Completion Certificate & Final Certificate:<br />
When the contractor fulfils his obligation under the contract he shall be eligible to<br />
apply for completion certificate in respect of the work by submitting the completion<br />
documents along with such application for completion certificate.<br />
The owner of his representative shall normally issue to the contractor the completion<br />
certificate within one month after receiving an application there of from the contractor<br />
after verifying from the completion documents and satisfying that the work has been<br />
completed in accordance with and as set out in the construction and erection<br />
drawings, and the contract documents. The contractor, after obtaining the completion<br />
certificate is eligible to present the final bill for the work executed by him under terms<br />
of the contract.<br />
Completion Certificate:<br />
Within one month of the completion of work in all respects, the contractor shall be<br />
furnished with a certificate by the owner or his representative of such completion but<br />
no completion certificate shall be given nor shall the work by deemed to have been<br />
executed until all scaffolding, surplus materials and rubbish are cleared off the site<br />
completely nor until the work shall have been measured by the Engineer, whose<br />
measurement shall be binding and conclusive, the binding and conclusive, the work<br />
will not be considered as complete and taken over by the owner until the temporary<br />
works and staff colonies etc. constructed are removed and work site cleared to the<br />
satisfaction of the owner.<br />
If the contractor shall fail to comply with the requirement of this clause on or before<br />
the date fixed for the completion of the work, the Engineer may at the expense of the<br />
contract remove such scaffolding, surplus materials and rubbish and dispose off the<br />
same as the things fit and clean off such dirt as aforesaid, and the contractor shall<br />
forth will pay the amount of all expenses so incurred and shall have no claim in<br />
respect of any such scaffolding or surplus materials as aforesaid except for any sum<br />
actually realized by the sale thereof.<br />
Completion certificate shall be in 3 parts as follows:<br />
(a) Physical/ Mechanical completion work.<br />
(b) Satisfactory completion of commissioning of equipment with load.<br />
(c) Satisfactory completion of guarantee.<br />
The contractor shall clearly indicate the three dates separately for completion<br />
documents / to form the completion documents.<br />
No. of Correction :<br />
No. of overwriting :<br />
Signature of the Contractor