in downtown Des<br />

Moines and consists of the Community Choice Credit<br />

Union Convention Center (previously known as the<br />

Veterans Memorial Auditorium), the existing Polk County<br />

Convention Complex, the new Hy‐Vee Hall, and the new<br />

Wells Fargo Arena. In addition, the Iowa State<br />

Fairgrounds, located in eastern Des Moines, hosted more<br />

than 1 million visitors to the annual Iowa State Fair over<br />

an 11‐day period in 2012.<br />

** U.S. Travel Association, “The Economic Impact of Travel on<br />

Iowa Counties, 2012”, A Study Prepared for the Iowa<br />

Economic Development Authority Iowa Tourism Office,<br />

August 2013.<br />

Data Centers. Iowa’s favorable tax environment, low cost of power, and<br />

central geographical location have attracted the data centers for major<br />

corporations such as Google, Facebook, and Microsoft Corporation. In<br />

addition, companies that provide information technology services to<br />

businesses are located in the Des Moines MSA, including EdgeBCC, Vital<br />

support Systems, and Iowa Network Services.<br />

* The Greater Des Moines Partnership is the economic and community<br />

development organization serving the Greater Des Moines metro covering a<br />

eight‐county region (Dallas, Guthrie, Jasper, Madison, Marshall, Polk,<br />

Poweshiek, and Warren).<br />

28<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Economic Basis for Airline Traffic – Economic Outlook<br />

KEY POINTS<br />

• The economic outlook for<br />

the United States, the<br />

State of Iowa, and the<br />

Des Moines MSA forms a<br />

basis for anticipated<br />

growth in airline traffic at<br />

the Airport.<br />

• Factors expected to<br />

contribute to continued<br />

economic growth in the<br />

Des Moines MSA and<br />

associated increases in<br />

airline travel include<br />

(1) diversity in the<br />

economic base, which<br />

lessens its vulnerability<br />

to weaknesses in<br />

particular industry<br />

sectors, (2) growth in the<br />

Des Moines MSA industry<br />

clusters as described<br />

earlier, (3) generally<br />

lower labor and living<br />

costs compared with<br />

those in other similarly<br />

sized cities in the nation<br />

and other metropolitan<br />

areas in the Midwest,<br />

(4) an educated labor<br />

force able to support the<br />

development of<br />

knowledge‐based and<br />

service industries, and<br />

(5) continued<br />

reinvestment to support<br />

the development of<br />

tourism, conventions,<br />

and other businesses.<br />

Global Economy Globalization of the world economy has<br />

created linkages between national economies that relate not<br />

only to trade but also to airline travel. The Des Moines MSA and<br />

the State have strong linkages to the global economy through a<br />

number of industry sectors such as bioscience, financial services,<br />

and information technology. The economic growth of world<br />

regions, in terms of gross domestic product (GDP), is directly<br />

related to the growth in airline travel. Projections of GDP for the<br />

world regions are shown in Table 11. In emerging economies<br />

such as Brazil, India, and China with strong growth in GDP<br />

combined with a growing middle class, the growth in passenger<br />

traffic has been significant. Continued growth in the economies<br />

of the world regions most closely aligned with the Des Moines<br />

MSA economy and airline service at the Airport are expected to<br />

contribute to continued growth in passenger traffic at the<br />

Airport.<br />

U.S. Economy The U.S. economy continues to recover from the<br />

most recent financial crisis and global recession, although the<br />

pace of the recovery remains slow. The consensus among<br />

economists is that downturns following financial crises tend to be<br />

more prolonged than other downturns. In addition, such<br />

recessions raise the level and duration of unemployment, reduce<br />

the number of hours that employees work, and dampen<br />

investment. Continued high unemployment, lower disposable<br />

incomes, and reduced spending by businesses and consumers,<br />

particularly in the near term, have the potential to dampen<br />

growth in the U.S. economy and passenger traffic nationally and<br />

at the Airport.<br />

The Congressional Budget Office (CBO) expects that U.S.<br />

economic growth, as measured by U.S. GDP in constant dollars,<br />

will increase 1.4% in 2013, reflecting an ongoing improvement in<br />

underlying economic factors and increases in federal taxes and<br />

reductions in federal spending that will limit growth. U.S. GDP is<br />

expected to increase 3.0% in 2014 and an average of 3.6% per<br />

year between 2013 and 2018. The CBO projects that the<br />

unemployment rate will average 8.0% in the 2013, decrease to<br />

7.6% in 2014, and decrease to 5.5% in 2018. The CBO’s<br />

projections are influenced to a large extent by fiscal policy<br />

specified by current law which resulted in tax increases and<br />

spending cuts in January 2013. In an alternative scenario, the<br />

CBO projects stronger economic growth (an estimated increase<br />

of 2.9% in U.S. GDP in 2013) if some or all of the fiscal<br />

restrictions are removed.<br />

Iowa Economy According to the Iowa Labor Market and<br />

Workforce Information Division, “the Iowa economy is<br />

expected to gain traction by the second half of 2013.” It is<br />

expected that:<br />

• Iowa’s industry sectors will increase hiring in 2013 due<br />

to a better housing market and increased construction<br />

activity.<br />

• In the next few years, Iowa construction projects<br />

include $900 million in construction at the University<br />

of Iowa, $580 million in construction spending in Cedar<br />

Rapids, mostly on public projects, and $600 million for<br />

highway construction and repairs by the Iowa<br />

Department of Transportation.<br />

• Employment in Iowa’s financial industry should<br />

continue to exceed national growth, reflecting an<br />

educated workforce and significantly lower labor costs<br />

compared to other financial hubs.<br />

• Employment in financial services, information<br />

technology, healthcare, and construction is expected to<br />

increase faster than the State average through 2020.<br />

Des Moines MSA Economy The economic drivers of the<br />

Des Moines MSA are diverse and include mature,<br />

stable, and emerging industries. According to a June<br />

2013 Moody's Analytics report:<br />

"The outlook for Des Moines is bright, and its<br />

economy will strengthen as financial services<br />

accelerate, helping to drive consumer spending.<br />

Construction is on the verge of an upswing. Farm<br />

incomes will grow, although at a slower pace, and<br />

the public sector will provide little support.<br />

Long‐term prospects are upbeat: A diverse industrial<br />

base, favorable business costs, and a skilled<br />

workforce lay the foundation for above‐average<br />

growth over the long run."<br />

Table 11<br />

Historical and Projected GDP Growth by World Region<br />

29<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Aviation Activity Forecast – Passenger Airline Traffic<br />

KEY POINTS<br />

• Forecasts of enplaned<br />

passengers were<br />

developed taking into<br />

account analyses of the<br />

economic basis for<br />

airline traffic, analyses<br />

of historical airline<br />

traffic, and an<br />

assessment of the key<br />

factors that may affect<br />

future airline traffic.<br />

• The number of enplaned<br />

passengers is forecast to<br />

increase from 1,038,484<br />

in 2012 to 2,046,000 in<br />

2032, an average<br />

increase of 3.4% per<br />

year.<br />

Assumptions<br />

• In the long term, changes in airline traffic at the Airport<br />

will occur largely as a function of growth in the<br />

population and economy of the Airport service region<br />

and changes in airline service.<br />

• Continued development of airline service at the Airport<br />

will not be constrained by the availability of aviation fuel,<br />

long‐term limitations in airline fleet capacity, limitations<br />

in the capacity of the air traffic control system or the<br />

Airport, or government policies or actions that restrict<br />

growth.<br />

• Considered recent and potential developments in the<br />

national economy and in the air transportation industry<br />

as they have affected or may affect airline traffic at the<br />

Airport.<br />

For 2013 through 2032, it is assumed that:<br />

• The U.S. economy will recover from the recession and<br />

sustained GDP growth will average between 2.0% and<br />

2.5% per year.<br />

• The economy of the Des Moines MSA would increase at a<br />

rate comparable to that of the nation as a whole.<br />

• A generally stable international political environment<br />

and safety and security precautions will ensure airline<br />

traveler confidence in aviation without imposing<br />

unreasonable inconveniences.<br />

• There would be no major disruption of airline service or<br />

air travel behavior as a result of international hostilities<br />

or terrorist actions.<br />

• Airline scheduling efficiencies and airport operational<br />

procedures would permit accommodation of the<br />

forecast demand.<br />

Enplaned Passenger Forecasts<br />

The number of enplaned passengers is forecast to increase<br />

from 1,038,484 in 2012 to 2,046,000 in 2032, an average<br />

increase of 3.4% per year (see Figure 21 and Table 12).<br />

The forecast of enplaned passengers are based on (1) the<br />

regression analysis and independent forecast of the key<br />

variables, (2) an evaluation of low-cost carrier service<br />

expansion at <strong>DSM</strong>, and (3) an assessment of the <strong>DSM</strong><br />

catchment area and the additional passengers that could<br />

be capture through the forecast period.<br />

Figure 21<br />

Historical and Forecast Enplaned Passengers<br />

Des Moines International Airport<br />

Table 12<br />

Historical and Forecast Enplaned Passengers<br />

Des Moines International Airport<br />

• The Airport will continue to be the principal airport<br />

serving the Des Moines MSA, the overall <strong>DSM</strong> catchment<br />

area, and the State of Iowa.<br />

• Passenger traffic growth at the Airport will continue to be<br />

supported by local businesses with a continued demand<br />

for national and global connectivity.<br />

• Competition among the airlines serving the Airport and<br />

the Des Moines MSA will ensure the continued<br />

availability of competitive airfares.<br />

• The price of oil and aviation fuel would remain at<br />

historically high levels but would not return to the prices<br />

experienced in 2008.<br />

30<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Aviation Activity Forecast – Air Cargo<br />

KEY POINTS<br />

• Regression analysis for<br />

air cargo activity at <strong>DSM</strong><br />

is not meaningful, since<br />

it has been driven more<br />

by the business plans of<br />

all-cargo airlines than<br />

economic activity in the<br />

Des Moines MSA.<br />

• Therefore, it is assumed<br />

that air cargo at the<br />

Airport would increase<br />

at rates comparable to<br />

the growth in the<br />

population of the Des<br />

Moines MSA, an average<br />

increase of 0.8% per<br />

year.<br />

As shown on Figure 22, total air cargo at <strong>DSM</strong> decreased an<br />

average of 4.3% between 1999 and 2012, with growth<br />

occurring between 2004 and 2006 (an average increase of<br />

5.0% per year) and 2010 and 2012 (an average increase of<br />

8.8%).<br />

The decreases in cargo at the Airport since 1999 are<br />

related to:<br />

• The slowdown in the regional economy related to the<br />

economic recessions in 2011 and 2008‐2009.<br />

• A reduction in available belly‐cargo capacity on<br />

passenger airline aircraft as a result of increases in the<br />

use of regional jet aircraft which have less cargo<br />

capacity than larger air carrier aircraft.<br />

• The availability of reduced‐cost belly‐cargo capacity,<br />

particularly on widebody aircraft designed for<br />

containerized cargo, and direct international freighter<br />

service at other gateway airports, such as Chicago<br />

O’Hare, Los Angeles, and Dallas/Fort Worth<br />

international airports.<br />

• An increasing trend among freight forwarders to bypass<br />

airports and truck cargo to gateways that have available<br />

reduced‐cost belly‐cargo capacity.<br />

Figure 22<br />

Historical Trend Analysis – Total Air Cargo<br />

Des Moines International Airport<br />

Table 13<br />

HISTORICAL AND FORECAST AIR CARGO—BASELINE<br />

Des Moines International Airport<br />

The definition of a regression model to represent air<br />

cargo activity at <strong>DSM</strong> is limited by:<br />

• Continued decreases in air cargo since 1999 which do<br />

not relate to traditional economic indicators such as<br />

Des Moines MSA employment or personal income<br />

which have generally increased between 1999 and<br />

2012<br />

• The data series for air cargo does not capture the<br />

entire cargo market including transport by other<br />

modes<br />

As a result of these limitations, a regression analysis was<br />

not meaningful. <strong>DSM</strong> air cargo trends have been driven<br />

more by the business plans of all‐cargo airlines than<br />

economic activity in the Des Moines MSA. The Airport<br />

has served as a second day hub for UPS but, due to less<br />

than expected demand for its second day product, UPS<br />

plans to transition out of its second day product. As a<br />

result, UPS cargo activity at <strong>DSM</strong> is expected to be<br />

limited.<br />

Therefore, it was assumed that air cargo at the Airport<br />

would increase at rates comparable to the growth in the<br />

population of the Des Moines MSA, an average increase<br />

of 0.8% per year, as shown in Table 13.<br />

• The reorganization and consolidation in the cargo<br />

industry in response to the increase in fuel prices in<br />

2008 and the national economic recession.<br />

Note: The forecasts presented in this figure were prepared using the information and<br />

assumptions given in the accompanying text. Inevitably, some of the assumptions<br />

used to develop the forecasts will not be realized and unanticipated events and<br />

circumstances may occur. Therefore, there are likely to be differences between<br />

the forecast and actual results, and those differences may be material.<br />

CAGR = Compound annual growth rate.<br />

Includes air freight and mail.<br />

Sources: Historical: Des Moines International Airport records.<br />

Forecast: LeighFisher, August 2013.<br />

31<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Aviation Activity Forecast – Aircraft Operations<br />

KEY POINTS<br />

• Forecasts of aircraft<br />

operations for passenger<br />

and cargo airlines,<br />

general aviation, and<br />

military activity are<br />

presented.<br />

• Total aircraft operations<br />

are forecast to increase<br />

an average of 0.9% per<br />

year from 80,036<br />

operations in 2012 to<br />

96,100 operations in<br />

2032.<br />

Assumptions<br />

• Forecasts of passenger aircraft operations were derived<br />

from forecasts of passengers using assumptions of (1)<br />

average aircraft size, measured by seats per aircraft<br />

operation, and (2) average aircraft utilization, measured in<br />

percentage terms (the “load factor”)<br />

• Assumptions regarding expected changes in aircraft size<br />

and assumed aircraft utilization together result in the<br />

calculation of the number of passengers per aircraft<br />

operation. The projection of aircraft operations is then<br />

derived by dividing the number of passengers by the ratio<br />

of passengers per aircraft operation. Table 14 summaries<br />

the data and assumptions for 2011 through 2032.<br />

Aircraft Operations Forecast Table 15 and Figure 23<br />

summarize the forecasts of total aircraft operations at the<br />

Airport, including commercial, general aviation, and military<br />

aircraft operations.<br />

Total aircraft operations are forecast to increase an average of<br />

0.9% per year from 80,036 operations in 2012 to 96,100<br />

operations in 2032.<br />

Commercial aircraft operations, including air carrier and air taxi<br />

operations, are forecast to increase from 44,200 operations in<br />

2012 to 60,700 operations in 2032, reflecting an increase in the<br />

average number of seats per operation. In 2032, commercial<br />

aircraft operations are forecast to account for approximately<br />

63% of total Airport operations.<br />

Table 15<br />

Historical and Forecast Aircraft Operations<br />

Des Moines International Airport<br />

• Commercial aircraft<br />

operations, including air<br />

carrier and air taxi<br />

operations, are forecast<br />

to increase from 44,200<br />

operations in 2012 to<br />

60,700 operations in<br />

2032, reflecting an<br />

increase in the average<br />

number of seats per<br />

operation.<br />

Table 14<br />

Passenger Airline Aircraft Operations Forecast Assumptions<br />

Des Moines International Airport<br />

Figure 23<br />

Historical and Forecast Aircraft Operations<br />

Des Moines International Airport<br />

• In 2032, commercial<br />

aircraft operations are<br />

forecast to account for<br />

approximately 63% of<br />

total Airport operations.<br />

32<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Aviation Activity Forecast – Based Aircraft and Aircraft Fleet<br />

KEY POINTS<br />

• Forecasts of based<br />

aircraft at the Airport is<br />

forecast to increase an<br />

average of 0.7% per year<br />

between 2012 and 2032,<br />

consistent with the<br />

growth rates forecast for<br />

the nation as a whole.<br />

• Forecasts of the aircraft<br />

fleet were based on a<br />

2013 base year<br />

distribution of<br />

operations by<br />

equipment type.<br />

Forecasts airline fleet<br />

mix for 2017, 2022,<br />

2027, and 2032 are<br />

presented.<br />

Based Aircraft Forecasts<br />

As shown on Table 16, the number of based aircraft at the<br />

Airport is forecast to increase average of 0.7% per year<br />

between 2012 and 2032, consistent with the growth rates<br />

forecast for the nation as a whole. In the FAA 2012 TAF for the<br />

Airport, the number of based aircraft is forecast to remain<br />

unchanged through 2032.<br />

Table 16<br />

Based Aircraft Forecasts<br />

Des Moines International Airport<br />

Based Aircraft Forecasts<br />

The forecasts of the aircraft fleet were based on a 2013<br />

base year distribution of operations by equipment type<br />

(e.g., Airbus 319, Boeing 737‐800).<br />

The 2013 distribution was developed using a combination<br />

of source data, including: published passenger airline<br />

Table 17<br />

Aircraft Fleet Mix<br />

Des Moines International Airport<br />

schedules; <strong>DSM</strong> airport records, and the FAA’s databases<br />

including the Enhanced Traffic Management System<br />

Counts (ETMSC), Operations Network (OPSNET), and Air<br />

Traffic Activity Data System (ATADS). Historical and<br />

projected distributions are presented in Table 17.<br />

33<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Aviation Demand Forecast<br />

Aviation Activity Forecast – Comparison with the FAA 2012 TAF<br />

KEY POINTS<br />

• The forecasts are<br />

compared for the<br />

components of total<br />

enplaned passengers,<br />

commercial aircraft<br />

operations, and total<br />

aircraft operations.<br />

• Forecast of enplaned<br />

passengers for <strong>DSM</strong> is<br />

higher than the TAF in<br />

2017 and 2022. The<br />

variance between the<br />

<strong>DSM</strong> enplaned<br />

passenger forecast and<br />

the FAA 2012 TAF is<br />

15.2% in 2017 and<br />

26.8% in 2022.<br />

Table 18<br />

FAA TAF Forecast Comparison<br />

Des Moines International Airport (2012 – 2027)<br />

The <strong>DSM</strong> planning forecasts are outside of the allowed<br />

variance* from the FAA 2012 TAF for the following<br />

reasons:<br />

• Economic and business trends in the Des Moines MSA<br />

discussed in Chapter 2, “Economic Basis for Airline<br />

Traffic” as well as recent traffic trends at <strong>DSM</strong> reflecting<br />

the expansion of low cost carrier service suggest that<br />

<strong>DSM</strong> passenger traffic will increase at a rate faster than<br />

forecast in the FAA 2012 TAF for <strong>DSM</strong> (an average of<br />

1.5% per year) and for the airports in the <strong>DSM</strong><br />

catchment area and adjacent region (an average of 2.4%<br />

per year), as shown in Figure 24.<br />

• Historically, <strong>DSM</strong> has accounted for nearly 30% of<br />

passengers enplaned at the regional airports shown in<br />

Figure 7‐1. In the <strong>DSM</strong> planning forecasts, it is assumed<br />

that <strong>DSM</strong> will increase gradually to 32% during the<br />

forecast period. In the FAA 2012 TAF, <strong>DSM</strong> accounts for a<br />

decreasing share of the passengers enplaned at the<br />

regional airports, as shown in Figure 25.<br />

Figure 24<br />

FAA 2012 TAF for <strong>DSM</strong> Catchment <strong>Area</strong> Airports and<br />

Adjacent Airports (1990-2032)<br />

Figure 25<br />

<strong>DSM</strong> Forecast Share of Regional Enplaned<br />

Passengers (1990-2032)<br />

• Forecast of commercial<br />

operations for <strong>DSM</strong> is<br />

lower than the TAF in<br />

2017 and 2022. The<br />

variance between the<br />

<strong>DSM</strong> commercial<br />

operations forecast and<br />

the FAA 2012 TAF is<br />

12.5% in 2017 and<br />

13.3% in 2022.<br />

• Forecast of total aircraft<br />

operations for <strong>DSM</strong> is<br />

lower than the TAF in<br />

2017 and 2022. The<br />

variance between the<br />

<strong>DSM</strong> total aircraft<br />

operations forecast and<br />

the FAA 2012 TAF is<br />

10.7% in 2017 and<br />

11.1% in 2022.<br />

Table 18 presents a comparison of the aviation activity<br />

forecasts prepared for <strong>DSM</strong> and the FAA 2012 TAF for the<br />

Airport. The forecasts are compared for the components of<br />

total enplaned passengers, commercial aircraft operations and<br />

total aircraft operations. The format of Table 18 is based on<br />

the template provided by the FAA for the comparison of<br />

airport planning forecasts and the FAA TAF. As required, the<br />

results are presented for the base year of 2012 and forecast<br />

horizons years which are equal to the base year, plus 1, 5, 10<br />

and 15 years (2013, 2017, 2022, and 2027).<br />

• In recent years, the number of passengers per<br />

commercial operation has increased at <strong>DSM</strong> as airlines<br />

replace 50‐seat regional aircraft with more fuel efficient<br />

larger aircraft. In the <strong>DSM</strong> planning forecasts, it is<br />

assumed that the number of passengers per commercial<br />

operation will increase an average of 1.5% per year,<br />

reflecting upgauging in airline fleets. In the FAA 2012<br />

TAF, the number of passengers per commercial<br />

operation is forecast to decrease an average of 0.7% per<br />

year, as shown in Figure 26.<br />

* As stipulated in the FAA forecast guidance, the planning<br />

forecasts must “differ by less than 10 percent in the 5‐year<br />

forecast period, and 15 percent in the 10‐year forecast<br />

period”.<br />

Figure 26<br />

Historical & Forecast Passengers per Commercial Operation<br />

Des Moines International Airport<br />

34<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


DEMAND/CAPACITY AND FACILITY REQUIREMENTS ANALYSES<br />

• Passenger <strong>Terminal</strong> Requirements<br />

• Ground Transportation Requirements<br />

• Airfield Requirements<br />

• Cargo, General Aviation, and Support Facility Requirements


Passenger <strong>Terminal</strong> Requirements<br />

Methodology and key assumptions<br />

KEY POINTS<br />

• For the development of<br />

terminal facility<br />

requirements, the ACRP<br />

terminal requirements<br />

model was used. The<br />

ACRP model evaluates<br />

facility requirements of<br />

major functional areas<br />

based on performance<br />

metrics.<br />

• Facility requirements for<br />

the following areas of<br />

the terminal were<br />

determined:<br />

— Apron gates<br />

— Ticketing / Check-in<br />

— Security checkpoint<br />

— Outbound baggage<br />

screening<br />

— Outbound baggage<br />

make-up<br />

— Concessions<br />

— Holdrooms<br />

— Baggage claim<br />

— Restrooms<br />

— Secondary and other<br />

areas<br />

<strong>Terminal</strong> requirements are driven by forecast aviation demand:<br />

• Based on projected levels of passenger activities at 2.5, 3.0 and 4.0 million annual passengers (MAP)<br />

which is expected to occur around 2018, 2027, and 2042, respectively<br />

• Peak period demand derived from the forecast are used as a basis for sizing the facility requirements.<br />

Number of passengers during the peak hour is shown in Figure 27. Rolling hourly enplaned<br />

passengers are shown on Figure 28.<br />

Development of terminal requirements are based on airport data and industry design standards:<br />

• The industry-standard Airport Cooperative Research Program (ACRP) terminal requirements model<br />

are used to assess the facility requirements for each PAL.<br />

• The ACRP model looks at the major functional areas of both airside and landside terminal operations<br />

to evaluate the facility requirements based on performance metrics such as targeted passenger wait<br />

time and level of service (LOS). Key assumptions were developed from data provided by the Airport,<br />

as well as data collected at other similar U.S. airports.<br />

Level of Service (LOS) is defined as:<br />

• A qualitative and quantitative measurement of comfort experienced by passengers using the airport<br />

terminal facility. The capacity of each element of a terminal facility can vary depending on the level of<br />

crowding and/or processing time that is considered acceptable. <strong>Terminal</strong> should be designed to<br />

maintain a certain LOS, even during the peak periods of the day, typically chosen as the peak hour of<br />

the average day in the peak month (ADPM). The International Air Transport Association (IATA)<br />

delineates level of service into 6 categories:<br />

1,800<br />

1,600<br />

1,400<br />

1,200<br />

1,000<br />

800<br />

600<br />

400<br />

200<br />

-<br />

Figure 27<br />

Number of Passengers During the Peak Hour<br />

2013 2.5 MAP 3.0 MAP 4.0 MAP<br />

Enplaned passengers Deplaned passengers Total passengers<br />

Figure 28<br />

Rolling Hourly Enplaned Passengers (June 3, 2013)<br />

• MAP stands for Million<br />

Annual Passengers, and<br />

includes enplaning and<br />

deplaning passengers.<br />

• LOS C is typically recommended as a design objective since it denotes good service at a<br />

reasonable investment. Therefore, the facilities for <strong>DSM</strong> are planned for LOS C.<br />

• Some factors that influence LOS for terminal planning are :<br />

– Passenger queuing space<br />

– Target maximum wait time<br />

– Linear frontage (e.g. for baggage claim)<br />

36<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Required space (sf)<br />

Count (ea)<br />

Passenger <strong>Terminal</strong> Requirements<br />

Summary of findings<br />

KEY POINTS<br />

• Existing facilities for<br />

ticketing, outbound<br />

baggage screening and<br />

make-up, holdrooms,<br />

and restrooms are<br />

inadequate.<br />

• Other terminal facilities,<br />

e.g. apron gates,<br />

security checkpoint, will<br />

be inadequate to meet<br />

forecast demand<br />

between 2.5 MAP and<br />

3.0 MAP.<br />

Most existing terminal facilities will be inadequate to meet forecast<br />

demand between 2.5 MAP and 3.0 MAP (see Figures 29 and 30):<br />

Figure 29<br />

Existing <strong>Terminal</strong> Stress Chart<br />

Figure 30<br />

Existing <strong>Terminal</strong> Stress <strong>Plan</strong><br />

Primary facilities are sized based on the area required for the<br />

functional components, passenger queuing, circulation, and for nonpassengers<br />

(e.g. employees, meeters and greeters, well-wishers)<br />

where applicable.<br />

Secondary facilities (e.g. airline operations, TSA admin/staff support,<br />

ground handling services, facilities support areas) are sized relative<br />

to the primary facilities requirements, and will be included in sizing<br />

the passenger terminal alternatives.<br />

Total space and unit requirements for each of the primary facilities<br />

are summarized on Figures 31 and 32.<br />

45,000<br />

40,000<br />

35,000<br />

30,000<br />

25,000<br />

Figure 31<br />

Total Space Requirements for Primary Facilities<br />

120<br />

100<br />

80<br />

Figure 32<br />

Total Unit Requirements for Primary Facilities<br />

20,000<br />

60<br />

15,000<br />

40<br />

10,000<br />

5,000<br />

20<br />

0<br />

Ticketing Security Outbound<br />

baggage<br />

screening<br />

Outbound<br />

baggage<br />

make-up<br />

Concessions Holdrooms Baggage<br />

claim<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Restrooms<br />

0<br />

Gates Ticketing positions Security lanes Baggage claim<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Source: LeighFisher, February 2014. Source: LeighFisher, February 2014.<br />

37<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Apron gate<br />

KEY POINTS<br />

• Gate requirements are<br />

based on existing gate<br />

utilization and assumes<br />

the pattern will remain<br />

relatively stable<br />

throughout the planning<br />

period. Changes in<br />

passengers per gate<br />

would be due to changes<br />

in fleet seating capacity<br />

and/or passenger load<br />

factors, rather than the<br />

increasing number of<br />

departures per gate.<br />

• Additional gate would<br />

be required by 2.5 MAP.<br />

Three additional gates<br />

would be needed by 3.0<br />

MAP and seven would<br />

be needed by 4.0 MAP.<br />

1.<br />

Activity Forecasts<br />

Annual enplaned passengers<br />

(millions):<br />

• Baseline: 1.1<br />

• 2.5 MAP: 1.25<br />

• 3.0 MAP: 1.5<br />

• 4.0 MAP: 2.0<br />

Annual passenger aircraft<br />

departures (thousands):<br />

• Baseline: 16.9<br />

• 2.5 MAP: 18.5<br />

• 3.0 MAP: 20.9<br />

• 4.0 MAP: 27.6<br />

2.<br />

Assumptions<br />

Target gate utilization:<br />

4.4 daily departures/gate<br />

(based on 2013 ADPM).<br />

Future gate requirements:<br />

Derived based on forecast<br />

annual enplanements and<br />

departures, assuming the<br />

same gate utilization factor<br />

as it is today.<br />

3.<br />

Existing Facilities<br />

Passenger gates:<br />

• 11 NBEG (Narrow-Body<br />

Equivalent Gates)<br />

• All of which are contact<br />

gates with loading<br />

bridges except Gate A5.<br />

4.<br />

Requirements<br />

Passenger gates:<br />

• Baseline: 11<br />

• 2.5 MAP: 12<br />

• 3.0 MAP: 14<br />

• 4.0 MAP: 18<br />

Based on the terminal requirements model results:<br />

• Additional gate would be required by 2.5 MAP, as<br />

shown below.<br />

Table 19<br />

Narrow-Body Equivalent Gates<br />

Source: ACRP <strong>Report</strong> 25, Airport Passenger <strong>Terminal</strong> <strong>Plan</strong>ning<br />

and Design. Volume 1: Guidebook.<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Apron gate requirements are expressed in terms of the<br />

number of “Narrow-Body Equivalent Gates”:<br />

• Definition of “gate” can vary, this metric is used to<br />

normalize the capacity to that of a typical narrow-body<br />

aircraft gate.<br />

• The amount of space required is based on the maximum<br />

wingspan of aircraft in its respective aircraft group.<br />

• Requirements for different mix of aircraft can be<br />

converted using the factors on Table 19.<br />

38<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Ticketing / Check-in<br />

KEY POINTS<br />

• Facility requirements for<br />

ticketing / airline checkin<br />

were developed for<br />

the number of staffed<br />

positions and space<br />

required.<br />

• Input data includes an<br />

estimate of how early<br />

the passengers arrive at<br />

the airport before their<br />

scheduled flight time, as<br />

well as the number of<br />

enplaned passengers per<br />

airline during the peak<br />

30-minute period.<br />

• Based on LOS C,<br />

requirements analysis<br />

showed that the existing<br />

queuing space is<br />

insufficient and<br />

additional self-service<br />

kiosks would be needed<br />

by 4.0 MAP.<br />

1.<br />

Activity Forecasts<br />

Average Day Peak Month<br />

peak hour enplaning<br />

passengers (total):<br />

• Baseline: 730<br />

• 2.5 MAP: 853<br />

• 3.0 MAP: 1,022<br />

• 4.0 MAP: 1,396<br />

Average Day Peak Month<br />

peak 30-minute enplaned<br />

passengers (2013):<br />

• American: 67<br />

• Delta: 88<br />

• Frontier: 38<br />

• Allegiant: 80<br />

• United: 114<br />

• US: 47<br />

• Southwest: 53<br />

2.<br />

Assumptions<br />

Check-in preferences (%):<br />

• Kiosks 47<br />

• Counters 30<br />

• Curbside 5<br />

• Offsite 18<br />

• Total 100<br />

Target maximum wait times<br />

for counter positions (min):<br />

8-10<br />

Average processing times<br />

(min/pax):<br />

• Kiosks 2.5<br />

• Counters 3.0<br />

• Curbside 2.0<br />

3.<br />

Existing Facilities<br />

Ticketing positions (ea)<br />

• Kiosks 30<br />

• Counters 54<br />

• Bag drops 25<br />

• Curbside 2<br />

• Total 111<br />

• Includes all available<br />

positions (leased and not<br />

leased).<br />

Ticketing area (sf)<br />

• Counters 1,190<br />

• Queue 1,520<br />

• Curbside 390<br />

• Ticket office 2,530<br />

• Circulation 2,250<br />

• Misc* 4,900<br />

• Total 12,780<br />

*Includes oversize bags,<br />

unused counters and bag<br />

belts<br />

4.<br />

Requirements<br />

Ticketing positions (ea)<br />

• Baseline: 49<br />

• 2.5 MAP: 55<br />

• 3.0 MAP: : 66<br />

• 4.0 MAP: 85<br />

Ticketing area (sf)<br />

• Baseline: 6,650<br />

• 2.5 MAP: 7,700<br />

• 3.0 MAP: 8,970<br />

• 4.0 MAP: 11,700<br />

Based on the terminal requirements model results:<br />

• Insufficient queuing space – deficit of 1,400 square feet–<br />

with the existing layout.<br />

• Additional self-service kiosks would be needed by<br />

4.0 MAP, other ticketing counters (agent, bagdrop,<br />

curbside) will be sufficient throughout the planning<br />

period.<br />

• Detailed requirements for ticketing positions and area<br />

are provided below.<br />

120<br />

100<br />

80<br />

60<br />

40<br />

20<br />

0<br />

14,000<br />

2<br />

25<br />

30<br />

54<br />

Ticketing Positions (ea)<br />

1<br />

12<br />

21<br />

1<br />

13<br />

23<br />

1<br />

16<br />

28<br />

15 18 21<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Agent Kiosk Bagdrop Curbside<br />

Ticketing <strong>Area</strong> (sf)<br />

1<br />

20<br />

37<br />

27<br />

12,000<br />

10,000<br />

4,898<br />

2,442<br />

8,000<br />

6,000<br />

4,000<br />

2,000<br />

0<br />

2,251<br />

1,311<br />

2,527 1,725<br />

385<br />

70<br />

1,520 2,912<br />

1,553<br />

1,988<br />

70<br />

3,346<br />

1,827<br />

2,363<br />

3,836<br />

4,984<br />

1,194 636 743 878 1,132<br />

70<br />

3,075<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Counter Queue Curbside<br />

Airline office Circulation Miscellaneous<br />

70<br />

39<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Security checkpoint<br />

KEY POINTS<br />

• A more conservative<br />

throughput of 170<br />

passengers per hour per<br />

lane was assumed to<br />

plan adequately for<br />

future demand.<br />

• Passengers in the<br />

existing conditions are<br />

processed at one of the<br />

six security screening<br />

checkpoints (SSCPs).<br />

The existing<br />

configuration is<br />

sufficient to guarantee<br />

an acceptable level of<br />

service with maximum<br />

wait time of 20 minutes<br />

until 4.0 MAP, when two<br />

additional lanes would<br />

be required.<br />

1.<br />

Activity Forecasts<br />

Average Day Peak Month<br />

peak 30-minute enplaned<br />

passengers:<br />

• Baseline: 393<br />

• 2.5 MAP: 458<br />

• 3.0 MAP : 549<br />

• 4.0 MAP : 751<br />

• Includes 10% crew/<br />

employees that require<br />

screening.<br />

2.<br />

Assumptions<br />

Target maximum wait times<br />

(minutes): 20<br />

Lane throughput<br />

(pax/lane/hour): 170<br />

Queuing space LOS C<br />

requirement (sf/pax): 12.9<br />

Security lane and spatial<br />

requirement derived using<br />

the peak 30-minute<br />

enplaning passengers based<br />

on queuing model satisfying<br />

the targeted maximum wait<br />

times.<br />

3.<br />

Existing Facilities<br />

Security lanes:<br />

• Regular 4<br />

• Overflow 2<br />

• Total 6<br />

Security space (sf)<br />

• Screening 7,820<br />

• Queue 2,590<br />

• Total 10,410<br />

4.<br />

Requirements<br />

Security lanes:<br />

• Baseline 4*<br />

• 2.5 MAP 5*<br />

• 3.0 MAP 6*<br />

• 4.0 MAP 8*<br />

* Does not include dedicated TSA<br />

Pre-check lane<br />

Security space (sf):<br />

• Baseline 9,380<br />

• 2.5 MAP 11,260<br />

• 3.0 MAP 13,490<br />

• 4.0 MAP 18,250<br />

Based on the terminal requirements model results:<br />

• Existing security queuing space is inadequate by LOS C<br />

standard.<br />

• Two additional checkpoint lanes will be needed by<br />

4.0 MAP.<br />

• Detailed requirements for security lanes and area are<br />

provided below.<br />

9<br />

8<br />

7<br />

6<br />

5<br />

4<br />

3<br />

2<br />

1<br />

0<br />

6<br />

Security Lanes (ea)<br />

4<br />

5<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

6<br />

8<br />

• By 2.5 MAP, it is<br />

estimated that the<br />

security checkpoint<br />

space will become<br />

inadequate.<br />

20,000<br />

18,000<br />

16,000<br />

Security <strong>Area</strong> (sf)<br />

2,240<br />

14,000<br />

12,000<br />

10,000<br />

8,000<br />

6,000<br />

4,000<br />

2,000<br />

2,593<br />

7,817<br />

1,120<br />

2,657<br />

5,600<br />

1,400<br />

2,864<br />

7,000<br />

1,680<br />

3,406<br />

8,400<br />

4,812<br />

11,200<br />

0<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Screening Queue Allowance<br />

40<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Outbound baggage screening<br />

KEY POINTS<br />

• Outbound baggage<br />

demand was estimated<br />

based on assumptions of<br />

the number of checked<br />

bags and percentage of<br />

passengers with checked<br />

bags during the peak<br />

hour.<br />

• The peak hour baggage<br />

demand was compared<br />

to the hourly screening<br />

machine throughput to<br />

calculate requirements<br />

for the number of<br />

screening equipment<br />

and space for<br />

equipment and<br />

adequate circulation.<br />

1.<br />

Activity Forecasts<br />

Average Day Peak Month<br />

peak hour bags to process:<br />

• Baseline: 566<br />

• 2.5 MAP: 661<br />

• 3.0 MAP: 792<br />

• 4.0 MAP: 1,082<br />

• 62% of passengers has<br />

checked bags, each with<br />

an average of 1.3 bags.<br />

2.<br />

Assumptions<br />

Screening alarm rates (%):<br />

• Level 1 EDS* 97<br />

• Level 2 OSR 25<br />

• Level 3 ETD 20<br />

* Excludes 3% oversize bags<br />

requiring ETD inspections.<br />

Screening processing rates<br />

(bags/hour):<br />

• Level 1 EDS 250<br />

• Level 2 OSR 120<br />

• Level 3 ETD 24<br />

3.<br />

Existing Facilities<br />

Screening space (sf)<br />

• Sorting matrices &<br />

conveyors 2,280<br />

• Baggage screening<br />

equipment 3,030<br />

• Circulation 900<br />

• Total 6,210<br />

Screening equipment (ea)<br />

• Level 1 EDS 3<br />

• Level 2 OSR 3<br />

• Level 3 ETD 10<br />

• Total 16<br />

4.<br />

Requirements<br />

Screening space (sf)<br />

• Baseline 6,030<br />

• 2.5 MAP 7,830<br />

• 3.0 MAP 7,830<br />

• 4.0 MAP 9,950<br />

Screening equipment (ea)<br />

• Baseline 7<br />

• 2.5 MAP 8<br />

• 3.0 MAP 8<br />

• 4.0 MAP 11<br />

Based on the terminal requirements model results:<br />

• Additional Level 1 EDS equipment will be required by 2.5<br />

MAP. Level 2 OSR and Level 3 ETD equipment will be<br />

adequate through the planning period.<br />

• Outbound baggage screening space will be inadequate<br />

by 2.5 MAP.<br />

• Detailed requirements for screening equipment and area<br />

are provided below.<br />

12,000<br />

10,000<br />

8,000<br />

6,000<br />

4,000<br />

2,000<br />

2,275<br />

900<br />

Baggage Screening <strong>Area</strong> (sf)<br />

2,680<br />

670<br />

3,030 2,680<br />

3,480 3,480<br />

870 870<br />

3,480 3,480<br />

4,420<br />

1,105<br />

4,420<br />

• Based on the analysis,<br />

additional screening<br />

equipment (Level 1<br />

EDS), as well as<br />

additional screening<br />

space of approximately<br />

400 sf, would be needed<br />

by 2.5 MAP.<br />

0<br />

18<br />

16<br />

14<br />

12<br />

10<br />

8<br />

6<br />

4<br />

2<br />

0<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

10<br />

3<br />

Baggage Screening Equipment<br />

2<br />

2<br />

3 3<br />

Baggage screening equipment<br />

Circulation<br />

Conveyors and sorting matrices<br />

2 2<br />

2 2<br />

4 4<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Level 1 EDS Level 2 OSR Level 3 ETD<br />

3<br />

3<br />

5<br />

41<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Outbound baggage make-up<br />

KEY POINTS<br />

• Outbound baggage<br />

makeup requirements<br />

were based on the<br />

number of departing<br />

flights in the peak twohour<br />

staging period.<br />

Outbound baggage<br />

makeup requirements<br />

were estimated by<br />

baggage make-up device<br />

(i.e. carts including<br />

tugs).<br />

• Based on the analysis,<br />

the baggage make-up<br />

area is currently<br />

inadequate – an<br />

additional 2,900 sf<br />

would be needed to<br />

provide sufficient space<br />

to satisfy 3.0 MAP.<br />

1.<br />

Activity Forecasts<br />

Annual passenger aircraft<br />

departures (thousands):<br />

• Baseline: 16.9<br />

• 2.5 MAP: 18.5<br />

• 3.0 MAP: 20.9<br />

• 4.0 MAP: 27.6<br />

2.<br />

Assumptions<br />

Average number of carts per<br />

departure: 2.5 (2 for RJ, 3 for<br />

NB)<br />

Average number of<br />

departures within two-hour<br />

staging period: 1.1<br />

<strong>Area</strong> per cart (sf): 300<br />

Outbound baggage makeup<br />

requirement derived based<br />

on the total space required by<br />

the number of baggage trains<br />

at each gate within a twohour<br />

staging period.<br />

3.<br />

Existing Facilities<br />

Make-up space (sf)<br />

• Make-up 6,110<br />

• Circulation 4,640<br />

• Total 10,750<br />

4.<br />

Requirements<br />

Make-up space (sf):<br />

• Baseline 10,800<br />

• 2.5 MAP 11,760<br />

• 3.0 MAP 13,800<br />

• 4.0 MAP 17,640<br />

Based on the terminal requirements model results:<br />

• Baggage make-up area is currently inadequate.<br />

• Detailed requirements for screening equipment and area<br />

are provided below.<br />

20,000<br />

18,000<br />

16,000<br />

14,000<br />

12,000<br />

10,000<br />

8,000<br />

6,000<br />

4,000<br />

2,000<br />

0<br />

4,640<br />

6,110<br />

Baggage Make-up <strong>Area</strong> (sf)<br />

1,800<br />

1,960<br />

9,000 9,800<br />

2,300<br />

11,500<br />

2,940<br />

14,700<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Baggage make-up area<br />

Baggage train circulation allowance<br />

42<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Concessions<br />

KEY POINTS<br />

• Facility requirements for<br />

the concessions include<br />

the total space for<br />

concession services<br />

only; back-of-house<br />

space that is necessary<br />

to support them, such as<br />

storage areas, kitchens,<br />

employee lockers,<br />

loading docks, and<br />

administrative offices<br />

are included in the<br />

secondary facilities<br />

evaluation.<br />

• It is assumed that 75%<br />

of the concessions<br />

would be post-security,<br />

where passengers would<br />

be more relaxed and<br />

more inclined to use the<br />

services.<br />

1.<br />

Activity Forecasts<br />

Annual enplaned passengers<br />

(millions):<br />

• Baseline: 1.1<br />

• 2.5 MAP: 1.25<br />

• 3.0 MAP: 1.5<br />

• 4.0 MAP: 2.0<br />

2.<br />

Assumptions<br />

<strong>Plan</strong>ning factors<br />

(sf per 1,000 pax):<br />

• F&B 8.0<br />

• Retail 4.0<br />

• Services 0.5<br />

• Total 12.5<br />

Split (%):<br />

• Pre-security 25<br />

• Post-security 75<br />

• Total 100<br />

Concessions space<br />

requirements derived based<br />

on the planning factors<br />

multiplied by the forecast<br />

annual enplaned passengers.<br />

3.<br />

Existing Facilities<br />

Concession space (sf)<br />

• Pre-security 8,420<br />

• Post-security 9,400<br />

• Support 4,970<br />

• Total 22,790<br />

Concession space breakdown<br />

(sf)<br />

• F&B 12,820<br />

• Retail 5,000<br />

• Services -<br />

• Support 4,970<br />

• Total 22,790<br />

4.<br />

Requirements<br />

Concession space (sf):<br />

• Baseline 17,279<br />

• 2.5 MAP: 19,630<br />

• 3.0 MAP 23,550<br />

• 4.0 MAP 31,400<br />

Based on the terminal requirements model results:<br />

• More of the existing concessions area should be<br />

allocated to post-security for revenue maximization.<br />

• Detailed requirements for concessions area by function<br />

and location are provided below.<br />

30,000<br />

25,000<br />

20,000<br />

15,000<br />

10,000<br />

5,000<br />

0<br />

9,400<br />

8,420<br />

Concessions <strong>Area</strong> (sf) - Location<br />

Pre-security<br />

Post-security<br />

10,313<br />

11,719<br />

14,063<br />

3,438 3,906 4,688<br />

18,750<br />

6,250<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Note: Excludes concession support space.<br />

• Based on industry<br />

planning guidelines,<br />

more of the existing<br />

concessions should be<br />

allocated post-security.<br />

Additional concession<br />

space would be required<br />

by 3.0 MAP.<br />

18,000<br />

16,000<br />

14,000<br />

12,000<br />

10,000<br />

8,000<br />

6,000<br />

4,000<br />

2,000<br />

-<br />

Concessions <strong>Area</strong> (sf) - Function<br />

16,000<br />

12,820<br />

12,000<br />

10,000<br />

8,800<br />

8,000<br />

5,000 4,400 5,000<br />

6,000<br />

- 550 625 750 1,000<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Note: Excludes concession support space.<br />

43<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Passenger Holdrooms<br />

KEY POINTS<br />

• Holdroom requirements<br />

include seating and<br />

standing areas for<br />

passengers, an airline<br />

agent check-in podium,<br />

space for boarding<br />

queue, and space for<br />

circulation and airport<br />

amenities.<br />

• Holdroom sizing is based<br />

on the average seating<br />

capacity of the typical<br />

aircraft expected to use<br />

the gate. Percentage of<br />

passengers to be seated<br />

or standing, as well as<br />

average area per<br />

passenger are based on<br />

Level of Service C.<br />

1.<br />

Activity Forecasts<br />

Annual enplaned passengers<br />

(millions):<br />

• Baseline: 1.1<br />

• 2.5 MAP: 1.25<br />

• 3.0 MAP: 1.5<br />

• 4.0 MAP: 2.0<br />

2.<br />

Assumptions<br />

Average number of seats on<br />

design aircraft: 89<br />

Passengers split (%):<br />

• Standing 20<br />

• Seated 80<br />

• Total 100<br />

Passengers space<br />

requirement for Level of<br />

Service C (sf/pax):<br />

• Standing 10<br />

• Seated 15<br />

3.<br />

Existing Facilities<br />

Holdrooms space (sf)<br />

• Holdrooms 20,170<br />

• Circulation 3,920<br />

• Total* 24,090<br />

*Includes holdroom space<br />

at Gate A5, which is<br />

currently not utilized.<br />

4.<br />

Requirements<br />

Holdrooms space (sf):<br />

• Baseline 25,245<br />

• 2.5 MAP 27,540<br />

• 3.0 MAP 32,130<br />

• 4.0 MAP 41,310<br />

• Includes 5% allowance<br />

for amenities, 35% for<br />

circulation.<br />

Based on the terminal requirements model results:<br />

• Existing holdroom space is insufficient unless the<br />

holdroom at Gate A5 (3,600 square feet ) is utilized to<br />

meet baseline demand.<br />

• Concessions planning will have an impact on holdroom<br />

size requirements.<br />

• Detailed requirements for holdroom area and circulation<br />

are provided below.<br />

45,000<br />

40,000<br />

35,000<br />

30,000<br />

25,000<br />

20,000<br />

15,000<br />

10,000<br />

5,000<br />

3,600<br />

3,920<br />

16,566<br />

Holdrooms <strong>Area</strong> (sf)<br />

6,545<br />

7,140<br />

18,700 20,400<br />

8,330<br />

23,800<br />

10,710<br />

30,600<br />

• Based on the analysis,<br />

existing holdroom<br />

space is insufficient to<br />

accommodate baseline<br />

demand.<br />

0<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Holdroom area Holdroom circulation Misc<br />

44<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Baggage claim<br />

KEY POINTS<br />

• Facility requirements for<br />

baggage claim<br />

considered both the<br />

passenger flow and the<br />

baggage flow.<br />

• To provide level of<br />

service C, several things<br />

were considered: the<br />

exposed length of the<br />

device (i.e. claim<br />

frontage), off-load space<br />

(to allow baggage carts<br />

to be pulled adjacent<br />

and handlers to load<br />

bags onto the claim<br />

device), total claim unit<br />

length (i.e. carousel<br />

frontage), and baggage<br />

hall space.<br />

1.<br />

Activity Forecasts<br />

Average Day Peak Month<br />

peak hour bags to process:<br />

• Baseline: 566<br />

• 2.5 MAP: 661<br />

• 3.0 MAP: 792<br />

• 4.0 MAP: 1,082<br />

• 62% of passengers has<br />

checked bags, each with<br />

an average of 1.3 bags.<br />

2.<br />

Assumptions<br />

Claim frontage per person at<br />

Level of Service C (feet): 1.5<br />

Carousel unit<br />

frontage (feet): 150<br />

Carousel module (sf): 4,400<br />

Includes 20% of space for<br />

baggage offices, 15% for<br />

meeter/greeter lobby, and<br />

25% for circulation.<br />

3.<br />

Existing Facilities<br />

Baggage claims (ea)<br />

• Units 2<br />

Existing baggage claims are<br />

flat plate units; for future<br />

requirements, carousel type<br />

units are recommended.<br />

Baggage claim space (sf)<br />

• Claim area 7,440<br />

• Baggage offices 810<br />

• Meeter/greeter 680<br />

• Circulation 7,130<br />

• Offload 4,060<br />

• Total 20,120<br />

4.<br />

Requirements<br />

Baggage claims (ea)<br />

• Baseline 2<br />

• 2.5 MAP 2<br />

• 3.0 MAP 2<br />

• 4.0 MAP 3<br />

Baggage claim space (sf)<br />

• Baseline 17,760<br />

• 2.5 MAP 20,050<br />

• 3.0 MAP 20,050<br />

• 4.0 MAP 30,080<br />

Based on the terminal requirements analysis:<br />

• Bag claim area is currently inadequate for the baggage<br />

offices, meeter/greeter lobby, and offload area. Future<br />

space requirements are based on carousel type bag<br />

claims.<br />

• Detailed requirements for various baggage claim areas<br />

are provided below.<br />

35,000<br />

30,000<br />

25,000<br />

20,000<br />

15,000<br />

10,000<br />

5,000<br />

4,060<br />

5,200<br />

7,130<br />

2,511<br />

680<br />

805<br />

1,116<br />

1,488<br />

Baggage Claim <strong>Area</strong> (sf)<br />

5,200 5,200<br />

2,970 2,970<br />

1,320<br />

1,760<br />

1,320<br />

1,760<br />

7,440 7,440 8,800 8,800<br />

7,800<br />

4,455<br />

1,980<br />

2,640<br />

13,200<br />

• Based on the analysis,<br />

the baggage claim area<br />

is currently inadequate<br />

particularly in the<br />

following areas:<br />

— Baggage offices<br />

0<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Claim area (carousels)<br />

Meeter/greeter lobby<br />

Inbound baggage offload area<br />

Baggage service offices<br />

Circulation<br />

— Meeter/greeter lobby<br />

— Off-load<br />

45<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

Restrooms, Secondary and Other <strong>Area</strong>s<br />

KEY POINTS<br />

• Restroom requirements<br />

are estimated separately<br />

for pre-security<br />

(including check-in<br />

lobby and arrivals lobby)<br />

and post-security (i.e.<br />

boarding area), based on<br />

the peak 30-minute<br />

arriving and departing<br />

passengers demand, as<br />

well as the percentage<br />

of meeter/greeter and<br />

well-wishers that will be<br />

using the facilities.<br />

• Based on the analysis,<br />

the existing space for<br />

restrooms in postsecurity<br />

is currently<br />

inadequate.<br />

• Secondary facilities<br />

include airline support,<br />

airport support, and<br />

facilities support and<br />

services.<br />

1.<br />

Activity Forecasts<br />

Average Day Peak Month<br />

peak 30-minute enplaned<br />

passengers*:<br />

• Baseline: 231<br />

• 2.5 MAP: 270<br />

• 3.0 MAP: 324<br />

• 4.0 MAP: 442<br />

*Excludes connecting passengers<br />

Average Day Peak Month<br />

peak 20-minute deplaned<br />

passengers:<br />

• Baseline: 284<br />

• 2.5 MAP: 331<br />

• 3.0 MAP: 397<br />

• 4.0 MAP: 543<br />

2.<br />

Assumptions<br />

Meeter/greeter<br />

(per deplaned pax): 0.2<br />

Well-wishers<br />

(per enplaned pax): 0.2<br />

Number of fixtures<br />

(per 100 pax): 1<br />

Restrooms area (sf):<br />

• Men/Women 70*<br />

• Family 100<br />

*area per fixture<br />

Restrooms split (%):<br />

• Women 60<br />

• Men 40<br />

Restrooms space split (%):<br />

• Pre-security 30<br />

• Post-security 70<br />

3.<br />

Existing Facilities<br />

Restrooms space (sf)<br />

• Pre-security 2,120<br />

• Post-security 3,240<br />

• Total 5,360<br />

4.<br />

Requirements<br />

Restrooms space (sf):<br />

• Baseline 6,700<br />

• 2.5 MAP 7,590<br />

• 3.0 MAP 8,970<br />

• 4.0 MAP 12,140<br />

Based on the terminal requirements model results:<br />

• Existing terminal provides adequate pre-security<br />

restrooms, but can provide more space post-security to<br />

meet passenger needs.<br />

• Detailed requirements for restrooms are provided below.<br />

14,000<br />

12,000<br />

10,000<br />

8,000<br />

6,000<br />

4,000<br />

2,000<br />

7,000<br />

6,000<br />

0<br />

3,238<br />

Restrooms <strong>Area</strong> (sf) - Pre/Post Security<br />

4,520<br />

5,180<br />

6,050<br />

2,120 2,180 2,410 2,920<br />

8,350<br />

3,790<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

Pre-security<br />

Post-security<br />

Restrooms <strong>Area</strong> (sf) - Mens/Womens/Family<br />

• The space allowance for<br />

secondary areas are<br />

calculated as a<br />

percentage of total<br />

major departures<br />

and/or arrivals<br />

functional areas.<br />

Secondary and Other <strong>Area</strong>s<br />

Requirements for secondary and other areas are sized based<br />

on existing facilities, relative to the space requirements for<br />

the primary area for each passenger demand level.<br />

Secondary facilities include:<br />

– Airline support (e.g. airline operations)<br />

– Airport support (e.g. Transportation Security Administration<br />

and staff support, ground handling services, operations and<br />

maintenance)<br />

– Facilities support and services (e.g. loading dock,<br />

trash/recycling)<br />

Additional areas include:<br />

– Building structure which includes foundations, columns,<br />

cores, walls, internal partitions, support structural<br />

framework, etc.<br />

– Building mechanical systems which include mechanical<br />

system/electric rooms, plumbing spaces, ducts for<br />

heating/ventilation/air conditioning, etc.<br />

5,000<br />

4,000<br />

3,000<br />

2,000<br />

1,000<br />

0<br />

6,650<br />

4,900<br />

4,130<br />

4,480<br />

3,570<br />

3,290<br />

2,450 2,730<br />

994 994133 400 400 400 500<br />

Existing Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

46<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Passenger <strong>Terminal</strong> Requirements<br />

<strong>Terminal</strong> Requirements Summary<br />

<strong>Terminal</strong> requirements are summarized in the table below:<br />

47<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Peak Occupancy (stalls)<br />

Peak Occupancy (stalls)<br />

Spaces<br />

Spaces<br />

Ground Transportation Requirements<br />

Parking<br />

KEY POINTS<br />

• Approximately 4,300<br />

spaces are available for<br />

public parking<br />

• Today, only<br />

approximately 3,425<br />

public spaces are<br />

occupied on a typical<br />

busy day<br />

• By 3.0 MAP, 5,100 public<br />

spaces are estimated to<br />

be required, translating<br />

to approximately 5 acres<br />

of additional parking<br />

• By 4.0 MAP, 6,800<br />

spaces are estimated to<br />

be required, translating<br />

to approximately 16<br />

acres of additional<br />

parking<br />

1. Existing Facilities<br />

Public Parking<br />

Parking Spaces<br />

• Short-term 341<br />

• Long-term 1,732<br />

• Economy 1,885<br />

• Economy 4* 300<br />

• Total 4,258<br />

* Economy Lot #4 currently<br />

has 1,000 parking spaces.<br />

Approximately 700 of those<br />

spaces have been leased to<br />

the rental car companies<br />

2. Methodology and Assumptions<br />

Current Demand Determination<br />

• ‘Typical busy day’ in past 12 months is used to identify existing design-day<br />

• All public parking facilities are evaluated combined, since distribution<br />

between parking products is determined by policy decisions and price points<br />

Key Assumptions<br />

• Demand will grow at same rate as passenger traffic<br />

• 10% ‘circulation’ factor is added to demand<br />

4,000<br />

3,500<br />

3,000<br />

2,500<br />

2,000<br />

1,500<br />

3,424 occupied spaces<br />

0 100 200 300<br />

Day Ranks<br />

3. Requirements<br />

Public Parking stalls required:<br />

• 2.5 MAP 4,200<br />

• 3.0 MAP 5,100<br />

• 4.0 MAP 6,800<br />

Additional Spaces required:<br />

• 2.5 MAP 0<br />

• 3.0 MAP 850<br />

• 4.0 MAP 2,550<br />

Additional <strong>Area</strong> required:<br />

• 2.5 MAP 0<br />

• 3.0 MAP 5.3 acres<br />

• 4.0 MAP 15.8 acres<br />

As shown in Figure 33, existing<br />

public parking spaces are<br />

inadequate by 3.0 MAP.<br />

7,000<br />

6,000<br />

5,000<br />

4,000<br />

3,000<br />

2,000<br />

1,000<br />

Public Parking<br />

3,770 4,220<br />

5,090<br />

6,760<br />

0<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

Requirements (spaces) Existing (4,258 spaces)<br />

400<br />

300<br />

200<br />

100<br />

0<br />

Employee Parking<br />

270 280 300<br />

340<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

Requirements (spaces)<br />

Existing (273 spaces)<br />

• 273 spaces are available<br />

for employee parking<br />

• The employee parking<br />

lot is currently nearing<br />

capacity and will slightly<br />

exceed capacity 2.5 MAP<br />

Employee Parking<br />

Parking Spaces<br />

• Total 273<br />

Current Demand Determination<br />

• ‘Typical busy day’ in past 12 months is used to identify existing design-day<br />

Key Assumptions<br />

• Demand will grow at same rate as aircraft operations<br />

• 5% ‘circulation’ factor is added to demand<br />

300<br />

250<br />

200<br />

150<br />

100<br />

50<br />

0<br />

257occupied spaces<br />

0 100 200 300<br />

Day Ranks<br />

Parking stalls required:<br />

• 2.5 MAP 280<br />

• 3.0 MAP 300<br />

• 4.0 MAP 340<br />

Additional Spaces required:<br />

• 2.5 MAP 10<br />

• 3.0 MAP 30<br />

• 4.0 MAP 70<br />

Additional <strong>Area</strong> required:<br />

• 2.5 MAP 0 acres<br />

• 3.0 MAP 0.2 acres<br />

• 4.0 MAP 0.4 acres<br />

As shown in Figure 33, existing<br />

employee parking spaces<br />

are marginal at 2.5 MAP and<br />

will become insufficient by<br />

3.0 MAP.<br />

Figure 33<br />

Parking Stress Chart<br />

48<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Feet<br />

Feet<br />

Feet<br />

Ground Transportation Requirements<br />

Roads and Curbsides<br />

KEY POINTS<br />

• Under the existing<br />

enforcement conditions,<br />

the inner curbside<br />

(private vehicles) is<br />

approaching a capacity<br />

constraint<br />

• If “active loading /<br />

unloading only” were<br />

enforced on the inner<br />

curbside, there would<br />

be enough passenger<br />

vehicle curbside<br />

capacity through the<br />

planning period<br />

• The outer curbside is<br />

currently at capacity, but<br />

is expected to operate at<br />

a borderline acceptable<br />

level through 3.0 MAP<br />

• Existing entrance and<br />

exit roadways have<br />

operational constraints<br />

but not capacity<br />

constraints<br />

• Roadway capacity<br />

constraints are not<br />

expected to occur in the<br />

planning period<br />

The roadway and curbside facility requirements to accommodate<br />

demand throughout the planning period are summarized in this<br />

section. Requirements are based on industry best practices related<br />

to airport roadway planning.<br />

Curbsides<br />

Traffic counts from April 2013 were used to define peak day<br />

volume. An analysis of the schedule revealed that approximately<br />

8% of departing seats occur during the peak hour, which was<br />

increased to 10% for a conservative estimate. Once the peak hour<br />

volumes for the peak day in April was determined, the volumes<br />

were adjusted for the peak month. Using historical data, June was<br />

identified as the busiest month, with approximately 23% higher<br />

traffic volumes than April. The resulting traffic volumes are shown<br />

below. Traffic was grown in direct proportion to forecasted growth<br />

in airline passenger traffic. Figure 34 shows insufficiencies in the<br />

existing curbsides by 2.5 and 3.0 MAP levels.<br />

1. Existing Facilities<br />

Curbside Length (linear feet)<br />

• Inner 545<br />

• Outer 571<br />

Traffic<br />

PM Peak Hour (13:30-14:30)<br />

April 2013 Traffic Counts<br />

adjusted for peak month and<br />

peak hour<br />

Vehicle Type<br />

Vehicles<br />

Taxi 32<br />

Hotel Shuttle 21<br />

Limo 3<br />

Off-Airport Parking 11<br />

Airport Parking Bus 14<br />

Private Vehicles<br />

Arrivals 52<br />

Departures 33<br />

Total 167<br />

2. Activity Forecasts 3. Assumptions 4. Requirements<br />

Grown in direct proportion to<br />

forecasted growth in airline<br />

passenger traffic<br />

Peak Hour Traffic Volumes<br />

Vehicle Type<br />

2.5 MAP 4.0 MAP<br />

Taxi 39 62<br />

Hotel Shuttle 25 40<br />

Limo 4 6<br />

Off A/P Parking 13 21<br />

A/P Parking 14 14<br />

Private Vehicles<br />

Arrivals 63 100<br />

Departures 40 64<br />

Total 198 308<br />

The traffic volumes were combined with the assumed dwell<br />

times and adjusted by the Poisson distribution to assure that<br />

enough spaces were available 95% of the time (a level of<br />

service C standard). The resulting curbside requirements are<br />

shown in the graphs below.<br />

Roadways<br />

The roadways have several operational issues, but do provide<br />

sufficient capacity . With the traffic volumes shown in the<br />

curbside analysis below, a single-lane entrance and exit<br />

roadway would meet capacity requirements. However, it is an<br />

industry standard to provide two-lane entrance and exit<br />

roadways to avoid a situation in which an accident or similar<br />

event could prevent access to the terminal.<br />

Length of curbside required is dependent<br />

on dwell time. Two scenarios were<br />

evaluated: (a) dwell times with current<br />

enforcement and (b) dwell times<br />

enforced for active loading/unloading<br />

Dwell Time Assumptions (min.)<br />

Vehicle Type<br />

Current<br />

Enforcement<br />

Active<br />

loading /<br />

Unloading<br />

Taxi 2.7 2.7<br />

Hotel Shuttle 3.5 3.5<br />

Limo 10 10<br />

Off A/P Parking 3.5 3.5<br />

A/P Parking 4 4<br />

Private Vehicles<br />

Arrivals 8.7 3.5<br />

Departures 3.0 2.5<br />

Inner Curbside<br />

800<br />

600<br />

400<br />

200<br />

0<br />

200<br />

Outer Curbside<br />

Current Enforcement<br />

230<br />

270<br />

300 340 390<br />

800<br />

600<br />

400<br />

200<br />

0<br />

4.0 MAP<br />

3.0 MAP<br />

2.5 MAP<br />

Existing<br />

320<br />

500<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

340 340 340<br />

240 270 270<br />

Legend – Level of service during peak periods<br />

Unacceptable<br />

800<br />

600<br />

400<br />

200<br />

0<br />

Pick-up Requirements<br />

Total Available Curbside (545 ft.)<br />

340<br />

390<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

Figure 34<br />

Existing Curbsides Stress Chart<br />

Inner<br />

Marginal<br />

Stricter Enforcement<br />

180 200<br />

Outer<br />

Acceptable<br />

230<br />

270<br />

180 180 200 230<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

Drop-off Requirements<br />

Arrivals Curbside (285 ft.)<br />

Taxi, Charter, and<br />

Airport Requirements<br />

Courtesy and Limo<br />

Requirements<br />

Total Available<br />

Curbside (571 ft.)<br />

Courtesy and Limo<br />

(232 ft.)<br />

49<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Spaces<br />

Acres<br />

Ground Transportation Requirements<br />

Rental Car Facilities and Hold Lot<br />

KEY POINTS<br />

1. Existing Facilities<br />

2. Methodology and Assumptions<br />

3. Requirements<br />

600<br />

Ready-Return Spaces<br />

• The rental car customer<br />

service facilities (Rental<br />

Car Counters and Ready-<br />

Return Spaces) will<br />

experience capacity<br />

constraints by 3.0 MAP<br />

• The existing QTA<br />

combined with the<br />

leased space in Economy<br />

Lot #4 is expected to<br />

provide enough space<br />

until 4.0 MAP<br />

• The construction of a<br />

Hold Lot is dependent<br />

on local policy decisions,<br />

but if built should<br />

accommodate 15 taxis, 5<br />

limos, and 3 buses to<br />

accommodate 2.5 MAP<br />

demands<br />

Rental Car Facilities<br />

Customer Facilities:<br />

• Customer Service <strong>Area</strong><br />

3,345 sq. ft.<br />

• Ready-Return Spaces<br />

370 spaces<br />

Quick Turn Around (QTA):<br />

• Wash and Fuel Facility<br />

4.3 acres<br />

• Storage (Economy Lot #4)<br />

700 spaces (4.3 acres)<br />

Hold Lot<br />

• Hold areas are divided into<br />

two primary areas: taxi<br />

queue and limo hold area<br />

• Current hold areas have<br />

room for eight taxicabs<br />

and three limos<br />

Rental Car Facilities Model<br />

• Created in conjunction with rental car industry leading architects<br />

• Model is based off inputs from a variety of Airports<br />

• Fundamentally based off rental car fleet size. To estimate the<br />

fleet size, a benchmarking ratio of 2,000 vehicles per MEP was<br />

created.<br />

• Growth for ready/return and QTA facilities increases in direct<br />

proportion to forecasted growth in O&D commercial passenger<br />

traffic. While the rental car industry is relatively volatile with a<br />

long history of new entrants and merges, the total market<br />

demand for vehicles will likely be unaffected by the changes.<br />

• Estimates individual facility needs for customer service facilities<br />

(queue space, counters, administration space, etc.) , ready/return<br />

spaces, and QTA (wash, fuel, maintenance, and storage)<br />

• For rental car operations with less than 4,000 vehicles and more<br />

than 4 companies, there is a reduction in operational efficiencies,<br />

resulting in increased requirements relative to benchmarks<br />

Potential Solutions<br />

• Policy regarding a hold lot is determined by local staff and politics<br />

• Current solution, the taxi ‘hold lot’ is a queue along the inbound<br />

roadway, typically occurring in a third lane on the right<br />

• Alternative 1: a paved parking lot with simple restroom facilities<br />

• Alternative 2: combine the hold lot with a gas station / convenience<br />

store along the primary route for rental cars (see example below)<br />

Customer Service <strong>Area</strong> (CSA)<br />

• 2.5 MAP 2,900 s.f.<br />

• 3.0 MAP 3,500 s.f.<br />

• 4.0 MAP 4,100 s.f.<br />

(add approximately 1,000 s.f.<br />

for a separate customer service<br />

bldg.)<br />

Ready-Return (R/R) Spaces:<br />

• 2.5 MAP 350<br />

• 3.0 MAP 420<br />

• 4.0 MAP 570<br />

QTA:<br />

• 2.5 MAP 5.5 acres<br />

• 3.0 MAP 6.5 acres<br />

• 4.0 MAP 8.8 acres<br />

As shown on Figure 35, CSA<br />

and R/R will be inadequate by<br />

3.0 MAP.<br />

The size of commercial vehicle<br />

hold lots are often determined by<br />

policy (how long taxis have to<br />

wait, what is the quality of the<br />

facilities, etc.)<br />

Taxis (estimated 2-3 hour wait)<br />

• 2.5 MAP 15<br />

• 4.0 MAP 25<br />

400<br />

200<br />

0<br />

10<br />

8<br />

6<br />

4<br />

2<br />

0<br />

310 350<br />

420<br />

570<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

Requirement (spaces) Existing (370 spaces)<br />

Quick-Turnaround<br />

4.9 5.5<br />

6.5<br />

8.8<br />

Baseline 2.5 MAP 3.0 MAP 4.0 MAP<br />

(2013)<br />

Requirement (acres) Existing (8.6 acres)<br />

Figure 35<br />

Rental Car Facilities and Hold Lot Stress Chart<br />

• Current hold area requires<br />

taxis to cross three lanes of<br />

traffic<br />

Taxi Hold Lot<br />

Limos and<br />

Busses<br />

Limos:<br />

• 2.5 MAP 5<br />

• 4.0 MAP 10<br />

• During peak hours, taxicabs<br />

are frequently re-circulating<br />

on the airport roadways<br />

waiting for space in the taxi<br />

queue<br />

Convenience<br />

Store<br />

Fuel<br />

Pumps<br />

Potential<br />

Cell lot<br />

Charter buses:<br />

• 2.5 MAP 3<br />

• 4.0 MAP 5<br />

Existing hold log is alreading<br />

insufficient to meet current<br />

demand, as illustrated on<br />

Figure 35.<br />

50<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Airfield requirements<br />

Runway length requirements<br />

KEY POINTS<br />

• Runway length<br />

requirements were<br />

evaluated for the<br />

selected aircraft types:<br />

— MD-83<br />

— Airbus 300-600<br />

— Airbus 330-300<br />

— Boeing 747-400<br />

— Boeing 767-300 Freighter<br />

• Existing runway length<br />

of 9,000 feet is sufficient<br />

to support all selected<br />

aircraft up to 80% of<br />

their useful load, and all<br />

of the selected aircraft<br />

for the selected<br />

destinations.<br />

Methodology:<br />

• Evaluation of runway length requirements involved:<br />

– Assessment of aircraft manufacturer’s published<br />

takeoff and landing criteria, as reported in<br />

aircraft planning manuals<br />

– A more detailed evaluation of the aircraft takeoff<br />

performance capabilities, as measured by<br />

takeoff weights and payloads.<br />

Assumptions:<br />

• The aircraft types considered were from the forecast<br />

prepared for the master plan, as well as the<br />

published flight schedules for commercial<br />

passenger, air taxi, and cargo operations based on<br />

FAA Traffic Flow Management System Counts<br />

(TFMSC) data, for the period CY 2005 to CY 2012.<br />

• The analysis of takeoff and landing runway length<br />

requirements incorporated the following<br />

assumptions:<br />

– Ambient temperatures of 86 F, reflecting the<br />

mean maximum temperature of the hottest<br />

month.<br />

– Existing airport elevation of 958 feet.<br />

– Zero wind, unless otherwise noted.<br />

Findings:<br />

• Figure 36 presents the results of the takeoff<br />

runway length evaluation. The existing runway<br />

length is sufficient to support all selected aircraft<br />

up to approximately 80% of their useful load.<br />

Aircraft do not typically operate at 100% of their<br />

useful load for practical reasons: (1) the aircraft<br />

may not be accommodating a full passenger load<br />

and (2) the aircraft may not be traveling<br />

sufficient distance to require a full load of fuel.<br />

• Figure 37 presents the results of the takeoff<br />

runway length requirements for selected<br />

destinations. The existing runway length of<br />

9,000 feet can accommodate all of the selected<br />

aircraft for the selected destinations.<br />

• Table 20 presents the results of landing runway<br />

length evaluation. Landing runway length<br />

requirements are shown for both dry and wet<br />

conditions. The existing runway lengths are<br />

sufficient to accommodate the aircraft fleet mix.<br />

Useful Load Takeoff length requirements were evaluated based on the<br />

aircraft’s “useful load” (as shown on Figure 38). Useful load is defined as<br />

the maximum takeoff weight minus the aircraft empty weight. An<br />

aircraft’s useful load can be used to transport either fuel or payload (i.e.,<br />

passengers, baggage, and cargo), and within certain limits, useful load<br />

can be allocated between fuel and passengers/cargo.<br />

Figure 38<br />

Figure 36<br />

Figure 37<br />

Table 20<br />

RUNWAY LANDING LENGTH SUMMARY<br />

Landing length requirement<br />

(ft)<br />

Aircraft<br />

Dry<br />

Wet<br />

B767-300 Freighter 6,270 7,180<br />

B747-400 6,490 7,190<br />

A330-300 5,640 n.a.<br />

A300B4-600 6,140 n.a.<br />

MD-83 5,300 6,140<br />

(1) Requirements based on standard day temperature (15ºC), zero wind, zero<br />

runway slope, no reverse thrust, and airport elevation of 985 and maximum<br />

design landing weight, unless otherwise stated.<br />

Sources: Aircraft Characteristics for Airport <strong>Plan</strong>ning, published by the Boeing<br />

Company and Airbus Industrie.<br />

51<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Airfield requirements<br />

Airfield capacity and delay<br />

KEY POINTS<br />

• Airfield capacity is<br />

evaluated based on the<br />

Annual Service Volume<br />

(ASV) and average<br />

aircraft delay methods<br />

from the current FAA’s<br />

Advisory Circular<br />

150/5060-5, Airport<br />

Capacity and Delay.<br />

• Based on the analysis,<br />

the existing airfield can<br />

accommodate forecast<br />

aviation demand<br />

throughout the entire<br />

planning period of the<br />

master plan, with<br />

average aircraft delay of<br />

less than 1 minute per<br />

operation.<br />

Methodology:<br />

• Annual Service Volume (ASV) is an estimate of how<br />

many aircraft operations an airport can accommodate<br />

in a year, and is calculated using the methods<br />

specified in the current FAA’s Advisory Circular<br />

150/5060-5, Airport Capacity and Delay (the AC). It is<br />

defined as the point at which further increases in<br />

demand will result in disproportionate increase in<br />

average aircraft delay.<br />

ASV = Cw x D x H<br />

Cw is the weighted average hourly capacity of the<br />

airfield.<br />

D is the ratio of annual to ADPM demand.<br />

H is the ratio of ADPM demand to peak-hour<br />

demand.<br />

• Average aircraft delays is estimated based on the ASV<br />

methodology described in the AC. This methodology<br />

is based on the relationship between the ratio of<br />

annual demand to ASV and average annual aircraft<br />

delay, as shown on Figure 41.<br />

Assumptions:<br />

• Annual capacity was based on the hourly capacities<br />

and runway use percentages from the previous<br />

master plan, as shown on Table 21.<br />

• Demand factors (i.e., D and H) were calculated based<br />

on the aviation forecast prepared for the master plan.<br />

Findings:<br />

• As shown on Figure 39, the existing airfield can<br />

accommodate an 148,700 operations a year, which<br />

exceeded the forecast aviation demand throughout<br />

the entire planning period.<br />

• As shown on Figure 40, average aircraft delay is<br />

estimated to be less than 1 minute per operation<br />

throughout the entire planning period.<br />

Figure 41<br />

Aircraft Delay Curve<br />

FAA AC 150/5060-5, Airport Capacity and Delay<br />

Table 21<br />

Runway Use Percentages and Hourly Capacities<br />

Figure 39<br />

Figure 40<br />

ASV = 148,700<br />

Source: Des Moines International Airport, Master <strong>Plan</strong> 2007<br />

52<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Air Cargo Facility Requirements<br />

All-Cargo<br />

KEY POINTS<br />

• Approximately 50 acres<br />

are currently reserved<br />

for air cargo operations<br />

at the Airport, mostly in<br />

the south quadrant of<br />

the site.<br />

• The facilities are not<br />

fully utilized and can be<br />

downsized.<br />

• By the end of the<br />

planning period, 12<br />

acres should be reserved<br />

for air cargo activity.<br />

The air cargo facility requirements to accommodate demand<br />

throughout the planning period are summarized in this section.<br />

Requirements were based on industry best practices related to<br />

cargo facility planning. The following functional areas were<br />

examined:<br />

• Processing and Warehouse Space. Processing and warehouse<br />

space consists of enclosed areas used to store and sort air<br />

cargo, as well as to provide office and other space to facilitate<br />

air cargo operations. Warehouse facility requirements and<br />

use, typically expressed in pounds or tons of cargo per square<br />

foot of warehouse space, vary significantly by airport,<br />

depending on the mix of cargo operators. Airports with<br />

higher concentrations of integrated carrier activity have much<br />

greater facility use ratios.<br />

1.<br />

Existing Facilities<br />

All-cargo apron (s.y.)<br />

• South 177,000<br />

• East 27,000<br />

• Total 204,000<br />

Warehouses (s.f.)<br />

• Bldg 31 12,300<br />

• Bldg 32 28,000<br />

• Bldg 35 27,350<br />

• Total 67,650<br />

• Approx. 68% of total square<br />

footage is leased<br />

Total land area (approx.): 50<br />

acres<br />

Existing warehouse utilization<br />

(based on leased space only): 1.5<br />

ton/s.f.<br />

2.<br />

Activity Forecasts<br />

All-cargo airline air cargo<br />

(millions of pounds)<br />

• 2012: 147.8<br />

• 4.0 MAP: 172.7<br />

• Compound annual growth<br />

rate (CAGR): 0.8%<br />

Annual cargo aircraft<br />

operations<br />

• 2012: 5,456<br />

• 4.0 MAP: 5,427<br />

• CAGR: 0.0%<br />

Airports that accommodate more heavy freight, including<br />

international cargo, must accommodate longer dwell times and,<br />

therefore, have lower ratios of cargo tonnage per square foot of<br />

cargo warehouse space. For planning purposes, the generally<br />

accepted cargo facility use ratio is between 0.5 ton, for a low<br />

automation, mostly manual, facility, and 1.6 tons annually per<br />

square foot of warehouse space for a highly automated cargo<br />

facility. In 2012, the Airport achieved a warehouse utilization of<br />

1.5 tons of cargo per square foot. It was assumed that this rate<br />

would be maintained throughout the planning period, resulting<br />

in a total of 54,000 square feet of warehouse being required by<br />

4.0 MAP to handle forecasted cargo volumes.<br />

3.<br />

Assumptions<br />

Target warehouse utilization:<br />

1.5 ton/s.f.<br />

0.5 ton/s.f. = Low automation<br />

facility<br />

0.9 ton/s.f. = Automated facility<br />

1.6 ton/s.f. = Highly automated<br />

facility<br />

Number of warehouse levels:<br />

1.0<br />

Target land requirement ratio:<br />

3.3<br />

Overall land area (warehouse<br />

building and landside facilities)<br />

derived using a ratio relative to<br />

cargo warehouse space<br />

4.<br />

4.0 MAP<br />

Requirements<br />

All-cargo aircraft stands (sized<br />

for ADPM)<br />

• ADG II 1<br />

• ADG IV 7<br />

• Total 8<br />

Warehouse and land<br />

requirements (s.f.)<br />

• Warehouse 53,700<br />

• Ramp 334,600<br />

• Landside 123,500<br />

Total land area (approx.): 12<br />

acres<br />

South cargo area is adequate<br />

throughout planning period<br />

• Ramp <strong>Area</strong>. The ramp area includes paved airside<br />

areas used for aircraft parking while air cargo is<br />

loaded and unloaded. For larger air cargo<br />

complexes, ramp area may include a maneuvering<br />

area for aircraft to access parking positions, as<br />

well as storage areas for ground support<br />

equipment (GSE) used to load air cargo onto<br />

aircraft, unload air cargo from aircraft, or service<br />

aircraft. The aircraft parking requirements were<br />

calculated based on future ADPM demand. Based<br />

on the forecasts, it was determined that<br />

approximately 8 aircraft will have to be<br />

accommodated during the ADPM by 4.0 MAP,<br />

distributed as follows: one ADG II, and seven<br />

ADG IV aircraft. This corresponds to a 335,000<br />

square foot apron area.<br />

• Landside <strong>Area</strong>s. Air cargo landside areas include<br />

areas that provide for vehicle access and<br />

circulation from the Airport’s primary roadway<br />

network, parking for employees and visitors, and<br />

parking for the trucks delivering air cargo to<br />

processing and warehousing facilities and for<br />

taking delivery of air cargo from these facilities.<br />

An allowance was included for landscaping and<br />

other improvements in the calculation of total<br />

required landside areas. Overall land area, which<br />

includes the warehouse building footprint and the<br />

associated landside facilities, is derived using a<br />

ratio relative to the gross floor area of cargo<br />

warehouse space. The traditional cargo industry<br />

gross floor area to land requirement ratio is 1:3.3.<br />

By 4.0 MAP, 124,000 square feet should be<br />

reserved for landside facilities associated with allcargo<br />

operations.<br />

53<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Air Cargo Facility Requirements<br />

Belly Cargo<br />

KEY POINTS<br />

• Building 5 will be<br />

sufficient to handle belly<br />

cargo throughout the<br />

planning period.<br />

• Current belly cargo<br />

facility utilization is low<br />

and could be increased<br />

to optimize future space<br />

usage.<br />

1.<br />

Existing Facilities<br />

Warehouse (s.f.) 7,150<br />

Ramp (s.f.) 17,700<br />

Landside (s.f.) 16,300<br />

1/3 of Building 5 is used for<br />

belly cargo (Bays 2 and 3)<br />

Total land area:


General Aviation Facility Requirements<br />

General Aviation Apron and Aircraft Storage Facilities<br />

KEY POINTS<br />

• Approximately 15,300<br />

square yards of itinerant<br />

general aviation apron<br />

are projected to be<br />

required to<br />

accommodate demand<br />

by the end of the<br />

planning period.<br />

• Approximately 6,900<br />

square yards of based<br />

general aviation aircraft<br />

parking apron is<br />

projected to be required<br />

to accommodate<br />

demand by 4.0 MAP.<br />

• By 4.0 MAP, 368,200<br />

square feet of<br />

conventional hangar<br />

space is projected to be<br />

required. In addition, a<br />

total of 60,000 square<br />

feet of T-hangar space<br />

will be required.<br />

General aviation facility requirements to accommodate<br />

demand through the planning period are summarized in<br />

this section. Overall GA facility requirements were<br />

derived based on a review of existing facilities, GA<br />

demand trends, activity forecasts, and discussions with<br />

key stakeholders.<br />

Aviation Forecast<br />

• Total general aviation operations at the Airport are<br />

forecast to remain relatively constant throughout the<br />

planning period, declining slightly from 31,962<br />

operations in 2012 to 31,600 operations in 2032.<br />

Itinerant general aviation operations are forecast to<br />

increase an average of 0.1 percent per year from<br />

2012 to 2032, while local GA operations are forecast<br />

to decrease 0.6 percent per year over the same time<br />

period. Itinerant operations accounted for 80.5<br />

percent of total GA operations at the Airport in 2012.<br />

This trend is expected to continue and itinerant<br />

operations are forecast to account for the majority of<br />

GA traffic at the Airport throughout the planning<br />

period.<br />

• Total based aircraft at the Airport are forecast to<br />

increase an average of 0.7 percent per year,<br />

increasing from 108 aircraft in 2012 to 124 by 2032<br />

(4.0 MAP). The based aircraft fleet will evolve toward<br />

more business/corporate jets, while the number of<br />

piston and multi-engine turboprop aircraft based at<br />

the Airport will decrease.<br />

Aircraft Parking Apron<br />

• Aircraft parking aprons provide space for itinerant<br />

and based general aviation, allowing passengers to<br />

access FBO facilities, fueling, and ground<br />

transportation and allowing service trucks and FBO<br />

personnel access to the aircraft. Itinerant and based<br />

aircraft apron requirements were calculated using<br />

the following methodology and assumptions:<br />

– In accordance with FAA guidance, itinerant aircraft apron<br />

requirements were determined assuming 360 square yards<br />

of apron for 50 percent of the itinerant aircraft using the<br />

Airport on the busy day of the peak month. The “busy day”<br />

is defined as 110 percent of the activity on the ADPM.<br />

Approximately 15,300 square yards of itinerant general<br />

aviation apron are projected to be required to<br />

accommodate demand by the end of the planning period.<br />

– Based aircraft parking apron requirements were<br />

determined assuming that 30 percent of based single and<br />

multi-engine aircraft will use ramp parking throughout the<br />

planning period. In accordance with FAA guidance, it was<br />

assumed that 300 square yards of apron space will be<br />

required per based aircraft tiedown position. It was<br />

assumed that no based jet aircraft will use tiedown space.<br />

Approximately 6,900 square yards of based general<br />

aviation aircraft parking apron is projected to be required<br />

to accommodate demand by 4.0 MAP.<br />

4.0 MAP<br />

3.0 MAP<br />

2.5 MAP<br />

Existing<br />

Tie<br />

Downs<br />

Figure 43<br />

Existing General Aviation Stress Chart<br />

Conv.<br />

Hangars<br />

T-<br />

Hangars<br />

Aircraft Storage Facilities<br />

• The Airport currently provides a total of 240,000 square<br />

feet of conventional hangar space and 54,000 square feet<br />

of T-hangar space.<br />

• Aircraft storage facility requirements are based on the<br />

forecast number and fleet mix of based aircraft. Aircraft<br />

storage facility requirements were based on the following<br />

planning assumptions and guidelines:<br />

– Throughout the planning period, the owners/operators<br />

of approximately 70 percent of single- and multi-engine<br />

aircraft will desire hangar space. Of these, 90 percent<br />

will be accommodated in T-hangars and 10 percent will<br />

be accommodated in conventional hangars. All<br />

corporate jet aircraft will occupy conventional hangar<br />

space.<br />

– Storage requirements in conventional hangars were<br />

calculated using the following assumptions: 2,750<br />

square feet per multi-engine aircraft, 1,400 square feet<br />

per single engine aircraft, and 1,000 square feet per<br />

helicopter. An average of 8,000 square feet of hangar<br />

per jet aircraft was used. While this allowance is higher<br />

than FAA guidelines, it reflects the current operating<br />

conditions at the Airport, with a high proportion of large<br />

business jets.<br />

– Each T-hangar consists of 1,200 square feet.<br />

• By 4.0 MAP, 368,200 square feet of conventional hangar<br />

space is projected to be required. In addition, a total of<br />

60,000 square feet of T-hangar space will be required.<br />

• Shown on Figure 43 is a stress chart showing deficiencies<br />

in existing aviation facilities to meet forecast demand.<br />

Legend – Level of service during peak periods<br />

Unacceptable<br />

Marginal<br />

Acceptable<br />

55<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Storage Requirements (gallons)<br />

Airline Support Facility Requirements<br />

Fuel Storage Requirements<br />

KEY POINTS<br />

• Airline support facilities<br />

include:<br />

— Fuel storage<br />

— Ground support<br />

equipment maintenance<br />

and storage<br />

— Deicing facilities<br />

— Aircraft maintenance<br />

— Flight kitchen<br />

• Fuel storage capacity<br />

should be increased by<br />

160,000 gallons to a<br />

total of 600,000 gallons<br />

to maintain 7 days of<br />

reserve by 4.0 MAP.<br />

1.<br />

Existing Facilities<br />

Fuel Storage<br />

• Jet fuel used by the passenger and all-cargo airlines is currently<br />

stored in two above ground storage tanks located on the south<br />

side of the Airport, with a total gross storage capacity of 440,000<br />

gallons of jet fuel. Requirements for fuel storage facilities were<br />

focused on the Airport’s main fuel farm. It was assumed that any<br />

expansion plan for the general aviation fuel farms would be the<br />

result of a business decision by the FBOs to construct additional<br />

storage capacity.<br />

• Requirements were based on an analysis of historical fuel<br />

flowage and aircraft operations data for the Airport in 2012.<br />

• Fuel storage requirements are expressed in terms of gross tank<br />

storage volume as well as land area required so that the Airport<br />

can (1) prepare to accommodate future demand for storage<br />

capacity without interfering with the business decisions of the<br />

passenger and all-cargo airlines; and (2) ensure that no other<br />

facilities encroach on the area required for future fuel storage<br />

facility development.<br />

• The 440,000-gallons of jet fuel storage capacity, situated on<br />

approximately 1.7 acres of land, provided a 7-day reserve supply<br />

of jet fuel in 2012. By 4.0 MAP, storage requirements would<br />

range from approximately 260,000 gallons for a 3-day reserve to<br />

860,000 gallons for a 10-day reserve, occupying land areas<br />

ranging from 1.0 acre to 3.2 acres, as illustrated on Figures 44<br />

and Table 22.<br />

• The number of days’ supply of fuel stored onsite in reserve is a<br />

business decision to be made by the airlines serving the Airport.<br />

In addition, the number and configuration of the tanks to be<br />

provided are ultimately determined by the airlines based on<br />

operating considerations, such as the tank filling and fuel settling<br />

process, as well as the reserve supply desired.<br />

900,000<br />

800,000<br />

700,000<br />

600,000<br />

500,000<br />

400,000<br />

300,000<br />

200,000<br />

100,000<br />

Figure 44<br />

Fuel Storage Requirements<br />

2.5 MAP 4.0 MAP<br />

3.0 MAP<br />

0<br />

2015 2020<br />

Year<br />

2025 2030<br />

3-day supply 5-day supply 7-day supply 10-day supply<br />

Table 22<br />

Fuel Storage Land <strong>Area</strong> Requirements<br />

3-day reserve supply<br />

Fuel storage (gallons)<br />

Land area (acres)<br />

5-day reserve supply<br />

Fuel storage (gallons)<br />

Land area (acres)<br />

7-day reserve supply<br />

Fuel storage (gallons)<br />

Land area (acres)<br />

10-day reserve supply<br />

Fuel storage (gallons)<br />

Land area (acres)<br />

Requirements<br />

4.0 MAP<br />

Existing capacity - 440,000 gallons<br />

256,800<br />

1.0<br />

428,000<br />

1.6<br />

599,200<br />

2.3<br />

856,000<br />

3.2<br />

56<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Airline Support Facility Requirements<br />

KEY POINTS<br />

• Additional GSE storage<br />

will be required to<br />

support the expansion<br />

of the passenger<br />

terminal building.<br />

• It is recommended that<br />

a GSE maintenance<br />

facility be built to<br />

minimize maintenance<br />

activities occurring on<br />

the apron.<br />

• A new consolidated<br />

deicing facility will be<br />

required to handle<br />

future traffic levels.<br />

• No additional airline<br />

support facilities are<br />

required to handle<br />

projected traffic<br />

throughout planning<br />

period.<br />

1.<br />

Existing Facilities<br />

Ground Support Equipment Maintenance and Storage<br />

1.1 acre will be required for on-stand and on-apron<br />

storage of GSE equipment. Additionally, an acre parcel<br />

should be reserved for a GSE maintenance facility.<br />

Deicing facility<br />

A new deicing facility will be required to handle future<br />

activity levels. A 1.6-acre composite deicing pad can<br />

accommodate two narrowbody aircraft simultaneously<br />

or one widebody aircraft. Additional taxiway<br />

connectors would be required to link the new pad to<br />

the existing airfield system.<br />

Aircraft Maintenance<br />

Requirements for facilities that are leased by the<br />

airlines or directly support airline operations are<br />

typically established based on airline business<br />

decisions. The need for aircraft maintenance facilities<br />

is not necessarily related to the number of aircraft<br />

operations at a given airport and it is, therefore,<br />

difficult to forecast demand for such facilities.<br />

Hangar #29 is too small and needs to be expanded or<br />

relocated to larger site.<br />

Flight Kitchen<br />

No flight kitchen currently operates at the Airport.<br />

When required, in-flight meals are either prepared<br />

offsite and are trucked to the Airport or loaded at the<br />

hub for a round trip. As an industry trend, the need for<br />

flight kitchens has diminished over the past decade as<br />

the result of airline cutbacks on complimentary<br />

onboard meal service. Even with the slight increase in<br />

the availability of buy-on-board meal service, the<br />

packaging and distribution of these on-board meal<br />

types are more efficient than that for the hot meals<br />

that were common in the past. Therefore, as a result<br />

of this trend, it is expected that future activity at the<br />

Airport will not be sufficient to sustain operation of a<br />

flight kitchen and no on-Airport flight kitchen is<br />

recommended throughout the planning period.<br />

1.<br />

Existing Facilities<br />

On-stand storage is provided in<br />

between gates on the terminal<br />

apron.<br />

1.<br />

Existing Facilities<br />

UA leases a garage a garage space space to<br />

perform<br />

to perform<br />

maintenance<br />

maintenance<br />

on<br />

equipment.<br />

on equipment.<br />

All other airlines perform the<br />

maintenance All other airlines on the apron. perfo<br />

Ground Support Equipment Storage Requirements<br />

2.<br />

Methodology and Assumptions<br />

On-stand equipment areas for equipment that must be readily<br />

accessible when an aircraft pulls onto a stand, calculated by:<br />

1 - Estimating the number of GSE pieces required to support<br />

airline operations at the future gates<br />

2- Converting the number of pieces into a required square<br />

footage<br />

3- Adding a 30% allowance for circulation<br />

On-apron equipment areas for backup GSE used for routine<br />

aircraft handling as well as less-frequently used maintenance<br />

equipment, calculated by:<br />

1- Assuming that GSE in mid-term hold equal 35% of staged GSE<br />

2- Converting the number of pieces into a required square<br />

footage<br />

3- Adding a 20% allowance for circulation<br />

Ground Support Equipment Maintenance Facility Requirements<br />

2.<br />

Assumptions<br />

• Percentage of GSE vehicles in workshop 8%<br />

• Workshop area per vehicle (s.f.) 500<br />

• Gross land area multiplier 4<br />

3.<br />

PAL2.0 Requirements<br />

Equipment parking areas<br />

(square feet):<br />

• On-stand 37,200<br />

• On-apron 12,000<br />

• Total 49,200<br />

Or 1.1 acre<br />

3.<br />

PAL2.0 Requirements<br />

Workshop requirement:<br />

10,000 square feet<br />

Total land area (approx.): 0.9<br />

acre<br />

57<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Airport Support Facility Requirements<br />

General Aviation Apron and Aircraft Storage Facilities<br />

KEY POINTS<br />

• Airport support facilities<br />

include:<br />

— Aircraft rescue and fire<br />

fighting<br />

— Airport maintenance<br />

— Airport administration<br />

— FAA facilities<br />

• Maintenance facilities<br />

need to be expanded<br />

and consolidated.<br />

• Other airport support<br />

facilities will be<br />

adequate through the<br />

planning period<br />

Aircraft Rescue and Fire Fighting<br />

The ARFF facility will be adequate throughout the planning period:<br />

1.<br />

Existing Facilities<br />

• The facility is currently classified as Index C<br />

• No index increase is expected based on the forecast future fleet mix<br />

• No additional ARFF equipment will be required throughout the planning<br />

period<br />

• The existing facility meets FAR-mandated response time requirements thanks<br />

to its location immediately north of the intersection of Runways 13-31 and 5-<br />

23. Unless significant airfield expansion is recommended, this location will be<br />

adequate throughout the planning period.<br />

Airport Maintenance Facility<br />

Building and airfield maintenance facility needs do not necessarily increase<br />

proportionally with activity, but are more a function of the overall pavement,<br />

grassy areas, and terminal square footage requiring maintenance as well as<br />

climatic conditions (for snow/ice removal). At <strong>DSM</strong>, maintenance facilities will<br />

need to be consolidated as well as expanded to handle the improvement<br />

projects that will be recommended as part of the <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong>.<br />

Maintenance areas located inside the terminal building are addressed in the<br />

terminal requirements analysis.<br />

Airport Administration<br />

Administration space is currently sized adequately and an increase in the<br />

number of administrative staff at the Airport is not anticipated. Therefore the<br />

current administration space is adequate throughout the planning period.<br />

FAA Facilities<br />

The FAA has not indicated that the ATCT is undersized or in need of<br />

rehabilitation at this time.<br />

During the alternatives evaluation phase, additional analyses will be required<br />

to determine if the development recommendations impact the line-of-sight<br />

between the ATCT and all movement areas on the airfield.<br />

58<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


CONCEPT ALTERNATIVES ANALYSIS<br />

• Land Use Alternatives<br />

• <strong>Terminal</strong> Alternatives


Land Use Alternatives<br />

Alternatives analysis and evaluation<br />

KEY POINTS<br />

• The initial step in the<br />

alternatives screening<br />

process was to look at<br />

the needs of each<br />

functional component<br />

and develop layouts<br />

showing how these<br />

“chunks” of land could<br />

be organized<br />

• Land Use Alternatives 1<br />

and 3 were selected as<br />

the top two<br />

This section of the technical report documents the<br />

alternatives analysis portion of the <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong><br />

<strong>Plan</strong> study. This plan element was accomplished in two<br />

rounds – first a high level screening of on-airport land uses<br />

and then development of terminal facility alternatives on<br />

the short-listed land use alternatives.<br />

To develop the land use alternatives, the size of the area<br />

needed to support long term facilities/operations for each<br />

of the Airports functional areas was determined. These<br />

areas were placed in various configurations around the<br />

airport based on size, relationship to airfield as well as to<br />

other uses, and particular geometric needs. For example,<br />

general aviation facilities are located in three different<br />

quadrants and there was a stated desire to consolidate<br />

that function into a single quadrant for reasons of<br />

efficiency. Also, consideration was given to the fact that<br />

certain facilities (such as the IANG) reflected sizable<br />

investments in infrastructure and the planning team was<br />

careful with suggestions on which facilities should be<br />

relocated.<br />

The process of screening the alternatives is graphically<br />

shown in Figure 45. The primary tool used in the screening<br />

process was a list of pros and cons of each alternative.<br />

These were presented to the Advisory Committee, who<br />

deliberated and determined the short list.<br />

Land Use Alternatives<br />

Figures 46 through 49 on the following pages present<br />

graphically each of the four land use alternatives prepared<br />

for this study. The figures also include a listing of the pros<br />

and cons associated with each alternative.<br />

Shortlisted Land Use Alternatives<br />

Alternatives 1 and 3 were shortlisted for further analysis.<br />

Key reasons the Advisory Committee chose these land use<br />

alternatives include:<br />

• Alternative 1 – This land use alternative was chosen<br />

because of the existing investment in terminal support<br />

infrastructure and the desire to explore if it was feasible<br />

for building a new terminal building in this area.<br />

• Alternative 3 – This land use alternative shows<br />

development of a new terminal complex in the south air<br />

cargo area. The extensive amount of heavy-duty apron<br />

was viewed as an asset that could be readily adapted to<br />

commercial passenger aircraft parking.<br />

Figure 45<br />

Flow Chart of Land Use Alternatives Screening Process<br />

Des Moines International Airport<br />

60<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Land Use Alternatives<br />

Long list land use alternatives – Alternative 1<br />

Figure 46<br />

Land Use Alternative 1<br />

Des Moines International Airport<br />

shortlisted<br />

Pros<br />

• 20 year demands can be accommodated with this configuration.<br />

• Reconfiguration of IANG leasehold areas provide operational flexibility<br />

and other opportunities to Airport<br />

• Maintains each major functional component largely within its current<br />

proximity, preserving infrastructure investments<br />

• Least amount of disruption for non-terminal functions<br />

• T-hangars can continue to be developed in their current area through a<br />

logical expansion pattern<br />

Cons<br />

• Large Signature FBO complex in existing terminal area must be relocated<br />

to north GA/Corporate land use area<br />

• Construction phasing of a terminal on the current site can add<br />

complexities and costs, as compared to a new building on a greenfield<br />

site<br />

• Excess air cargo facilities (including aircraft parking apron) will continue<br />

to be underutilized<br />

• Corporate GA will be fully consolidated, providing efficiencies and deconflicting<br />

the terminal area<br />

• <strong>Terminal</strong> expansion can be phased as budget allows<br />

61<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Land Use Alternatives<br />

Long list land use alternatives – Alternative 2<br />

Figure 47<br />

Land Use Alternative 2<br />

Des Moines International Airport<br />

Pros<br />

• 20-year demands can be accommodated with this configuration<br />

• Reconfiguration of IANG leasehold areas provide operational flexibility<br />

and other opportunities to Airport<br />

• Opportunities for establishing and expanding the passenger terminal<br />

area are significantly improved<br />

• Excess air cargo facilities, primarily aircraft parking apron, would be<br />

more fully utilized by a passenger terminal use<br />

Cons<br />

• Cost to convert air cargo area (apron/utilities) to passenger terminal use<br />

could be significant<br />

• Cost to relocate air cargo facilities to existing terminal area could be<br />

significant<br />

• Impact of air cargo use on east site, near residential, could result in<br />

impacts<br />

• T-hangars would need to be relocated to the north quadrant<br />

• Vehicular access to passenger terminal area improved over current<br />

situation<br />

• Airline facilities (maintenance hangar) would need to be removed to<br />

make room for the terminal development<br />

• Allows Signature FBO to remain in place and potentially expand<br />

• Fuel farm is close to the airlines, who are a major user<br />

62<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Land Use Alternatives<br />

Long list land use alternatives – Alternative 3<br />

Figure 48<br />

Land Use Alternative 3<br />

Des Moines International Airport<br />

shortlisted<br />

Pros<br />

• 20-year demands can be accommodated with this configuration<br />

• Reconfiguration of IANG leasehold areas provide operational flexibility<br />

and other opportunities to Airport<br />

• Opportunities for establishing and expanding the passenger terminal<br />

area are significantly improved<br />

• Excess air cargo facilities, primarily aircraft parking apron, would be<br />

more fully utilized by a passenger terminal use<br />

• Vehicular access to passenger terminal area improved over current<br />

situation<br />

Cons<br />

• Cost to convert air cargo area (apron/utilities) to passenger terminal use<br />

could be significant<br />

• Cost to relocate air cargo facilities to existing terminal area could be<br />

significant<br />

• T-hangars would need to be relocated to the north quadrant<br />

• Signature FBO would need to be relocated to the north quadrant<br />

• Airline facilities (maintenance hangar) would need to be removed to<br />

make room for the terminal development<br />

• Fuel farm is close to the airlines, who are a major user<br />

• Air cargo to be relocated to the east quadrant<br />

63<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Land Use Alternatives<br />

Long list land use alternatives – Alternative 4<br />

Figure 49<br />

Land Use Alternative 4<br />

Des Moines International Airport<br />

Pros<br />

• 20-year demands can be accommodated with this configuration<br />

• Reconfiguration of IANG leasehold areas provide operational flexibility<br />

and other opportunities to Airport<br />

• Opportunities for establishing and expanding the passenger terminal<br />

area are significantly improved under this scheme<br />

• Excess air cargo facilities, primarily aircraft parking apron, would be<br />

more fully utilized by a passenger terminal use<br />

• Vehicular access to passenger terminal area improved over current<br />

situation<br />

Cons<br />

• Cost to convert air cargo area (apron/utilities) to passenger terminal use<br />

could be significant<br />

• Cost to relocate air cargo facilities could be significant<br />

• T-hangars and Signature FBO would need to be relocated to the north<br />

quadrant<br />

• Airline facilities (maintenance hangar) would need to be removed to<br />

make room for the terminal development<br />

• Fuel farm is close to the airlines, who are a major user<br />

64<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Initial list and screening of alternatives<br />

KEY POINTS<br />

• Two terminal<br />

alternatives were<br />

developed for each of<br />

the short-listed land use<br />

plans<br />

• Initial evaluation<br />

reduced the terminal<br />

alternatives from four to<br />

two<br />

This section describes the development and evaluation of<br />

the terminal complex alternatives. Alternatives were<br />

formulated to meet the requirements documented in the<br />

facility requirements section.<br />

<strong>Terminal</strong> area alternatives were developed and evaluated<br />

through an integrated and collaborative approach.<br />

Working in close collaboration with executive management<br />

at the Des Moines International Airport and the <strong>Terminal</strong><br />

<strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong> Advisory Committee, a set of goals and<br />

objectives were established for the Master <strong>Plan</strong> project.<br />

The goals and objectives identified were:<br />

• Develop a long-term solution to the obsolescence of the<br />

existing passenger terminal complex and its lack of<br />

capacity expansion potential<br />

• Provide a comprehensive look at each of the Airport’s<br />

functional components to ensure that corresponding<br />

components could grow and meet projected demands<br />

• Propose a terminal plan that is functional, affordable,<br />

and enhances the overall passenger experience<br />

An initial set of alternatives was formulated based on longterm<br />

development options to inform near-term strategies.<br />

Aircraft gate capacity was studied to identify potential for<br />

growth at both the south air cargo site and the existing<br />

terminal site. Through primary screening of the initial<br />

alternatives, two options were selected for further<br />

development. Detailed plans and cost estimates were then<br />

prepared for the shortlist alternatives, which were subject<br />

to secondary screening evaluation. These screening<br />

criteria were established to evaluate financial, operational,<br />

and environmental impacts of each alternative, which led<br />

to the ultimate selection of a preferred terminal<br />

alternative. Figure 50 illustrates a flowchart of the<br />

terminal alternatives screening process.<br />

Initial <strong>Terminal</strong> <strong>Area</strong> Alternatives<br />

Informed by the two short-listed land use alternatives<br />

addressed in the previous section, two potential sites were<br />

identified for passenger terminal area development – the<br />

current south air cargo site and the existing terminal area.<br />

Four initial terminal alternatives were generated to explore<br />

and understand the feasibilities and constraints on each<br />

site. Figure 51 shows two alternatives on the south air<br />

cargo site – Alternatives 1 and 2. Alternative 1 capitalizes<br />

on the existing cargo apron for the initial 14 gates required<br />

by 3.0 MAP, which requires some demolition of existing<br />

facilities to implement. On the other hand, Alternative 2<br />

requires demolition of four existing aircraft hangars and a<br />

cargo sorting facility to the west in order to build the new<br />

aircraft apron needed to meet gate demand. This option<br />

imposes more disruptions to current airport operations as<br />

compared to Alternative 1. Both options require construction<br />

of a full-length parallel taxiway southwest of Runway 13-31 as<br />

well as new access roadways and a 4-level garage to support<br />

the concept. The full-build 18 gates scenario is shown on<br />

both options meeting 4.0 MAP requirements.<br />

Figure 52shows two alternatives on the existing terminal site<br />

– Alternative 3 and 4. Alternative 3 indicates a new terminal<br />

Figure 50<br />

Flow Chart of <strong>Terminal</strong> Alternatives Screening Process<br />

Des Moines International Airport<br />

and concourse offset to the northwest of the existing<br />

terminal, which would require complex phasing to construct<br />

while the Airport remains in operation. Alternative 4 is easier<br />

to phase with the new terminal located just north of the<br />

existing, providing the least amount of disruption to existing<br />

operations during construction. Since Alternative 3 imposes<br />

the most disruptions to current Airport operation, which<br />

could be expensive and a cause for passenger dissatisfaction,<br />

this option was quickly dismissed as an infeasible alternative.<br />

Based on the pros and cons described herein, the <strong>Terminal</strong><br />

<strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong> Advisory Committee selected <strong>Terminal</strong><br />

Alternatives 1 and 4, representing the south cargo site and<br />

the existing terminal site, respectively, for further refinement.<br />

65<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Long-list terminal alternatives<br />

Figure 51<br />

Long-list <strong>Terminal</strong> Alternatives – South Air Cargo Site<br />

Des Moines International Airport<br />

Figure 52<br />

Long-list <strong>Terminal</strong> Alternatives – Existing <strong>Terminal</strong> Site<br />

Des Moines International Airport<br />

shortlisted<br />

TERMINAL<br />

ALTERNATIVE 1<br />

TERMINAL<br />

ALTERNATIVE 3<br />

TERMINAL<br />

ALTERNATIVE 2<br />

shortlisted<br />

TERMINAL<br />

ALTERNATIVE 4<br />

66<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Short-listed <strong>Terminal</strong> Alternative 1<br />

<strong>Terminal</strong> Alternative 1<br />

Figures 53 and 54 show the more developed Alternative 1<br />

with a two-level terminal processor at approximately 250<br />

feet deep by 600 feet wide that’s centrally located on the<br />

existing aircraft apron. Both passenger processing for<br />

departures and arrivals are located on the ground level,<br />

with the security screening checkpoint and a single-loaded<br />

concourse (approximately 80 feet wide) running along the<br />

northwest-southeast direction situated on the second<br />

level. The linear concourse is configured to accommodate<br />

18 gates, required by 4.0 MAP, with expansion capabilities<br />

on both the southeast or southwest end, as shown dashed.<br />

A four-level parking garage is provided directly across from<br />

the terminal processor with an elevated pedestrian bridge<br />

linking Level 2 of the garage to the second level security<br />

screening checkpoint for passenger convenience. The<br />

public garage footprint measures approximately 360 feet deep by<br />

840 feet wide and can hold roughly 1,080 parking spaces on each<br />

level with Level 1 dedicated for rental car ready/return<br />

operations. Future expansion is available directly to the east and<br />

west of the proposed garage.<br />

Additional required infrastructure includes new terminal access<br />

roadways and two parallel terminal curbsides - with an inner<br />

curb to serve private vehicles and an outer curb dedicated to<br />

commercial vehicles. The terminal loop road wraps around the<br />

Airport’s existing fuel farm facility to avoid expensive relocation<br />

costs. A new fuel access road is shown west of the existing fuel<br />

farm to provide vehicular access to the fuel farm and airport<br />

maintenance facilities that will remain in this area. A 340-space<br />

employee surface parking lot is provided west of the new parking<br />

garage and a potential hold lot is shown north of the existing<br />

surface Lot #4 (existing rental car stacking and storage lot).<br />

The existing parking garages will be converted to provide<br />

remote parking and a new shuttle route will be needed to<br />

transfer passengers between the facilities potential. Future<br />

expansion sites for surface parking lots are shown dashed on<br />

Figure 54.<br />

For safety reasons (avoiding crossing an active runway) a fulllength<br />

parallel taxiway southwest of Runway 13-31, as shown in<br />

Figure 53, is required if a passenger terminal building is built on<br />

this site. A west deicing pad able to accommodate two<br />

narrowbody aircraft, parked side-by-side, as well as additional<br />

apron to park four remain overnight (RON) positions on the far<br />

west end and three RON positions on the far east end are also<br />

needed as a part of this terminal alternative.<br />

Figure 53<br />

<strong>Terminal</strong> Alternative 1 – 3D Massing Overview<br />

Des Moines International Airport<br />

Figure 54<br />

<strong>Terminal</strong> Alternative 1 – Full Build Scenario (18 Gates)<br />

Des Moines International Airport<br />

Aerial Source: Google Earth<br />

67<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Short-listed <strong>Terminal</strong> Alternative 1<br />

<strong>Terminal</strong> Phasing<br />

<strong>Terminal</strong> Alternative 1 should be constructed in two phases –<br />

Phases 1 and 2, as shown on Figure 55. Enabling projects are<br />

organized as Phase 0.<br />

Phase 0 requires relocation of Signature Flight Support from<br />

the existing east quadrant into the Iowa Air National Guard<br />

(IANG) site to the north. As of the writing of this document,<br />

the Airport is in discussions with IANG personnel regarding<br />

the ultimate makeup of the IANG facilities , although it is<br />

assumed a portion will be given back to the Airport since the<br />

IANGs mission has changed and there are facilities they no<br />

longer need or can support. The Airport plans to convert<br />

approximately 18 acres of the IANG site, located immediately<br />

west of the existing north general aviation quadrant, into a<br />

new and consolidated Fixed Based Operator / General<br />

Aviation facility. Once Signature Flight Support vacates the<br />

east quadrant, the air cargo operators will relocate to this site<br />

and allow for demolition and site preparation to take place at<br />

the south cargo site. A new fuel access road will also be<br />

constructed in this phase to provide dedicated access to the<br />

fuel farm and airport maintenance facilities while demolition<br />

takes place.<br />

Phase 1 is the first construction phase that requires building a<br />

full-length parallel taxiway on the southwest side of Runway<br />

13-31 in order to operate the new south passenger terminal.<br />

The entire terminal processor, a linear concourse - singleloaded<br />

- to accommodate 14 aircraft gates (meeting 3.0 MAP<br />

requirements) with 4 narrowbody RON parking positions<br />

west of the new terminal building will also be built under this<br />

phase. This concourse configuration takes full advantage of<br />

the existing cargo apron with a small apron addition needed<br />

at the northwest corner to serve as a west deicing pad able<br />

to park two side-by-side narrowbody aircraft. New terminal<br />

access roadways, curbsides, Air Operations <strong>Area</strong> (AOA)<br />

perimeter fences, first phase of the new 4-level parking<br />

garage (610 spaces per level) with rental car ready/return on<br />

Level 1, a customer service building with an elevated<br />

pedestrian bridge, and a temporary surface lot east of the<br />

new garage to hold 430 parking spaces are also shown to<br />

occur in Phase 1. A new shuttle route along the existing<br />

Airport Frontage Road will be needed to transfer passengers<br />

between the new passenger terminal to the existing parking<br />

garages (to be converted into remote parking spaces). A<br />

340-space employee parking lot east of the new parking<br />

garage and a potential hold lot along the new shuttle route<br />

will also be provided during this phase.<br />

Phase 2 will require demolition of Building 31, the south<br />

cargo building, prior to the new apron construction needed<br />

to provide 4 additional aircraft gates (for a total of 18 gates)<br />

and 3 remain overnight (RON) aircraft parking positions to<br />

meet passenger demand at 4.0 MAP. The 4-level parking<br />

garage will be expanded to the east to handle a total of<br />

1,080 parking spaces per level. Two potential lots are<br />

identified east of the new parking garage to accommodate<br />

future parking demands (shown dashed on Figure 55).<br />

Cost Estimates<br />

The costs to build <strong>Terminal</strong> Alternative 1 are shown in Table 23<br />

below. Separate cost estimates were developed for the flat<br />

work (civil engineering) and vertical (buildings) portions of the<br />

proposed development, using different estimators specializing<br />

in those areas. Construction costs are the hard costs associated<br />

with the construction of the facilities; while soft costs include<br />

items such as design, construction administration, and<br />

contingencies. As this is a conceptual plan, there are generous<br />

contingencies (calculated based on a percentage of the<br />

construction cost estimates) build into the soft costs. At this<br />

initial stage of plan development, the cost to build <strong>Terminal</strong><br />

Alternative 1 to accommodate 14 gates is approximately $464<br />

million, with another $57 Million to add four gates in Phase 2.<br />

Table23<br />

<strong>Terminal</strong> Alternative 1 – Rough Order of Magnitude Cost Summary<br />

Des Moines International Airport<br />

Source: Foth Infrastructure & Environment; and<br />

CONNICO, December 2013<br />

68<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

<strong>Terminal</strong> Alternative 1 - phasing<br />

Figure 55<br />

<strong>Terminal</strong> Alternative 1 - Phasing <strong>Plan</strong>s<br />

Des Moines International Airport<br />

Phase 1 work:<br />

1. Construct new fulllength<br />

taxiway<br />

2. Build new terminal<br />

and apron for 14<br />

gates and 4 RON<br />

positions<br />

3. Construct deicing<br />

pad for 2 side-byside<br />

narrowbody<br />

aircraft<br />

4. Construct new<br />

roadways and<br />

curbsides<br />

5. Build Phase 1 of<br />

new 4-level garage<br />

structure,<br />

employee parking<br />

and hold lot<br />

EXISTING SOUTH AIR CARGO SITE<br />

PHASE 1 (14 GATES)<br />

Phase 0 work:<br />

1. Relocate<br />

“Signature” FBO<br />

to Iowa Air<br />

National Guard<br />

(IANG) site<br />

2. Relocate Air<br />

Cargo to old<br />

“Signature” site.<br />

3. Demolish existing<br />

buildings and<br />

access roads as<br />

shown dashed<br />

4. Build new fuel<br />

access road<br />

PHASE 0<br />

Phase 2 work:<br />

1. Demolish Building<br />

31 (South Cargo<br />

Building) prior to<br />

construction of<br />

Phase 2<br />

2. Construct new<br />

apron for 4 gates<br />

and 3 RON<br />

positions<br />

3. Construct Phase 2<br />

of new 4-level<br />

garage structure<br />

PHASE 2 (18 GATES)<br />

69<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Short-listed <strong>Terminal</strong> Alternative 4<br />

<strong>Terminal</strong> Alternative 4<br />

The existing terminal complex sits on an already constrained<br />

site in the east quadrant, framed by the two runways on the<br />

west and Fleur Drive, a major traffic thoroughfare, to the east.<br />

Figures 56 and 57 below show a concept for the development<br />

of Alternative 4, which takes into account these physical<br />

constraints.<br />

Alternative 4 was developed with a main intent to explore<br />

viable terminal options on the east quadrant that makes full<br />

use of existing infrastructures to minimize construction cost.<br />

As shown on the full build scenario on Figure 57, a new twolevel<br />

terminal processor (250 feet deep by 600 feet wide) is<br />

strategically located parallel to Runway 5-23, rotated roughly<br />

45° east of the existing terminal structure. This placement<br />

would allow construction of the first terminal sub phase to<br />

have the least amount of impact to current airport operations.<br />

Similar to <strong>Terminal</strong> Alternative 1, both passenger processing<br />

for departures and arrivals are located on the ground level,<br />

with the security screening checkpoint and the singleloaded<br />

main concourse (approximately 80 wide) running<br />

along the southwest-northeast orientation on the second<br />

level. The linear concourse with an angled bend at the<br />

southwest end is configured to accommodate 18 gates,<br />

required by 4.0 MAP, with expansion capabilities on the<br />

southwest end to accommodate two additional aircraft<br />

gates, as shown dashed.<br />

A new four-level parking garage is provided directly across<br />

from the terminal processor, parallel to the new terminal<br />

curbsides, and attached to the northwest corner of the<br />

existing north parking garage. The public garage footprint is<br />

approximately 126,000 square feet, able to hold roughly<br />

450 parking spaces on each level with Level 1 dedicated to<br />

rental car operation.<br />

For passenger convenience, an elevated pedestrian bridge is<br />

provided, linking Level 2 of the public garage to the second level<br />

security screening checkpoint. A surface lot (approximately<br />

45,000 square feet), adjacent to the new garage, is needed to<br />

supplement the rental car ready/return spaces in the garage.<br />

New terminal access roadways and dual terminal curbsides -<br />

with an inner curb to serve private vehicles and an outer curb<br />

dedicated to commercial vehicles – are provided to address<br />

some of the operational and safety concerns that were<br />

discussed in the Existing Conditions section of this report.<br />

Considerations addressed include, limiting to two decision<br />

points at intersections, creating a more defined channelization<br />

from toll booths and merges on Cowles Drive, and providing<br />

appropriate distances between decision points.<br />

Figure 56<br />

<strong>Terminal</strong> Alternative 4 – 3D Massing Overview<br />

Des Moines International Airport<br />

Figure 57<br />

<strong>Terminal</strong> Alternative 4 – Full Build Scenario (18 Gates)<br />

Des Moines International Airport<br />

Aerial Source: Google Earth<br />

70<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Short-listed <strong>Terminal</strong> Alternative 4<br />

A west deicing pad able to accommodate two narrowbody<br />

aircraft, parked side-by-side, as well as additional apron to<br />

park 2 RON positions on the far northeast corner and 5 RON<br />

positions north of Runway 31are also needed as a part of<br />

this terminal alternative.<br />

<strong>Terminal</strong> Phasing<br />

<strong>Terminal</strong> Alternative 4 will be constructed in two phases –<br />

Phases 1 and 2, as shown on Figure 58.<br />

Phase 0 requires relocation of Signature Flight Support,<br />

currently located north of the existing terminal building, into<br />

the Iowa Air National Guard (IANG) site that’s still under<br />

negotiations to return to the Airport. The Airport plans to<br />

convert this approximately 18 acres IANG site, immediately<br />

west of the existing north general aviation quadrant, into a<br />

new and consolidated Fixed Based Operator / General<br />

Aviation facility. Once Signature Flight Support vacates the<br />

east quadrant, demolition of the existing hangars and access<br />

roadways should occur. Construction of the first part of the<br />

new roadway system should then begin under this phase,<br />

which ties into the existing curbsides.<br />

Phase 1 is the first construction phase that will be built in<br />

two sub-phases: Phases 1A and 1B. The first part of the<br />

terminal processor, including the entire check-in/outbound<br />

baggage makeup area and a portion of the baggage<br />

claim/inbound baggage makeup area with an 8-gate linear<br />

concourse on the far northeast corner of the site will be<br />

built under Phase 1A. This allows construction to happen<br />

simultaneously while the Airport remain in operation at the<br />

existing terminal. Additional apron space to accommodate 2<br />

narrowbody remain overnight (RON) parking positions, a<br />

taxilane with the associated west deicing pad to park two<br />

side-by-side narrowbody aircraft should also be provided. A<br />

temporary link from the existing check-in lobby to the new<br />

processor is shown. Upon completion of Phase 1A, when<br />

the new 8-gate concourse begins operation, demolition of<br />

the existing 7-gate Concourse C should commence. For a<br />

short duration, the Airport will need to operate out of two<br />

separate facilities – 4 gates out of the remaining existing<br />

terminal and 8 gates out of the new terminal building on the<br />

northeast end.<br />

Phase 1B will include constructing the second part of the<br />

new terminal processor, a 6-gate concourse and the<br />

associated apron area when demolition of Concourse C is<br />

complete. Remainder of the new terminal access roadways,<br />

curbsides, Air Operations <strong>Area</strong> (AOA) perimeter fences will<br />

also be constructed in this phase. First part of the new 4-<br />

level parking garage at a footprint of approximately 72,500<br />

square feet (260 spaces per level) with rental car<br />

ready/return on Level 1 and public parking on Levels 2-4 will<br />

be required to meet 3.0 MAP demands. Directly adjacent<br />

to the garage is a customer service building with an elevated<br />

pedestrian bridge that links back to the second level security<br />

screening checkpoint at the new terminal building.<br />

Expansion of the economy parking lot to 400 spaces<br />

(approximately 112,000 square feet) and construction of a<br />

small surface lot southwest of the new garage to<br />

supplement RAC ready/return spaces in the garage are also<br />

needed. Remainder of the existing terminal and concourse<br />

can be demolished at the end of Phase 1B.<br />

Phase 2 will require construction of a new concourse extension<br />

to accommodate 4 additional aircraft gates for a total of 18<br />

gates to meet 4.0 MAP requirements. It will also require<br />

expanding the new 4-level garage by 190 spaces per level, at a<br />

footprint of approximately 53,600 square feet. Level 1 remains<br />

for RAC ready/return and Levels 2-4 are used for public parking.<br />

Economy Lot #4 will be converted entirely to RAC Quick Turn<br />

Around (QTA), staging, and storage. Construction of a 1,500<br />

space remote surface lot (approximately 420,000 square feet)<br />

for public parking is also needed in this phase.<br />

Cost Estimates<br />

The costs to build <strong>Terminal</strong> Alternative 4 are shown in Table 24.<br />

As this is a conceptual plan, there are generous contingencies<br />

(calculated based on a percentage of the construction cost<br />

estimates) build into the soft costs. At this initial stage of plan<br />

development, the cost to build <strong>Terminal</strong> Alternative 4 to<br />

accommodate 14 gates is approximately $363 million, with<br />

another $53 million to add four gates in Phase 2.<br />

Table 24<br />

<strong>Terminal</strong> Alternative 4 – Rough Order of Magnitude Cost Summary<br />

Des Moines International Airport<br />

Source: Foth Infrastructure & Environment; and CONNICO, December 2013<br />

71<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

<strong>Terminal</strong> Alternative 4 - phasing<br />

Figure 58<br />

<strong>Terminal</strong> Alternative 4 - Phasing <strong>Plan</strong>s<br />

Des Moines International Airport<br />

Phase 0:<br />

1. Relocate<br />

“Signature” FBO<br />

to Iowa Air<br />

National Guard<br />

(IANG) site<br />

2. Demolish existing<br />

buildings and<br />

access roads as<br />

shown dashed<br />

3. Build first part of<br />

new roadways<br />

PHASE 0<br />

Phase 1b:<br />

1. Build remainder of<br />

new terminal<br />

processor, 6 gate<br />

concourse and<br />

apron<br />

2. Construct<br />

remainder of new<br />

roadways<br />

3. Build first part of<br />

new 4-level garage<br />

structure with RAC<br />

on Level 1, parking<br />

on Levels 2 to 4<br />

4. Expand economy<br />

parking lot to 400<br />

spaces (112,000 sf)<br />

5. Demolish<br />

remainder of<br />

existing concourse<br />

and terminal at the<br />

end of this phase<br />

PHASE 1B (14 GATES)<br />

Phase 1a:<br />

1. Build first part of<br />

new terminal<br />

processor, 8 gate<br />

concourse and<br />

apron for 2 RON<br />

positions<br />

2. Build temporary<br />

link from existing<br />

ticketing lobby to<br />

new processor<br />

3. Construct new<br />

deicing pad and<br />

taxilane for 2<br />

side-by-side<br />

narrowbody<br />

aircraft<br />

4. Demolish existing<br />

Concourse C at<br />

end of this phase.<br />

PHASE 1A (8 GATES)<br />

Phase 2:<br />

1. Construct new<br />

concourse<br />

expansion and<br />

apron for 4<br />

additional gates<br />

and 5 RON<br />

positions<br />

2. Build garage<br />

expansion<br />

3. Convert all of Lot<br />

#4 to RAC<br />

storage/QTA<br />

4. Construct 1,500<br />

remote surface<br />

public parking<br />

spaces (420,000 sf)<br />

PHASE 2 (18 GATES)<br />

72<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


<strong>Terminal</strong> Alternatives<br />

Evaluations matrix and selection of preferred terminal alternative<br />

Selection of Preferred <strong>Terminal</strong> Alternative<br />

<strong>Terminal</strong> Alternative 1 was selected as the preferred<br />

terminal alternative by the <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong><br />

Advisory Committee.<br />

Figure 59<br />

<strong>Terminal</strong> Alternative Evaluations Matrix<br />

Des Moines International Airport<br />

During Workshop #3, the two terminal alternatives were<br />

presented by the planning team. In addition, an evaluation<br />

matrix, shown in Figure 59, was also presented and<br />

explained. The evaluation matrix uses “stop light” chart<br />

graphics to describe how the respective terminal<br />

alternatives are judged against established criteria. The<br />

matrix does not factor in the fact that some criteria may be<br />

more important than others. However, from the<br />

discussions that took place among the Advisory Committee<br />

members, two criteria were regarded as perhaps most<br />

important in making this decision – long range expansion<br />

capability and passenger experience. <strong>Terminal</strong> Alternative<br />

1 clearly has the ability to add more gates (needed beyond<br />

the planning timeframe) than <strong>Terminal</strong> Alternative 4. With<br />

regard to the passenger experience, the fact that <strong>Terminal</strong><br />

Alternative 1 could be built while not disturbing existing<br />

passenger operations, was considered important.<br />

Criteria Alternative 1<br />

(South Cargo)<br />

Passenger Experience<br />

Flexibility<br />

Ease of Phasing<br />

Phasing Options<br />

Alternative 4<br />

(Existing <strong>Terminal</strong>)<br />

Best<br />

The financial feasibility of both terminal alternatives was<br />

also discussed during Workshop #3. At this initial<br />

conceptual stage, it would be challenging for the Airport to<br />

implement either <strong>Terminal</strong> Alternative 1 or 4. To make it<br />

viable financially, significant additional monies, outside of<br />

the typical funding scenarios, would need to be raised.<br />

The Financial Feasibility section of this report addresses<br />

that in more detail.<br />

Long-Range Expansion Capability<br />

Operational Efficiency<br />

Financial Feasibility<br />

Environmental<br />

Worst<br />

Compatibility with Airport Projects<br />

Impact to Stakeholders<br />

73<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


PREFERRED ALTERNATIVES REFINEMENTS<br />

• Preferred Land Use Alternative Refinements<br />

• Preferred <strong>Terminal</strong> Alternative Refinements<br />

• Project Implementation <strong>Plan</strong>


Preferred Land Use Alternative<br />

Land use plan refinements<br />

This section of the technical report presents refinements to<br />

the land use plan and to the preferred terminal alternative,<br />

<strong>Terminal</strong> Alternative 1. It documents the evolution of the<br />

plans from rough concepts to more refined concepts. This<br />

is a key aspect of the overall project as each round of<br />

refinement yields a better, more efficient plan. The initial<br />

round of refinement on <strong>Terminal</strong> Alternative 1 yielded cost<br />

reductions in the $60-$70 million range. This is typical of<br />

such a planning process and it is reasonable to assume<br />

that as this plan moves from the conceptual stage to an<br />

even more refined planning and programming stage (prior<br />

to actual architectural and engineering design) additional<br />

efficiencies will be found.<br />

Preferred Land Use Alternative:<br />

Based on the selection of <strong>Terminal</strong> Alternative 1 as the<br />

preferred terminal alternative, Land Use Alternative 3<br />

becomes the preferred land use alternative, as shown on<br />

Figure 60. Based on discussions among Airport senior<br />

leadership, the Advisory Committee, and the planning<br />

team, the following refinements were made to the land<br />

use plan:<br />

• Combined General Aviation (T-hangars) and Iowa Air<br />

National Guard (IANG) land use designations on the<br />

northwest corner of the Airport to allow flexibility in<br />

land use to accommodate future IANG occupancy<br />

changes.<br />

• Identified the west quadrant of the Corporate General<br />

Aviation land use as areas currently under negotiations<br />

with IANG to return to the Airport.<br />

Figure 60<br />

Preferred Land Use Alternative<br />

Des Moines International Airport<br />

75<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preferred <strong>Terminal</strong> Alternative<br />

Figure 61<br />

Preferred <strong>Terminal</strong> Alternative – 3D Massing Overview<br />

Des Moines International Airport<br />

Aerial Source: Google Earth<br />

76<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preferred <strong>Terminal</strong> Alternative<br />

<strong>Terminal</strong> alternative refinements<br />

KEY POINTS<br />

• Several refinements<br />

were made to the layout<br />

of the concourse, rental<br />

counter and bag claim<br />

plans<br />

• Size of parking garage in<br />

Phase 1 reduced, with<br />

close-in surface parking<br />

added<br />

• <strong>Terminal</strong> roadways<br />

reconfigured to optimize<br />

automobile flow<br />

<strong>Terminal</strong> Alternative 1 was selected by the <strong>Terminal</strong> Advisory<br />

Committee as the preferred terminal alternative. Refinements<br />

were then incorporated into the preferred terminal alternative<br />

with the primary goals to reduce project cost and improve<br />

operational efficiencies. Refinements include:<br />

Airfield and <strong>Terminal</strong> -<br />

• Added a second deicing pad and aircraft apron for 3 RON<br />

positions to the east<br />

• Reduced concourse footprint by shortening concourse<br />

length and double-loading end gates<br />

• Reduced terminal footprint by eliminating in-terminal RAC<br />

counters and rotating baggage claim devices 90 degrees to<br />

decrease terminal depth<br />

• Extended pedestrian bridge connector from garage to upper<br />

level security screening checkpoint for passengers with no<br />

bags to check<br />

Parking and Roadways –<br />

• Relocated rental car counters from terminal to a<br />

separate customer service building adjacent to the<br />

garage where rental car ready/return is located to<br />

provide improved customer experience<br />

• Reduced garage size in Phase 1 and added close-in<br />

surface parking to provide “product” diversity<br />

• Removed “hold lot” and employee parking lots from<br />

South Cargo site<br />

• Reconfigured terminal roadways for more efficient<br />

flow<br />

As shown on Figures 62 and 63, the refined preferred<br />

terminal alternative indicates a linear concourse parallel<br />

to Runway 13-31 that is able to accommodate 18 aircraft<br />

gates to meet 4.0 MAP requirements. A two-level<br />

terminal building is centrally located to the concourse<br />

for passenger processing.<br />

On the ground level, passenger Check-in can be found to the<br />

east and Baggage Claim to the west of the terminal building.<br />

Security screening checkpoint is centrally located on the upper<br />

level with a direct link to the 4-level parking garage immediately<br />

southwest of the terminal building.<br />

The new parking garage is able to hold a total of 2,320 spaces<br />

(580 per level) with the entire first level dedicated to rental car<br />

operation. Footprint of the garage is approximately 173,000<br />

square feet with sloping floor ramps. A 5,200 square feet rental<br />

car customer service building is located just north of the new<br />

parking garage. Two surface lots are shown to the east and west<br />

of the parking garage, each to accommodate approximately 600<br />

uncovered parking spaces. The existing parking garage and<br />

surface lots will provide remote parking spaces via a shuttle<br />

route along the South Airport Frontage Road to transfer<br />

passengers to and from the new passenger terminal.<br />

Figure 62<br />

Preferred <strong>Terminal</strong> Alternative – 3D Massing Overview<br />

Des Moines International Airport<br />

Figure 63<br />

Preferred <strong>Terminal</strong> Alternative – Full Build Scenario (18 Gates)<br />

Des Moines International Airport<br />

77<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preferred <strong>Terminal</strong> Alternative<br />

Phase 1 to provide capacity until 2042<br />

New terminal access roadways entering from SW 28 Street,<br />

directly off of Army Post Road, are provided with two<br />

terminal curbs - an inner curb to serve private vehicles and<br />

an outer curb for commercial vehicles. The terminal loop<br />

road avoids the Airport’s existing fuel farm facility in order<br />

to avoid expensive relocation cost. A separate utility road is<br />

shown west of the existing fuel farm to provide vehicular<br />

access to the airport fuel farm and maintenance support<br />

facilities located southwest of the new terminal complex.<br />

<strong>Terminal</strong> Phasing<br />

The preferred terminal alternative will require two main<br />

construction phases to implement – Phases 1 and 2, as<br />

shown on Figure 64. Phase 0 is a demolition and<br />

preparation phase.<br />

Phase 1 is the first construction phase that will be built in<br />

two sub-phases: Phases 1A and 1B. Intent is for the Airport<br />

to start operating out of the new passenger terminal at the<br />

completion of Phase 1A, while Phase 1B is under<br />

construction. Phase 1A requires construction of a new fulllength<br />

parallel taxiway southwest of Runway 13-31, the<br />

entire terminal processor and a portion of the concourse to<br />

accommodate 14 aircraft gates with 4 narrowbody remain<br />

overnight (RON) parking positions west of the new terminal<br />

building. This configuration takes full advantage of the<br />

existing cargo apron with new apron space needed to<br />

handle the west deicing pad to park two side-by-side<br />

narrowbody aircraft. New terminal access roadways,<br />

curbsides, Air Operations <strong>Area</strong> (AOA) perimeter fences, first<br />

phase of the new 4-level parking garage with rental car<br />

ready/return on Level 1, the customer service building with<br />

an elevated pedestrian bridge, and a small surface lot west<br />

of the new garage to hold 270 parking spaces are also<br />

required in Phase 1A. The shuttle route used to transfer<br />

passengers between the new passenger terminal to the<br />

existing parking garages for remote parking should also be<br />

in-place under this sub-phase. Phase 1B would require<br />

construction of a new apron for the east deicing pad to<br />

accommodate 2 additional side-by-side narrowbody aircraft,<br />

and new aircraft apron east of the new concourse to handle<br />

4 RON parking positions.<br />

Aerial Source: Google Earth<br />

Most of the facilities will need to be expanded in Phase 2 to<br />

meet 4.0 MAP passenger demand. A new hammerhead<br />

concourse, to the east on the second level, is required to<br />

handle 4 additional contact gates for a total of 18 aircraft<br />

gates needed by 4.0 MAP. Due to this demand, new apron is<br />

provided south of the east deicing pad to accommodate 3<br />

displaced narrowbody RON parking positions under this<br />

phase. The 4-level parking garage will be expanded to the<br />

east to accommodate an additional 600 parking spaces total,<br />

equivalent to 150 spaces on each level. A new 600 space<br />

surface lot is required to the east of the parking garage and<br />

an additional 330 spaces are required on the west surface lot.<br />

Additional terminal curb lengths, both inner and outer, are<br />

also required to meet passenger demand.<br />

Cost Estimates<br />

Table 25 provides a summary of the order of magnitude cost<br />

estimates for the preferred development alternative. Through<br />

a series of refinements to the initial plan, the total cost of the<br />

program was reduced from the initial $520 million to $468<br />

million. The costs are broken down by civil projects, buildings,<br />

and enabling projects. Enabling projects are necessary to<br />

allow for the major terminal complex elements to be<br />

constructed. Phase 1 costs are the most important for this<br />

planning effort as they are the focus of the financial capacity<br />

analysis. Phase 2 will not need to be implemented until about<br />

2042.<br />

Table 25<br />

Preferred <strong>Terminal</strong> Alternative - Refined Order Of Magnitude Cost Summary<br />

Des Moines International Airport<br />

78<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preferred <strong>Terminal</strong> Alternative<br />

<strong>Terminal</strong> phasing plans<br />

Figure 64<br />

Preferred <strong>Terminal</strong> Alternative – Phasing <strong>Plan</strong>s<br />

Des Moines International Airport<br />

Footnote:<br />

1/ T-hangar demolition and relocation<br />

not included in the terminal project<br />

financial analysis or cost estimates<br />

Phase 0 work:<br />

1. Relocate “Signature” FBO<br />

to Iowa Air National<br />

Guard (IANG) site<br />

2. Relocate FedEx to IANG<br />

site<br />

3. Demolish existing<br />

buildings and access<br />

roads as shown dashed<br />

4. Build new fuel access<br />

road<br />

5. Relocate UPS to<br />

“Signature” site once<br />

new terminal is open for<br />

operation<br />

PHASE 0<br />

Phase 1A work:<br />

1. Construct new full-length<br />

taxiway<br />

2. Build new terminal and<br />

apron for 14 gates and 4<br />

remain overnight parking<br />

(RON) positions<br />

3. Construct west deicing<br />

pad to accommodate 2<br />

side-by-side narrowbody<br />

aircraft<br />

4. Construct new roadways,<br />

curbsides and AOA fence<br />

5. Build new 4-level parking<br />

garage with rental car<br />

ready/return on Level 1<br />

6. Build new RAC Customer<br />

Service Building and<br />

elevated pedestrian<br />

bridge<br />

7. Construct new surface<br />

parking lot<br />

PHASE 1A (14 GATES)<br />

Phase 1B work:<br />

1. Construct east<br />

deicing pad to<br />

accommodate 2<br />

side-by-side<br />

narrowbody aircraft<br />

2. Construct additional<br />

aircraft apron for 4<br />

remain overnight<br />

parking (RON)<br />

positions to the east<br />

PHASE 1B (14 GATES)<br />

Phase 2:<br />

1. Construct new apron<br />

for 3 remain<br />

overnight parking<br />

(RON) positions to<br />

the east<br />

2. Construct new<br />

hammerhead<br />

concourse to the<br />

east<br />

3. Build new garage<br />

expansion<br />

4. Construct new<br />

surface parking lots<br />

5. Extend terminal<br />

curbside<br />

PHASE 2 (18 GATES)<br />

79<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Project Implementation <strong>Plan</strong><br />

Full project phasing<br />

Figure 65<br />

Preferred <strong>Terminal</strong> Alternative – Project Implementation Phasing<br />

Des Moines International Airport<br />

Aerial Source: Google Earth<br />

80<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Project Implementation <strong>Plan</strong><br />

Enabling projects will be key to Phase 1 development phasing<br />

Through extensive collaboration with Airport management<br />

and the Airport’s consulting engineers, a list of enabling<br />

projects was identified prior to implementation of the<br />

preferred terminal project.<br />

Project Implementation Phasing<br />

Figure 65 provides a list of these enabling projects and the<br />

various work required at each phase to implement this<br />

terminal program. The Airport’s successful reclamation of<br />

approximately 18 acres of land (including apron areas)<br />

currently leased to the Iowa Air National Guard (IANG)<br />

located adjacent to the existing north general aviation area<br />

is critical to the overall program schedule. Possession of<br />

this IANG parcel will enable both FedEx and Signature<br />

Flight Support to move into this area and make way for<br />

demolition and preparation of the south cargo site for the<br />

new passenger terminal and the existing Signature site to<br />

become the new air cargo facility. The old 18 acres IANG<br />

parcel will eventually become the new consolidated Fixed<br />

Based Operator (FBO) / General Aviation (GA) facility<br />

situated on the north quadrant of the Airport.<br />

Aside from the suggested terminal phasing mentioned in<br />

the previous section, Phase 1 will also include converting<br />

two existing surface parking lots (Lots #3 and #4) into<br />

employee parking and rental car stacking and storage. At<br />

the completion of Phase 1, and once the new south<br />

passenger terminal is in full operation, the existing<br />

terminal and concourse building will be demolished to<br />

provide expanded apron space to handle cargo operation.<br />

Existing parking garages and surface lots will remain and be<br />

used as remote parking facilities.<br />

Project Implementation Schedule<br />

The project implementation schedule, as shown on Figure<br />

66, indicates the south passenger terminal’s Phase 1 (14<br />

gates) target Date of Beneficial Occupancy (DBO) in 2024.<br />

This informs that airline and terminal tenant coordination<br />

and programming should start no later than the beginning<br />

of 2016. Some enabling tenant relocations, such as<br />

FedEx’s temporary move and Signature’s permanent move<br />

to the old IANG site, which will become the new FBO/GA<br />

facility, should also occur around this time.<br />

<strong>Terminal</strong> site preparation should begin around 2017 when<br />

affected tenants have been relocated to their respective<br />

homes. The new full-length taxiway should start at the<br />

beginning of 2020, and will take several phases to build as<br />

indicated on the schedule. Assuming the new terminal will<br />

take a little more than 2 years to design, this element should<br />

start at the beginning of 2019. Accounting for approximately<br />

9 months for general contractor’s bidding, negotiations,<br />

Figure 66<br />

Preferred <strong>Terminal</strong> Alternative – Project Implementation Schedule<br />

Des Moines International Airport<br />

staging and coordination, and an estimated 2 years to<br />

construct, terminal construction should begin no later than<br />

early 2022 in order to meet the target DBO at the end of 2023.<br />

Construction of the apron, deicing pads and parking garage,<br />

rental car service building are independent projects; therefore,<br />

could occur concurrent to the terminal construction<br />

timeframe. Demolition of the existing terminal should begin in<br />

2024.<br />

81<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


PRELIMINARY FINANCIAL CAPACITY ANALYSIS<br />

• Key Drivers<br />

• Industry Benchmarks<br />

• Preliminary <strong>Plan</strong> of Finance<br />

• Sensitivity Analyses and Financial Conclusions


Preliminary Financial Capacity Analysis<br />

Overview and Key Assumptions<br />

KEY POINTS<br />

• A comprehensive<br />

financial model was<br />

used to assess the<br />

reasonableness of the<br />

proposed terminal<br />

development program<br />

• Key financial drivers<br />

were developed jointly<br />

with the Airport<br />

This section of the technical report documents the<br />

preliminary financial capacity analyses conducted as<br />

part of the <strong>Terminal</strong> <strong>Area</strong> <strong>Concept</strong> <strong>Plan</strong>. Financial<br />

results were projected using a comprehensive<br />

financial planning model, and are considered high<br />

level preliminary results based on the conceptual<br />

nature of the <strong>Plan</strong>. The initial capacity analysis was<br />

conducted on two alternatives: <strong>Terminal</strong> Alternative 1<br />

and <strong>Terminal</strong> Alternative 4. Following the Advisory<br />

Committee’s selection of <strong>Terminal</strong> Alternative 1 as the<br />

preferred terminal alternative, and the refinement of<br />

the physical plan, a revised financial capacity analysis<br />

was conducted. Stress tests were also performed to<br />

test sensitivity to key variables.<br />

Key drivers<br />

Many factors (drivers) and assumptions went into the<br />

preparation of the preliminary financial capacity<br />

analysis. These key drivers are listed and discussed<br />

below.<br />

• Forecast Traffic Activity Levels. – Many of the<br />

sources of airport revenue are derived from activity<br />

projections. The most important of these is the<br />

number of passengers expected to use the airport.<br />

Passenger activity drives a number of key airport<br />

revenues, including terminal concessions, public<br />

parking, rental car, passenger facility charges<br />

(PFCs), as well as AIP grant funding levels.<br />

• Timing of Development – The Date of Beneficial<br />

Occupancy (or “DBO”) is projected to occur in<br />

2024. This is based on the implementation plan<br />

discussed in the previous section. Project costs,<br />

which were estimated in 2014 dollars, are<br />

escalated at 3% per year to the mid-point of<br />

construction to account for inflation, which is the<br />

reason project costs in this section are higher than<br />

those previously stated.<br />

• Project Costs<br />

– Projections of capital expenditures beyond the Authority’s<br />

current 2013 – 2017 Capital Improvement Program (“CIP”)<br />

were developed recognizing the time required to build the<br />

new terminal and need to maintain terminal operations and<br />

level of service. Improvements to the existing terminal are<br />

estimated at $5 million per year from 2016 through 2021;<br />

$4 million in 2018, $3 million in 2019, $2 million in 2020, and<br />

$1 million in 2021<br />

– Soft costs/contingency allowances applied to civil and<br />

vertical project costs<br />

– Escalation rate of 3.0% per year to midpoint of construction<br />

– 3.0 MAP program requirements at DBO<br />

– Post DBO, $2 million per year in capital expenditures net of<br />

grants, escalated at 3% per year from 2014<br />

• Grants<br />

– Federal Airport Improvement Program (AIP)<br />

entitlement/discretionary grants would fund 90% of the<br />

eligible costs of the new terminal taxiway, apron, and deicing<br />

facilities<br />

– AIP “entitlement” grants ($4 million per year) targeted to<br />

new terminal roadways beginning in 2019<br />

– TSA grant of $7 million for new terminal security<br />

infrastructure improvements<br />

– State vertical infrastructure grant for new Signature hangar<br />

of $2.5 million<br />

– Various levels of State and other non-AIP grants were<br />

assumed to meet feasibility targets<br />

• Passenger Facility Charge (PFC) Level<br />

– Current PFC level would remain at $4.50 (base case)<br />

– Sensitivity analyses included PFC levels of $6.00 and $8.50<br />

beginning in 2016, if authorized by Congress as part of the<br />

FAA reauthorization on October 1, 2015<br />

• Rental Car Customer Facility Charge (CFCs)<br />

– Amounts collected pre-DBO in excess of reimbursement for<br />

the Quick Turnaround (QTA) facility to be used for pay-asyou-go<br />

funding of program costs<br />

– Post DBO CFC revenues used to pay debt service on<br />

outstanding General Airport Revenue Bonds (GARBs) for<br />

debt related to rental car facilities (e.g., counters, readyreturn<br />

car parking<br />

• <strong>Plan</strong> of Finance<br />

– 30-year tax-exempt revenue bonds at 6.5% interest rate<br />

issued annually to minimize financing costs<br />

– Interest capitalized through DBO<br />

– Debt service reserve cash funded through bonds<br />

– PFC revenues leveraged on a direct off-set basis (which<br />

requires amendment to bond indenture)<br />

– Signature contributes $2.5 million to its new hangar<br />

• Airline Business Deal<br />

– Existing ratemaking approach.<br />

– Existing leasable space protocols, increase in rented<br />

exclusive use space<br />

– Amortization of existing terminal improvements expire at<br />

DBO and unamortized balance is not recovered<br />

(assuming 10 year amortization for pre-DBO<br />

improvements)<br />

• Operation & Maintenance (O&M) Expenses<br />

– Inflation of 3.5% per year over 2014 budgeted O&M<br />

expenses<br />

– O&M expense increase to reflect increase in gross<br />

terminal square footage<br />

– Increase in parking and rental car O&M expense to reflect<br />

(1) longer shuttle to economy parking (old garage) and<br />

additional patrons to shuttle to old garage and (2) O&M<br />

for new rental car customer service building<br />

– Aircraft Rescue and Firefighting services becomes<br />

Authority responsibility in 2015, resulting in increased<br />

O&M expenses of $1.2 million per year<br />

• Non-Airline Revenues<br />

– <strong>Terminal</strong> concession revenues increase with projected<br />

passenger growth and 2% per year inflation plus 15%<br />

boost in net terminal concession revenue per passenger<br />

at DBO<br />

– Rental car revenues increase with projected passenger<br />

growth and 2% per year inflation<br />

– Daily public parking rates increase $1 per day every three<br />

years beginning in 2018<br />

– Mesaba maintenance base rentals and one-third of UPS<br />

rentals for south site construction discontinued.<br />

– Other revenues increase by 1% per year<br />

83<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preliminary Financial Capacity Analysis<br />

Industry Benchmarks to Gauge Reasonableness<br />

KEY POINTS<br />

• Industry benchmarks<br />

are used as a primary<br />

tool to assess the<br />

reasonableness of the<br />

proposed terminal<br />

development program<br />

• Recently completed and<br />

future capital programs<br />

at other airports are<br />

useful to understand<br />

and to provide context<br />

for evaluating industry<br />

airline cost per<br />

enplaned passenger<br />

data<br />

• Current levels of cost<br />

per enplaned passenger<br />

are not particularly<br />

relevant in terms of<br />

evaluating future<br />

investments<br />

Industry Benchmarks<br />

This element is focused on<br />

benchmark data related to the<br />

financing of capital programs at<br />

comparable large U.S. airports, with<br />

particular focus on comparable<br />

terminal development programs.<br />

Industry benchmarks are used heavily<br />

in this analysis because, on a<br />

preliminary basis, they represent<br />

strong tools for judging the<br />

reasonableness of the terminal<br />

development plan. Airline cost per<br />

enplaned passenger at airports<br />

(CPE)—the total amount paid by<br />

airlines in airport rents and fees<br />

divided by the total number of<br />

passengers enplaned at an airport—is<br />

an accepted industry metric used to<br />

evaluate the “reasonableness” or<br />

“affordability” of current airport<br />

operations and proposed future<br />

airport development.<br />

Following are key metrics that were calculated<br />

for this analysis, as well as an indication of<br />

recommended minimum/maximum levels.<br />

• Airline cost per enplaned passenger (CPE)<br />

– Comparisons with nearby airports with<br />

major terminal programs, as illustrated<br />

on Figure 67<br />

– Comparisons with peer airports (small<br />

and medium hub airports served by<br />

Southwest Airlines) shown on Figure 68<br />

• Airline CPE as a percent of fare revenue<br />

• Airline revenues as a percent of total airport<br />

revenues<br />

• Debt service coverage –airport revenues less<br />

operating expenses divided by<br />

annual debt service payments<br />

• Outstanding debt per enplaned passenger<br />

(DPE), as referenced on Figure 69<br />

• Liquidity or days cash on hand – unrestricted<br />

cash divided by annual operating expenses<br />

• Size of capital program<br />

Figure 67<br />

Airline CPE at Airports With Major <strong>Terminal</strong> Programs<br />

$17.00<br />

$16.00<br />

$15.00<br />

$14.00<br />

$13.00<br />

$12.00<br />

$11.00<br />

$10.00<br />

$9.00<br />

$8.00<br />

$7.00<br />

$6.00<br />

$5.00<br />

$4.00<br />

$3.00<br />

$2.00<br />

$1.00<br />

$0.00<br />

Figure 68<br />

2012 Airline CPE at Peer Airports With Similar Service<br />

75th Percentile<br />

($9.15)<br />

50th Percentile<br />

($7.67 Median)<br />

25th Percentile<br />

($6.33)<br />

Sources: Rating agency reports, FAA Form 5100-127, and Comprehensive Annual Financial <strong>Report</strong>s ("CAFRs").<strong>DSM</strong> 2025 CPE (in 2013$) with new terminal $200M Grant.<br />

$275<br />

$250<br />

$225<br />

$254<br />

Figure 69<br />

Debt per Enplaned Passenger - U.S. Small Hub Airports<br />

$200<br />

$175<br />

$150<br />

$198<br />

$183<br />

$175<br />

$154<br />

$149<br />

$125<br />

$100<br />

$75<br />

$50<br />

$43<br />

$25<br />

$24<br />

$16<br />

$-<br />

Sources: rating agency reports in 2012 and 2013.<br />

Estimated <strong>DSM</strong>* estimated after new after terminal new terminal (2025) (2025) with with $200 $200 million million non-AIP non-AIP grant. grant.<br />

84<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preliminary Financial Capacity Analysis<br />

Preliminary <strong>Plan</strong> of Finance and Establishing Financial Targets<br />

KEY POINTS<br />

• The preliminary plan of<br />

finance, using key<br />

industry metrics as a<br />

guide, shows that the<br />

Airport must secure<br />

$200 million in non-AIP<br />

grants for the terminal<br />

development program to<br />

be affordable.<br />

Preliminary <strong>Plan</strong> of Finance<br />

Due to inflation of construction costs and the project schedule for<br />

the various components of the terminal development plan, the<br />

actual price tag for Phase 1 is $538 M (escalated from $420 M in<br />

2014 dollars). Following are recommendations for funding the<br />

proposed terminal development. The conceptual funding plan as<br />

illustrated on Figure 70 below shows the various sources of funds<br />

for this preliminary plan of finance.<br />

• Grants<br />

– Secure maximum AIP participation in the new terminal<br />

program for apron, taxiway, roadways<br />

– Secure state or other non-Federal grants to achieve financial<br />

affordability<br />

• PFCs<br />

– Amend bond indenture to maximize PFC leveraging via a<br />

direct off-set structure<br />

• Airline Business Deal<br />

– Engage airlines in the new terminal planning discussions<br />

early<br />

– Attempt to negotiate a new airline agreement with<br />

ratemaking that contemplates the new terminal<br />

Figure 70<br />

<strong>Concept</strong>ual Funding <strong>Plan</strong><br />

Credit/Structuring Debt and Establishing Financial Targets<br />

Regarding the Authority’s credit rating, the debt should be<br />

structured to maintain “A” credit rating. Financial targets were<br />

established as follows:<br />

– Airline CPE of < $13.50 (in 2014$)<br />

– CPE as a percent of fare revenues < 6%<br />

– Liquidity/days cash on hand > 365 Days<br />

– Debt per enplaned passenger of < $165<br />

– Debt service coverage of no less than 1.65x<br />

– Airline revenue as a percent of total airport revenue < 45%<br />

Preliminary Financial Projections:<br />

Comparison of Projected Financial Metrics to Targets and Medians<br />

Table 26 below, shows the preliminary results of the financial capacity<br />

analysis, based on how the key financial metrics compare to target<br />

levels. The primary variable shown in the table is the amount of non-<br />

AIP grants ($50M, $165M or $200M) the Airport will need to secure.<br />

The preliminary conclusion is that the Airport will need to secure a<br />

minimum of $200 million in non-AIP grants to meet the key metrics to<br />

be considered reasonable.<br />

Table 26<br />

Financial Metric Comparison<br />

2012 Preferred <strong>Terminal</strong> Alternative - 2025<br />

Moody's Financial Amount of Non-AIP Grant<br />

Financial Metric <strong>DSM</strong> Median* Targets $50 M $165 M $200 M<br />

Cost per enplaned passenger $8.90 $6.73 $22.26 $17.94 $16.63<br />

CPE discounted to 2013 $ $8.90 $6.73 $13.50 $17.55 $14.15 $13.11<br />

CPE as percent of fare revenues 4.6% n.a, 6.0% 8.1% 6.5% 6.0%<br />

Debt per enplaned passenger $43 $65 $165 $250 $173 $149<br />

Debt service coverage** 2.09 1.67 1.65 1.11 1.45 1.66<br />

Airline revenues as percent of total revenues 35.6% 27% 45.0% 50.0% 44.6% 42.7%<br />

Notes:<br />

* Small hub airports from Moody's Investor Service, Median <strong>Report</strong>: US Airport Medians for FY 2012 , November 2013.<br />

** 2012 debt service coverage ratio excludes one-time amounts received for the UPS settlement.<br />

** Cannot be lower than 1.25 under bond rate covenant.<br />

85<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport


Preliminary Financial Capacity Analysis<br />

Sensitivity Analyses and Financial Conclusion<br />

KEY POINTS<br />

• The sensitivity analyses<br />

shows how much the<br />

non-AIP grant would<br />

need to increase to<br />

afford the new terminal<br />

under more conservative<br />

assumptions for key<br />

variables<br />

• Initial results show that a<br />

significant amount of<br />

grant funding will be<br />

needed to make the<br />

project affordable<br />

• Securing airline input<br />

and alignment is<br />

recommended for a<br />

successful program<br />

Stress Tests<br />

Various stress tests were conducted to determine the<br />

sensitivity of the plan of finance to certain variables.<br />

Scenarios analyzed include higher construction costs, slower<br />

traffic growth, higher bond interest rates, a higher PFC<br />

amount, and lower AIP grant amounts.<br />

Table 27 below shows how much the non-AIP grant would<br />

need to increase (decrease) over the minimum $200 million<br />

level to stay within the range of the financial targets under<br />

changes in assumptions to the key variables. The amounts in<br />

the table are not cumulative.<br />

Table 27<br />

<strong>Plan</strong> of Finance Sensitivity Analysis<br />

Financial conclusions<br />

• A significant amount of grant funding will be needed to<br />

make the new terminal affordable.<br />

• Deferring the implementation will not necessarily enhance<br />

affordability due to construction escalation.<br />

• Securing airline input and alignment is important for a<br />

successful program.<br />

* See previous page for financial targets.<br />

86<br />

TERMINAL AREA CONCEPT PLAN TECHNICAL REPORT<br />

Des Moines International Airport

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!