Completion Certificate & Final Certificate:<br />

When the contractor fulfils his obligation under the contract he shall be eligible to<br />

apply for completion certificate in respect of the work by submitting the completion<br />

documents along with such application for completion certificate.<br />

The owner of his representative shall normally issue to the contractor the completion<br />

certificate within one month after receiving an application there of from the contractor<br />

after verifying from the completion documents and satisfying that the work has been<br />

completed in accordance with and as set out in the construction and erection<br />

drawings, and the contract documents. The contractor, after obtaining the completion<br />

certificate is eligible to present the final bill for the work executed by him under terms<br />

of the contract.<br />

Completion Certificate:<br />

Within one month of the completion of work in all respects, the contractor shall be<br />

furnished with a certificate by the owner or his representative of such completion but<br />

no completion certificate shall be given nor shall the work by deemed to have been<br />

executed until all scaffolding, surplus materials and rubbish are cleared off the site<br />

completely nor until the work shall have been measured by the Engineer, whose<br />

measurement shall be binding and conclusive, the binding and conclusive, the work<br />

will not be considered as complete and taken over by the owner until the temporary<br />

works and staff colonies etc. constructed are removed and work site cleared to the<br />

satisfaction of the owner.<br />

If the contractor shall fail to comply with the requirement of this clause on or before<br />

the date fixed for the completion of the work, the Engineer may at the expense of the<br />

contract remove such scaffolding, surplus materials and rubbish and dispose off the<br />

same as the things fit and clean off such dirt as aforesaid, and the contractor shall<br />

forth will pay the amount of all expenses so incurred and shall have no claim in<br />

respect of any such scaffolding or surplus materials as aforesaid except for any sum<br />

actually realized by the sale thereof.<br />

Completion certificate shall be in 3 parts as follows:<br />

(a) Physical/ Mechanical completion work.<br />

(b) Satisfactory completion of commissioning of equipment with load.<br />

(c) Satisfactory completion of guarantee.<br />

The contractor shall clearly indicate the three dates separately for completion<br />

documents / to form the completion documents.<br />

No. of Correction :<br />

No. of overwriting :<br />

Signature of the Contractor