OUR ASSETS Tschudi Project<br />
<br />
Current Status / Timeline to Production<br />
1 2 3 4 5 6 7<br />
Month +1 – 3 Month +4 Month +8 Month +16 Month +17 Month +18 Month +19<br />
First copper<br />
Start front end<br />
engineering<br />
Start earthworks<br />
and<br />
civil construction<br />
Mining<br />
contractor<br />
mobilises<br />
Commence<br />
mining ore<br />
Commission<br />
Crushers<br />
Complete first<br />
leach pad cells<br />
Commence<br />
irrigation<br />
Commission<br />
SX-EW plant<br />
Obtain<br />
environmental<br />
clearance<br />
Funding<br />
completed