General Terms &<br />

Conditions for the<br />

Supply of Electricity to<br />

New Subdivisions and<br />

Site Developments<br />

March 2011<br />

29 MARCH 2011<br />

ISSUE 3<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

PREPARED BY:<br />

Streetlight Business Process Analyst<br />

AUTHORISED BY:<br />

Manager Streetlight Business<br />

DOCUMENT NUMBER: <strong>CEOP2015</strong> - Issue 3<br />

This plan is copyright. No part may be reproduced by any process without written permission,<br />

except as permitted under the copyright act.<br />

DISCLAIMER<br />

1 <strong>Essential</strong> <strong>Energy</strong> may change the information in this document without notice. All changes<br />

take effect on the date made by <strong>Essential</strong> <strong>Energy</strong>. A print version is always an uncontrolled<br />

copy. Before using this document, please ensure that it is still current.<br />

2 This document may contain confidential information. Restrictions on the use and disclosure<br />

of confidential information by employees are set out in your contract of employment.<br />

Restrictions on the use and disclosure of confidential information by contractors are set out in<br />

your contract of engagement with <strong>Essential</strong> <strong>Energy</strong>. Sub-contractors are bound by the<br />

confidentiality provisions set out in their contract with the contractor engaged by <strong>Essential</strong><br />

<strong>Energy</strong>.<br />

2011 ESSE N T I A L E N E R G Y<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 2 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

CONTENTS PAGE<br />

1 INTRODUCTION ............................................................................................. 4<br />

2 CONTESTABLE WORKS ................................................................................... 5<br />

2.1 Categories Of Contestable Works ..................................................................... 5<br />

2.2 General Principles .......................................................................................... 5<br />

2.3 Legal ............................................................................................................ 6<br />

2.3.1 Stakeholder Relationship ............................................................................ 6<br />

2.3.2 Indemnity ................................................................................................ 6<br />

2.4 Customer Responsibility ................................................................................. 6<br />

2.5 Standards And Specifications .......................................................................... 7<br />

2.6 Materials ...................................................................................................... 8<br />

2.7 Environmental Assessment ............................................................................. 8<br />

2.8 Easements .................................................................................................... 8<br />

2.9 Street Lighting .............................................................................................. 9<br />

2.9.1 Public Roadways ....................................................................................... 9<br />

2.9.2 Private Roadways/Community Titles ............................................................ 9<br />

2.10 Non Electrical Works ...................................................................................... 9<br />

3 CONTESTABILITY – THE COMPETITIVE PROCESS .............................................. 10<br />

3.1 Customer Enquiry ......................................................................................... 10<br />

3.2 Design Information ....................................................................................... 10<br />

3.3 Design Submission ........................................................................................ 11<br />

3.4 Design Certification ....................................................................................... 11<br />

3.4.1 Requirements for Certification: .................................................................. 12<br />

3.5 Notification To Commence Construction ........................................................... 12<br />

3.6 Notice Of Arrangement .................................................................................. 12<br />

3.7 Access Permit/Outage Request ....................................................................... 12<br />

3.8 “As Installed” Plan ........................................................................................ 13<br />

3.9 Completion Notice ......................................................................................... 13<br />

3.10 Warranty ..................................................................................................... 13<br />

3.11 Certificate Of Acceptance ............................................................................... 14<br />

4 KEY TERMS AND DEFINITIONS ....................................................................... 18<br />

5 REFERENCES ................................................................................................ 20<br />

6 REVISIONS .................................................................................................. 21<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 3 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

1 INTRODUCTION<br />

This procedure outlines <strong>Essential</strong> <strong>Energy</strong>’s requirements for Developers and Service Providers to<br />

follow, when engaged in the design and construction of Contestable Works with regard to electricity<br />

transmission, sub transmission and/or distribution network for subdivisions and site developments.<br />

This document provides both administrative and technical support for level 1 and Level 3 Service<br />

Providers.<br />

The purpose of this document is to provide the General Terms and Conditions for the design,<br />

construction and/or installation of an asset, the ownership of which may on completion be<br />

transferred to <strong>Essential</strong> <strong>Energy</strong>.<br />

The NSW Electricity Supply Act 1995 allows customers to choose a suitably qualified Service<br />

Provider to perform work that is deemed to be contestable. Furthermore, <strong>Essential</strong> <strong>Energy</strong> through<br />

the Independent Pricing and Regulatory Tribunal’s determination 5.4, may require a customer to<br />

contribute towards the cost of extending and/or increasing the capacity of its existing distribution<br />

system where that is necessary to support the asset being connected.<br />

The Code of Practice, Contestable Works sets out the guidelines for contestable work in New South<br />

Wales and defines the obligations of both <strong>Essential</strong> <strong>Energy</strong> and the customer.<br />

Contestability requires <strong>Essential</strong> <strong>Energy</strong> to play two roles in the overall process:<br />

1 It must remain the “regulator” being <strong>Essential</strong> <strong>Energy</strong> responsible for the setting of<br />

standards and ensuring quality control by implementing inspection and auditing procedures.<br />

The costs associated with <strong>Essential</strong> <strong>Energy</strong> performing the “regulatory” role are eligible to<br />

be recouped through a schedule of monopoly fees as determined by IPART.<br />

2 <strong>Essential</strong> <strong>Energy</strong> may compete for the contestable work subject to appropriate accreditation<br />

being maintained and effective partitioning of the respective business units ensured.<br />

Note: It is critical that the proper steps be followed when offering to do work. There is a<br />

long-term risk to the organisation if the correct procedures are not followed. The legal,<br />

i.e. non-financial procedures and requirements outlined herein are compulsory for all<br />

persons/organisations undertaking work where the asset may become the property of<br />

<strong>Essential</strong> <strong>Energy</strong>.<br />

Accredited Service Providers seeking any form of dispensation to the process outlined in this<br />

Procedure are required to make written application to the Contractor Accreditation and Auditing<br />

Manager for approval. Unless written approval is offered the conditions of this procedure<br />

(CEPG2015) prevail.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 4 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

2 CONTESTABLE WORKS<br />

2.1 Categories Of Contestable Works<br />

The following categories of Contestable Work are directly attributed to this procedure:<br />

Underground Reticulation (URD)<br />

<strong>Essential</strong> <strong>Energy</strong>’s Underground Design Manual – CEM7098 and Underground Construction Manual –<br />

CEM7199, outline the design and construction requirements for developments adopting underground<br />

techniques.<br />

Overhead Reticulation (O/H)<br />

Construction of or extension to an overhead electricity Distribution System in accordance with<br />

<strong>Essential</strong> <strong>Energy</strong>’s Overhead Design Manual – CEM7097 (Draft) and Overhead Construction Manual –<br />

CEM7099 (Draft).<br />

Zone Substation Construction<br />

<strong>Essential</strong> <strong>Energy</strong>’s Procedural Guidelines CEPG8032 – Zone Substation Design Guidelines offers the<br />

criteria required to enable participation in the specialist area of Zone Substation construction.<br />

2.2 General Principles<br />

Contestability allows customers in <strong>Essential</strong> <strong>Energy</strong>’s Distribution area to:<br />

Engage a Level 3 Service Provider to design an EDS.<br />

Engage a Level 1 Service Provider to construct and/or install an EDS, and<br />

Supply materials conforming to <strong>Essential</strong> <strong>Energy</strong>’s specification to complete these works.<br />

The customer may contact the Department of <strong>Energy</strong>, Utilities and Sustainability for the current list<br />

of Accredited Service Providers or visit their Web site at www.deus.nsw.gov.au.<br />

The following principles apply to contestable works:<br />

The customer has the right to choose which Service Provider will undertake the design,<br />

construction and/or installation of contestable work.<br />

Only Service Providers appropriately accredited with the Department of <strong>Energy</strong>, Utilities and<br />

Sustainability may engage in Contestable Works in New South Wales.<br />

<strong>Essential</strong> <strong>Energy</strong> will provide technical information, design and construction standards for<br />

contestable work in accordance with the relevant Acts, Regulations and Codes of Practice<br />

(Note Monopoly Fees apply).<br />

<strong>Essential</strong> <strong>Energy</strong> will obtain the customer’s written consent prior to sharing any sensitive<br />

information with other parties.<br />

The Independent Pricing and Regulatory Tribunal (IPART) has determined a fee structure<br />

allowing <strong>Essential</strong> <strong>Energy</strong> to charge for the following services as part of managing<br />

Contestable Works:<br />

Design information<br />

Design certification<br />

Design re-checking (where applicable)<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 5 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

Inspection/Audit<br />

Re-inspection/Audit<br />

Access Permit<br />

Substation Commissioning<br />

Administration<br />

Notice of Arrangement and/or Certificate of Acceptance<br />

Access<br />

Authorisation<br />

Site establishment<br />

The full Pricing Determination is available from the Tribunals Web Site at www.ipart.nsw.gov.au and<br />

unless IPART advises otherwise the current fee structure will remain effective for the period July<br />

2004 > June 2008.<br />

2.3 Legal<br />

2.3.1 Stakeholder Relationship<br />

In carrying out the Works, the construction site will be under the control of the customer and the<br />

customers’ contractors and not under the control of <strong>Essential</strong> <strong>Energy</strong>.<br />

The relationship between <strong>Essential</strong> <strong>Energy</strong> and the customer exists solely on the basis that:<br />

1 <strong>Essential</strong> <strong>Energy</strong> owns the existing assets and has been asked to accept a transfer of the<br />

Contestable Works undertaken, and<br />

2 <strong>Essential</strong> <strong>Energy</strong> is merely specifying the conditions and standards which must exist before<br />

it will agree to accept a transfer of the Works, and<br />

3 <strong>Essential</strong> <strong>Energy</strong> is not acting as a supervising authority.<br />

2.3.2 Indemnity<br />

The customer indemnifies <strong>Essential</strong> <strong>Energy</strong> against all claims/liability in respect of the construction<br />

and existence of the Works and the acts and omissions of the customer, their employees, agents<br />

and contractors.<br />

Appropriate liability insurance is a prerequisite for Accreditation with the Department of <strong>Energy</strong>,<br />

Utilities and Sustainability.<br />

2.4 Customer Responsibility<br />

If proposing to initiate contestable works the customer must arrange the following actions, either<br />

directly or where technical or administrative expertise is required, through their chosen Service<br />

Provider acting as their agent:<br />

Advise <strong>Essential</strong> <strong>Energy</strong> of the type, magnitude and timing of any proposed development<br />

and other relevant information. This will enable <strong>Essential</strong> <strong>Energy</strong> to determine design,<br />

augmentation, construction and/or installation requirements.<br />

Ensure that only suitably Accredited Service Providers undertake contestable works.<br />

Provide detailed design plans in accordance with <strong>Essential</strong> <strong>Energy</strong> published requirements.<br />

Comply with the relevant contract, Codes of Practice, Acts and Regulations as to the<br />

carrying out of the contestable works. Including <strong>Essential</strong> <strong>Energy</strong>’s published design and<br />

construction standards and any project specific request identified at the design information<br />

stage.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 6 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

Ensure that the works are executed in accordance with the certified designs and that all<br />

equipment installed meets <strong>Essential</strong> <strong>Energy</strong>’s stated standards and specifications.<br />

Co-operate with <strong>Essential</strong> <strong>Energy</strong> in immediately ensuring a Service Provider ceases work if<br />

the Service Provider fails to carry out the work in accordance with <strong>Essential</strong> <strong>Energy</strong>’s<br />

“Network Management Plan – CEPG8029”. The Network Management Plan is derived from<br />

the Electricity Supply (Safety and Network Management) Regulation 2002.<br />

The customer or their agent will be responsible for:<br />

Co-ordinating all the contestable works including any arrangements associated with works<br />

performed by <strong>Essential</strong> <strong>Energy</strong>.<br />

All fees applicable to the various stages of the works undertaken.<br />

Notifying and arranging the testing (including the provision of completed test certificates)<br />

and inspection of works that <strong>Essential</strong> <strong>Energy</strong> require.<br />

The quality of the contracted Service Provider’s work and for its compliance with <strong>Essential</strong><br />

<strong>Energy</strong>’s standards and specifications.<br />

Lodging a surety by way of a Bank Guarantee or direct payment to warrant the works free<br />

of defects or faults for up to 12 months (Refer 4.10 Warranty).<br />

2.5 Standards And Specifications<br />

The customer will ensure that all works are executed in accordance with the certified designs and<br />

the equipment installed meets the conditions of <strong>Essential</strong> <strong>Energy</strong>’s Approved Materials strategy<br />

(Refer clause 3.6).<br />

If during the construction period, the customer refuses to comply with directions issued by <strong>Essential</strong><br />

<strong>Energy</strong>’s Quality Control Co-ordinators with regard to replacement or modification of works that are<br />

non conformant, <strong>Essential</strong> <strong>Energy</strong> may have such works removed, replaced or modified at the<br />

customer’s expense.<br />

Before proceeding with certain works and to meet agreed audit milestones, the customer will liaise<br />

with <strong>Essential</strong> <strong>Energy</strong>’s Quality Control Co-ordinator to schedule their presence on site subject to pre<br />

determined project deadlines.<br />

A minimum of five (5) working days notice is required for progress audits.<br />

The customer will be responsible for ensuring that the completed work is tested and test certificates<br />

provided where required. Refer to <strong>Essential</strong> <strong>Energy</strong>’s Work Instruction CEPG4005 – High and Low<br />

Voltage Underground Cable Testing.<br />

Note: <strong>Essential</strong> <strong>Energy</strong> may seek a presence during these testing procedures<br />

Where the customer requires <strong>Essential</strong> <strong>Energy</strong> to inspect the electricity system outside <strong>Essential</strong><br />

<strong>Energy</strong>’s normal working hours, the customer will be responsible for all additional costs incurred by<br />

<strong>Essential</strong> <strong>Energy</strong>, including overtime penalties and other costs, associated with attending outside<br />

normal working hours.<br />

Where the inspection/audit program identifies a non-conformance, <strong>Essential</strong> <strong>Energy</strong> will issue an<br />

appropriate notice to the Service Provider or customer specifying details of the non-conformance.<br />

Where the works do not comply with <strong>Essential</strong> <strong>Energy</strong>’s Network Management Plan (CEPG8029),<br />

<strong>Essential</strong> <strong>Energy</strong> may instigate the disconnection and/or physical removal of the defective work from<br />

the transmission/distribution system.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 7 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

If non conformances and/or faults are discovered after the commissioning of the electricity works, a<br />

non-conformance notice is to be issued to the Service Provider and the conditions of the Warranty<br />

agreement will prevail. Where fault and/or emergency restoration is actioned by <strong>Essential</strong> <strong>Energy</strong> as<br />

a first response, all associated cost and charges will be passed onto the Service Provider with whom<br />

the responsibility for the conditions of warranty were established in the first instance.<br />

Where non-conformances are not rectified within the prescribed period, <strong>Essential</strong> <strong>Energy</strong> will carry<br />

out the repairs and charge the customer, or the cost incurred by <strong>Essential</strong> <strong>Energy</strong> to effect repairs<br />

will be withdrawn from the warranty lodged for the project (Refer clause 4.10).<br />

2.6 Materials<br />

Materials used for contestable works must be listed in <strong>Essential</strong> <strong>Energy</strong>’s approved materials<br />

inventory. Where the customer sources materials not listed in the inventory, the item/s must be<br />

offered to <strong>Essential</strong> <strong>Energy</strong>’s standards group for acceptance and/or inclusion onto the current<br />

listing.<br />

Refer: CEFD6030 – Approved Materials form (Attachment “J”)<br />

Submissions to include:<br />

Quantities<br />

Specifications of material<br />

Test certificates<br />

sample<br />

The approval process may attract a fee.<br />

2.7 Environmental Assessment<br />

Environmental assessment, enhancement and management are vital components to the successful<br />

design and construction of an EDS.<br />

The Environmental Planning and Assessment Act 1979 requires <strong>Essential</strong> <strong>Energy</strong> to take into account<br />

to the fullest extent possible, all matters affecting or likely to affect the environment by reason of<br />

carrying out an activity such as constructing an EDS.<br />

The designer must be familiar with all aspects of <strong>Essential</strong> <strong>Energy</strong>’s procedure CEPG2016<br />

Environmental Assessment or arrange for the environmental assessment to be undertaken by<br />

person/s suitably qualified to undertake the assessment (such training/experience depends on the<br />

level of assessment required).<br />

The environmental impact assessment form – CEFD6024 is to accompany the construction drawings<br />

when they are submitted for design certification. CEF6024 is an integral part of CEPG2016 (Refer<br />

attachment “O”).<br />

Irrespective of who carried out the environmental assessment, <strong>Essential</strong> <strong>Energy</strong>, as proponent and<br />

determining authority, must ensure that the requirements of the Environmental Planning and<br />

Assessment Act 1979 and the Electricity Supply Act 1995 are satisfied. The Electricity Supply Act<br />

1995 imposes Licensing conditions for the Distribution Network Service Provider (DNSP) with regard<br />

to Demand Side Management therefore, it is imperative that this subject be considered as part of<br />

the Environmental Assessment.<br />

2.8 Easements<br />

Where padmounted substations, underground cables, overhead powerlines, service mains and all<br />

associated equipment are intended to become part of the EDS and are not established on or over<br />

public roads or public reserves, <strong>Essential</strong> <strong>Energy</strong> requires a registered easement over such land.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 8 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

The customer shall provide the required easements free of any encumbrances at no cost and in<br />

favour of <strong>Essential</strong> <strong>Energy</strong>. The easements will be in accordance with <strong>Essential</strong> <strong>Energy</strong>’s document<br />

CEPG8046 – Easement Requirements and is to be considered in conjunction with CEPG8019 –<br />

Capital Contributions.<br />

Where the Developer requires access to any existing easement/s, issued in favour of <strong>Essential</strong><br />

<strong>Energy</strong>, the Developer or their chosen Service Provider must make contact with <strong>Essential</strong> <strong>Energy</strong> for<br />

approval to carry out the certified work in accordance with the terms of the existing easement and<br />

any local arrangements between the Developer and the land owner. The Developer and its<br />

contractors will indemnify <strong>Essential</strong> <strong>Energy</strong> for all work carried out in the easement.<br />

<strong>Essential</strong> <strong>Energy</strong> will require the customer to obtain written consent from the Local Council, to locate<br />

such equipment in the footpath area.<br />

2.9 Street Lighting<br />

2.9.1 Public Roadways<br />

The Roads and Traffic Authority (RTA) and/or Local, City and Regional Councils as members of the<br />

Local Government and Shires Association of NSW are responsible for the approval, acceptance and<br />

funding for public lighting in their respective jurisdictions. Note: Appropriate Australian Standards<br />

apply.<br />

The customer shall arrange for <strong>Essential</strong> <strong>Energy</strong>’s form CEFD6127 – Public Lighting Installation and<br />

Connection Consent to be completed and signed by the approving authority (RTA, Local, City or<br />

Regional Council) and attach the completed form with the request for design certification.<br />

A copy of the application is provided as attachment C.<br />

2.9.2 Private Roadways/Community Titles<br />

The installation of lighting along roadways, pathways, reserves and other areas not dedicated to the<br />

public will be the responsibility of the customer.<br />

The customer must arrange for the metering and payment of any ongoing electricity and<br />

maintenance costs. The lighting installation shall be installed by a licensed electrical contractor in<br />

accordance with AS/NZS3000 the Wiring Rules.<br />

<strong>Essential</strong> <strong>Energy</strong>’s Capital Contributions document – CEPG8019 provides for alternative ownership<br />

arrangements and specifies the conditions under which such arrangements may be established.<br />

2.10 Non Electrical Works<br />

Non-electrical works comprise ancillary activities such as, surveying, tree clearing, excavation,<br />

restoration, landscaping and any construction that supports the electrical work.<br />

Non-electrical works are contestable and therefore will be funded by the customer.<br />

Refer to <strong>Essential</strong> <strong>Energy</strong>’s Document CEM7098 – Underground Design Manual for details of non<br />

electrical works.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 9 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

3 CONTESTABILITY – THE COMPETITIVE PROCESS<br />

The following section outlines the various stages and their sequence for consideration when<br />

engaging in Contestable Work/s and attachment “A” to this document offers a flow chart, over<br />

viewing the process.<br />

While the level of involvement between projects may vary for the respective stakeholders each<br />

stage must be considered and where applicable the appropriate forms are to be lodged within the<br />

prescribed time frames.<br />

3.1 Customer Enquiry<br />

The customer or their agent shall make initial contact with <strong>Essential</strong> <strong>Energy</strong>’s Planning and Customer<br />

Connection Manager with regard to the region where the work is contemplated. (refer attachment P<br />

Regional Map). This contact will firstly establish an awareness of the proposed works for Planning<br />

staff and secondly ensure the customer liaises with the most appropriate employees (Refer clause<br />

3.4).<br />

3.2 Design Information<br />

Where design information is required, the Level 3 Service Provider will submit to <strong>Essential</strong> <strong>Energy</strong>’s<br />

Planning and Customer Connection Manager a completed form CEFD6010 –Contestable Work Design<br />

Information Application (Refer attachment B).<br />

Through lodgement of this form, the Accredited Service Provider will provide sufficient information to<br />

allow <strong>Essential</strong> <strong>Energy</strong> to determine the most appropriate method and location from where supply<br />

will be taken and offer technical information if/where required.<br />

<strong>Essential</strong> <strong>Energy</strong> may impose site specific conditions on particular projects. Such conditions may<br />

include but not be limited to nominating live line technics for the commissioning of high voltage<br />

installations.<br />

Where an Accredited Service Provider is unable through not having appropriately qualified<br />

employees and/or specialist equipment to provide the site specific activity, they may engage another<br />

suitably Accredited Service Provider to complete the task. If <strong>Essential</strong> <strong>Energy</strong> was to be the default<br />

Service Provider, such agreement would need to be negotiated with the Planning and Customer<br />

Connection Manager as part of the Design Information package.<br />

<strong>Essential</strong> <strong>Energy</strong>’s assets and operational equipment forming part of the proposed works will be<br />

allocated numbers in accordance with Regional protocols.<br />

Asset and operational numbers will be offered by the Planning and Customer Connection Manager as<br />

part of the Design Information Package.<br />

<strong>Essential</strong> <strong>Energy</strong> is committed to providing design information within 14 working days of all the<br />

required information being submitted however, larger projects may require a longer period.<br />

Service Providers will be advised if delays are expected to exceed 14 working days.<br />

The design information offered shall lapse after a period of three months from the date of issue.<br />

Note: Monopoly Fees apply<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 10 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

3.3 Design Submission<br />

The preparation of construction plans depicting the existing and proposed electricity distribution<br />

system layout shall be presented in a manner consistent with <strong>Essential</strong> <strong>Energy</strong>’s certification<br />

process.<br />

It is the Level 3 Service Provider’s responsibility to ensure the conversion process is achievable.<br />

Should the customer be unable to provide the layout plan in any of the formats nominated, a<br />

digitising fee at the commercial rate will apply. The customer will be advised if/when this fee is<br />

required.<br />

<strong>Essential</strong> <strong>Energy</strong> will provide drawing numbers for all drawings being submitted and these numbers<br />

shall be identified within the drawing sheets and as the electronic file name.<br />

3.4 Design Certification<br />

The Level 3 Designer seeking Certification shall lodge completed design material directly to the<br />

Planning and Customer Connection Manager responsible for the Network area where the<br />

construction is proposed.<br />

<strong>Essential</strong> <strong>Energy</strong>’s asset and operational numbers for both existing and proposed equipment must<br />

appear on the plan when submitted for certification. Asset and operational numbers are available<br />

from the Planning and Customer Connection Manager, subject to the Region where the works are<br />

contemplated.<br />

Having considered the design proposal and confirmed acceptance of the design concept, the plan will<br />

be stamped “Certified” by <strong>Essential</strong> <strong>Energy</strong>’s Planning Officer and the construction stage may<br />

proceed, subject to the Level 1 Service Provider lodging the notification to commence construction<br />

form – CEFD6012 (Refer attachment E).<br />

<strong>Essential</strong> <strong>Energy</strong> is committed to certify or comment on designs within 14 working days of receiving<br />

them. However, larger projects may require a longer approval period.<br />

Service Providers will be advised if delays are expected to exceed 14 working days.<br />

A design certification fee, payable to <strong>Essential</strong> <strong>Energy</strong> and scaled according to the magnitude of the<br />

development will apply to each proposal submitted.<br />

Should the design fail to gain certification on the first round, the customer will be notified<br />

accordingly. When an amended design is resubmitted the monopoly re-checking fee will apply.<br />

Where an amendment to the original layout occurs after a plan has been certified, the amended<br />

design shall be lodged with <strong>Essential</strong> <strong>Energy</strong> for re-certification and the re-checking fee will apply.<br />

Design certification shall lapse after 6 months from the date of issue.<br />

Where design certification has lapsed, the Level 3 Accredited Designer should reconsider the design<br />

and must resubmit it for certification at which time the monopoly fee structure and response time<br />

commitments recommence.<br />

In certifying the design, <strong>Essential</strong> <strong>Energy</strong> makes no warranty, express or implied, that the Design is:<br />

Fit for its intended purpose<br />

Suitable for the site conditions.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 11 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

The Level 3 Accredited Designer acknowledges that <strong>Essential</strong> <strong>Energy</strong> has not inspected the site and<br />

is therefore unaware of the site conditions. The certification process by <strong>Essential</strong> <strong>Energy</strong> is granted<br />

exclusively on the basis of the submitted design with respect to the construction standards offered<br />

at the time and has no reference to any underlying assumptions or conditions.<br />

3.4.1 Requirements for Certification:<br />

The proposed final plan in digital format for certification.<br />

Design information.<br />

Note: Design information to acknowledge any statutory approval/s pending (eg)<br />

easements, Department of Infrastructure, Planning and Natural Resources (DIPNR)<br />

Department of Environment and Conservation (DEC), Rail Infrastructure Corporation etc<br />

Environmental assessment<br />

The design certification process will identify the Quality Control or Works Co-ordinator responsible<br />

for the area where the works are to be undertaken establishing a liaison for the Level 1 Service<br />

Provider/Project Manager.<br />

Note: Monopoly fees apply.<br />

3.5 Notification To Commence Construction<br />

The Level 1 Service Provider will lodge a completed version of <strong>Essential</strong> <strong>Energy</strong>’s form CEFD6012 –<br />

Notification to Start Construction (Attachment E) directly to the Quality Control Co-ordinator<br />

advising of their presence and that the construction/audit trail has commenced.<br />

The Quality Control Co-ordinator will then initiate an audit program for the nominated works subject<br />

to the Service Providers grading with the Department of <strong>Energy</strong>, Utilities and Sustainability and the<br />

magnitude of work with respect to monopoly fees.<br />

3.6 Notice Of Arrangement<br />

Where the customer wishes to proceed to registration at the Lands Title Office prior to or during the<br />

construction phase, the customer may apply to the Regional Planning and Customer Connection<br />

Manager with whom the original construction plans were lodged for the issue of a Notice of<br />

Arrangement advising the Local Council that satisfactory arrangements are in place for the provision<br />

of electricity (Monopoly fees apply).<br />

The issue of the Notice of Arrangement will be subject to the developer satisfying <strong>Essential</strong> <strong>Energy</strong>’s<br />

requirements for project documentation, provision of easements, any other specific conditions and<br />

either prepayment to <strong>Essential</strong> <strong>Energy</strong> or the lodging of a bank guarantee in favour of <strong>Essential</strong><br />

<strong>Energy</strong> for the full value of work required to make electricity supply available. This value will be<br />

agreed with the Regional Planning and Customer Connection Manager and may include provision for<br />

any ancillary works required before the electrical installation can be implemented.<br />

The bank guarantee will be released by <strong>Essential</strong> <strong>Energy</strong> after commissioning and acceptance of the<br />

electrical works following which normal warranty conditions will apply.<br />

Note: A Notice of Arrangement will precede, not replace, a Certificate of Acceptance<br />

3.7 Access Permit/Outage Request<br />

When the construction phase nears completion and there is a need to connect to, or work on or near<br />

the existing high voltage network, the Level 1 Service Provider will submit <strong>Essential</strong> <strong>Energy</strong>’s form<br />

CEFD6013 – Notice of Required Outage/Connection to the Quality Control Co-ordinator. This form<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 12 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

will then be lodged internally to the department responsible for scheduling the outage and offering<br />

access as requested.<br />

Form CEFD6013 is to be adopted whenever work on or near the high voltage network is planned,<br />

where a particular activity requires the low voltage network to be isolated or as otherwise<br />

determined by CEPG8030 – Electrical Safety Rules.<br />

Note 1:<br />

1 Lodgement of the Notice of Required Outage form – CEFD6013 must precede the preferred<br />

outage date by a minimum of ten (10) working days.<br />

2 <strong>Essential</strong> <strong>Energy</strong> personnel will advise of any changes to the nominated date/s.<br />

3 Monopoly fees apply.<br />

4 A copy of CEFD6013 – Notice of Required Outage is offered as attachment G.<br />

Note 2: Monopoly fees apply.<br />

3.8 “As Installed” Plan<br />

The customer shall be responsible for all “As Installed” details being accurately captured as they<br />

occur. These details shall be accurately marked up on the “As Installed” drawing and presented to<br />

<strong>Essential</strong> <strong>Energy</strong> on the completion of the works and prior to connection and/or commissioning.<br />

Such “As Installed” information should comprise accurate details of where poles, streetlights, cables,<br />

conductors, conduits, pillars/pits etc are actually installed and offer correct labelling of all assets and<br />

operational devices including the final system configuration.<br />

All “As Installed” details shall be presented to <strong>Essential</strong> <strong>Energy</strong> by electronic copy and in either of<br />

the formats previously specified in this document at clause 4.3.<br />

Should the customer be unable to full fill this requirement a digitising fee at the commercial rate will<br />

apply.<br />

<strong>Essential</strong> <strong>Energy</strong> will advise the customer if this fee is applicable.<br />

3.9 Completion Notice<br />

<strong>Essential</strong> <strong>Energy</strong>’s Form CEFD6302 – Completion Notice (Attachment H), is to be used by the Level 1<br />

Service Provider to confirm the project has been completed and the asset is now ready to be<br />

commissioned and form part of <strong>Essential</strong> <strong>Energy</strong>’s Network.<br />

The document offers a standard proforma covering the various stages of each project and<br />

establishes a check list for both the Level 1 Service Provider and the Quality Control Co-ordinator to<br />

verify the construction and documentation stages have been completed.<br />

Note: The completion Notice will always precede the Certificate of Acceptance<br />

3.10 Warranty<br />

The Service Provider is required to warrant the contestable works undertaken. The warranty period<br />

will commence from when the completed asset is transferred and continue for a period of 12<br />

months. Where the total value of the contestable works exceeds ten thousand dollars ($10.000),<br />

the warranty must be either an irrevocable and unconditional bank guarantee from a financial<br />

institution in a format acceptable to <strong>Essential</strong> <strong>Energy</strong> or a cheque payable to <strong>Essential</strong> <strong>Energy</strong> for the<br />

agreed amount.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 13 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

When offered, the bank guarantee or cheque will be retained by <strong>Essential</strong> <strong>Energy</strong> pending its<br />

release, if not utilised either fully or partially under the warranty conditions.<br />

The dollar value of the warranty is dependent on the Accredited Service Providers grading as<br />

determined by the Department of <strong>Energy</strong>, Utilities and Sustainability namely “A”, “B” or “C” grade.<br />

The following percentages aligned with the respective grading, is used as a multiple of the overall<br />

project cost to determine a value for the warranty.<br />

A Grade – 2%<br />

B Grade – 5%<br />

C Grade – 10%<br />

Where the Service Provider elects not to disclose the total value of the project for the purpose of<br />

establishing the warranty, <strong>Essential</strong> <strong>Energy</strong> will nominate a value based on industry pricing<br />

guidelines from the non-contestable arena.<br />

Alternatively, the Service Provider may choose to have an ongoing (rolling) $25,000 bank guarantee<br />

in favour of <strong>Essential</strong> <strong>Energy</strong> rather than have a warranty created for each project.<br />

This form of warranty shall be lodged and registered with the Contractor Accreditation and Auditing<br />

Manager prior to <strong>Essential</strong> <strong>Energy</strong> issuing a ‘Certificate of Acceptance’.<br />

3.11 Certificate Of Acceptance<br />

The Certificate of Acceptance signifies <strong>Essential</strong> <strong>Energy</strong>’s acceptance of the commissioned works as<br />

part of their network and that all the conditions of the original agreement/s have been established.<br />

After the final audit is completed and all <strong>Essential</strong> <strong>Energy</strong>’s requirements are met (including<br />

warranty) the “Certificate of Acceptance” will be forwarded to the customer.<br />

The customer may present this Notice to the relevant Local Council as evidence that all conditions<br />

for the supply of electricity to the development have been fulfilled and where required, permit<br />

release of the linen plan for registration at the Lands Title Office.<br />

Note: The Monopoly fee “Notice of Arrangement” may apply.<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 14 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

ATTACHMENT A – CONTESTABILITY – THE COMPETITIVE PROCESS<br />

CONTESTABILITY - THE COMPETITIVE PROCESS<br />

CUSTOMER ENQUIRY<br />

Directly to Planning & Customer Connection Manager<br />

(P&CCM's)- Regionally (clause 4.1)<br />

Design Information Required<br />

NO<br />

Planning Officer provides<br />

design information and<br />

terms and conditions for<br />

establishing electricity<br />

supply<br />

Request for Design Information (CEF6010)<br />

Regionally P&CCM's<br />

Note: Fees Apply (clause 4.2)<br />

Submit Design (CEF6011) (clause 4.3)<br />

Public Lighting Installation &<br />

Connection Consent Form<br />

(CEF6127) (clause 3.9)<br />

Design Certification<br />

Note: Fees Apply (clause 4.4)<br />

Design Certified<br />

NO<br />

Revisit design and<br />

certification process<br />

- new fees apply<br />

Passed on to Level 1 Service Provider to construct<br />

Confirm suitable arrangements<br />

if augmentation by others is<br />

required<br />

Level 1 Service Provider submits<br />

Notification to Commence Construction<br />

(CEF6012) and establishes liaison with<br />

Quality Control Co-ordinator (clause 4.5)<br />

Notice of Arrangement<br />

(CEF6016) (clause 4.6)<br />

Construction proceeds through to<br />

commissioning<br />

Lodge Notice of Required Outage/Connection (CEF6013).<br />

Arrange Access Permit where required<br />

Note: Fees Apply (clause 4.7)<br />

Connect/Commission EDS after testing<br />

procedures confirm compliance and test<br />

results are documented<br />

Quality Control<br />

Co-ordinator audits the work,<br />

receives test results and<br />

documents<br />

non-conformances where<br />

required. Completes Project<br />

Assessment (CEF6020) using<br />

Checklist (CEF6015)<br />

Submit Completion Notice (CEF6302) (clause 4.9) and<br />

"As Installed Plan" (Clause 4.8) concurrenlty<br />

Complete all outstanding documentation, confirm warranty (clause 4.10)<br />

arrangements, release Certificate of Acceptance (CEF6016) (clause 4.11)<br />

and notify System Control of any alterations to the network<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 15 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

All these forms are available on the policy library<br />

ATTACHMENT B – CONTESTABLE WORK DESIGN INFORMATION<br />

APPLICATION – CEOF6010<br />

ATTACHMENT C – PUBLIC LIGHTING INSTALLATION AND CONNECTION<br />

CONSENT – CEOF6127<br />

ATTACHMENT D – CONTESTABLE WORK DESIGN SUBMISSION – CEOF6011<br />

ATTACHMENT E –<br />

NOTIFICATION TO COMMENCE CONSTRUCTION – CEOF6012<br />

ATTACHMENT F – NOTICE OF ARRANGEMENT FOR ELECTRICITY SUPPLY TO<br />

A NEW SUBDIVISION/ALLOTMENT – CEOF6016<br />

ATTACHMENT G – NOTICE OF REQUIRED OUTAGE/CONNECTION –<br />

CEOF6013<br />

ATTACHMENT H – COMPLETION NOTICE – CEOF6032<br />

ATTACHMENT I – CERTIFICATE OF ACCEPTANCE – CEOF6309<br />

ATTACHMENT J – APPROVED MATERIALS FORM – CEOF6030<br />

ATTACHMENT K – HV UNDERGROUND CABLE TEST REPORT – CEOF6022<br />

ATTACHMENT L – LV UNDERGROUND CABLE TEST REPORT – CEOF6023<br />

ATTACHMENT M – CONTESTABLE CONSTRUCTION WORKS IN PROGRESS<br />

FINAL AUDIT CHECKLIST – CEOF6015<br />

ATTACHMENT N – PROJECT ASSESSMENT LEVEL 1 (NETWORK) SERVICE<br />

PROVIDER – CEOF6020<br />

ATTACHMENT O – ENVIRONMENTAL ASSESSMENT – CEOF6024<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 16 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

ATTACHMENT P – MAP<br />

Telephone Contact Numbers for Planning and Customer Connection Managers:<br />

Central Western Region 02 6338 3697<br />

Far North Coast Region 02 6643 9153<br />

Mid North Coast Region 02 6589 8447<br />

North Western Region 02 6883 4589<br />

Northern Region 02 6701 7577<br />

Riverina Region 02 6933 5805<br />

South Western Region 02 6042 3346<br />

South Eastern Region 02 6214 9772<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 17 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

4 KEY TERMS AND DEFINITIONS<br />

Access Permits/Substation Commissioning Fees: covers <strong>Essential</strong> <strong>Energy</strong>’s costs for the issue<br />

and administration of access permits and for the commissioning of new distribution substations in<br />

accordance with the Electricity Supply (Safety and Network Management) Regulation 2002. These<br />

fees, where applicable, will be payable prior to the issue of the Completion Notice.<br />

Accredited Service Provider: a company or sole trader having formally established accreditation<br />

with the Department of <strong>Energy</strong>, Utilities and Sustainability to engage in contestable work activities in<br />

NSW.<br />

Authorisation: is written permission by <strong>Essential</strong> <strong>Energy</strong> as the Network Owner, to an individual,<br />

allowing works “on or near” its transmission and/or distribution system.<br />

Authority Benefited: means <strong>Essential</strong> <strong>Energy</strong> (its successors) and its employees, agents,<br />

contractors and persons authorised by it.<br />

Commercial-In-Confidence: this is a general sensitivity label to be applied to information assets<br />

that are not to be released outside of the organisation, but are freely available to all employees and<br />

other personnel working directly for <strong>Essential</strong> <strong>Energy</strong>. An example of the use of this sensitivity label<br />

would be its application to the corporate policies, forms, procedures, standards, manuals and<br />

guidelines to be applied across the organisation. For more information refer to Information Security<br />

Sensitivity Labelling and Handling CEPG1096 and CEM7063.<br />

Certificate of Acceptance: written acknowledgment to the customer for presentation to the Local<br />

Council and/or other interested parties indicating that <strong>Essential</strong> <strong>Energy</strong> accepts transfer of the as<br />

constructed works. Note: Warranty conditions apply at the time of issuing a “Certificate of<br />

Acceptance”.<br />

Completion Notice: written acknowledgment by the Service Provider or their authorised<br />

representative that the works are complete, operational and capable of being used as an electricity<br />

distribution system (refer attachment H).<br />

Contestable Works: under the Electricity Supply Act 1995, customers are required to fund certain<br />

works which are required to enable new or expanded connection to the electricity network. These<br />

works then become contestable and the customer may choose a service provider to carry out these<br />

works. Such choice facilitates competition between providers of these services. The areas of work<br />

deemed to be contestable are set out in the Code of Practice Contestable Works.<br />

<strong>Essential</strong> <strong>Energy</strong>: for the purposes of this document, <strong>Essential</strong> <strong>Energy</strong> refers to the network<br />

owner/administrator as opposed to <strong>Essential</strong> <strong>Energy</strong> as an Accredited Service Provider (Contractor).<br />

<strong>Essential</strong> <strong>Energy</strong> Network: the sub transmission and distribution infrastructure for which<br />

<strong>Essential</strong> <strong>Energy</strong> is the Distribution Network Service Provider (DNSP).<br />

<strong>Essential</strong> <strong>Energy</strong>’s Officer: is the authorised representative of <strong>Essential</strong> <strong>Energy</strong> responsible for<br />

the co-ordination, liaison, certification and connection of customer installed electricity distribution<br />

systems.<br />

Customer: for the purposes of this document (CEPG2015) customer is defined as the individual or<br />

entity, presenting to <strong>Essential</strong> <strong>Energy</strong> for business dealings related to the connection of an electricity<br />

distribution system to <strong>Essential</strong> <strong>Energy</strong>’s network (Refer clause 3.4).<br />

Customer Connection Assets: means assets dedicated to the customer at the time of connection,<br />

up to the nearest point of the network capable of supporting the customer’s load.<br />

Design Certification: is the process whereby <strong>Essential</strong> <strong>Energy</strong>’s Planning and Customer<br />

Connection Manager accepts the construction plan offered as depicting the proposed construction<br />

and installation of the electricity distribution system at the site.<br />

Design Certification Fee: a fee approved by the Independent Pricing and Regulatory Tribunal<br />

(IPART) to off set the costs to <strong>Essential</strong> <strong>Energy</strong> for assessing and certifying plans submitted by Level<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 18 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

3 Service Providers’. The Service Provider will be invoiced for the fee, following the certification<br />

process.<br />

Design Information Fee: a fee approved by the Independent Pricing and Regulatory Tribunal<br />

(IPART) to off set the costs to <strong>Essential</strong> <strong>Energy</strong> for compiling preliminary information necessary for a<br />

Level 3 Accredited Designer to prepare an electricity distribution system design in accordance with<br />

<strong>Essential</strong> <strong>Energy</strong>’s Policies and Procedures. The fee will be invoiced to the Level 3 Accredited Service<br />

Provider on receipt of an “Application for Contestable Work Design Information” (Refer attachment<br />

“B”).<br />

Design Re-Checking Fee: a fee approved by the Independent Pricing and Regulatory Tribunal<br />

(IPART) and applied when a design has been rejected by <strong>Essential</strong> <strong>Energy</strong> and is re-submitted for<br />

certification or when re-certification is required due to design alterations.<br />

Department of <strong>Energy</strong>, Utilities and Sustainability: the owner/manager of the process for<br />

accrediting service providers to undertake contestable works in New South Wales.<br />

Easement Site: that part of the lot burdened subject to a registered easement.<br />

Electricity Distribution System (EDS): includes the electrical cables, conductors, poles,<br />

substations and associated equipment connecting the EDS to <strong>Essential</strong> <strong>Energy</strong>’s network.<br />

Erect: includes construct, repair, replace, maintain, modify, use and remove.<br />

Independent Pricing and Regulatory Tribunal (IPART): is the NSW Governments endorsed<br />

Regulator, responsible for determining, from time to time, the application of monopoly fees with<br />

respect to Contestable Work. The current fee structure is affective July 2004 > June 2008.<br />

Inspection Fee: a fee approved by the Independent Pricing and Regulatory Tribunal (IPART) to<br />

offset the cost/s of <strong>Essential</strong> <strong>Energy</strong>’s Quality Control Officers inspecting the Service Providers work<br />

to ensure compliance with <strong>Essential</strong> <strong>Energy</strong>’s construction standards. The inspections may be<br />

conducted during and/or at the completion of construction. The inspection fee is scaled in<br />

accordance with the Service Provider’s accreditation rating and the magnitude of the works to be<br />

undertaken. The appropriate fee/s will be invoiced accordingly and <strong>Essential</strong> <strong>Energy</strong>’s standard debt<br />

recovery process will monitor the activity.<br />

Monopoly Fees: monopoly fees determined by the Independent Pricing and Regulatory Tribunal<br />

(IPART) and payable to <strong>Essential</strong> <strong>Energy</strong> irrespective of the Service Provider engaged by the<br />

customer to perform the contestable work . Monopoly fees are listed on the Tribunal’s Web site at<br />

www.ipart.nsw.gov.au<br />

Near:<br />

either:<br />

a person’s body,<br />

or<br />

means in proximity to an exposed conductor, where there is a reasonable possibility of<br />

any object which the person might be carrying or touching during the course of work which is not<br />

designed for use on live conductors of the same voltage coming closer to the exposed conductor<br />

than the relevant safe working distances specified in <strong>Essential</strong> <strong>Energy</strong>’s document CEPG8030 –<br />

Electrical Safety Rules.<br />

Normal Working Hours: between the hours 8.00am > 4.00pm Monday to Friday excluding Public<br />

Holidays.<br />

Notice of Arrangement: written acknowledgment to the customer for presentation to the Local<br />

Council and/or other interested parties indicating that <strong>Essential</strong> <strong>Energy</strong> accepts the proposal prior to<br />

completion. Note: Conditions and securities apply to the issuing of a “Notice of Arrangement” (Refer<br />

attachment F).<br />

On: means in contact.<br />

Owner: means the registered proprietor from time to time of the lot burdened (including those<br />

claiming under or through the registered proprietor).<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 19 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

Padmounted Substation: means a padmounted electricity substation together with any<br />

underground or overhead electricity cables and any ancillary electrical equipment.<br />

Point of Supply: the junction of the Electricity Distributor’s conductors with the consumer’s mains.<br />

Note: point of supply was formerly known as “consumer’s terminals”.<br />

Residue Lot: means any lot in a subdivision where:<br />

No structure or building exists;<br />

Electricity supply is not required, and<br />

Is capable of further subdivision.<br />

Shared Assets: means works associated with providing adequate supply to a customer and which,<br />

at the time of connection, are shared by other customers.<br />

Warranty: a security deposit held in <strong>Essential</strong> <strong>Energy</strong>’s favour pending the expiration of a<br />

nominated period deeming workmanship and materials offered as fit for purpose.<br />

Works: means the construction, installation and testing of an EDS at the site and the connection of<br />

the EDS at the site.<br />

5 REFERENCES<br />

CEM7063 – Information Security Sensitivity Labelling and Handling<br />

CEM7097 – Overhead Design Manual<br />

CEM7098 – Underground Design Manual<br />

CEM7099 – <strong>Essential</strong> <strong>Energy</strong>’s Overhead Construction Manual<br />

CEM7199 – Underground Construction Manual<br />

CEPG1096 – Information Security Sensitivity Labelling and Handling<br />

CEPG2016 – Environmental Impact Assessment<br />

CEPG4005 – High And Low Voltage Underground Cable Testing<br />

CEPG8019 – <strong>Essential</strong> <strong>Energy</strong>’s Capital Contribution Policy<br />

CEPG8020 – Reimbursement Scheme for Rural and Large Load Customers<br />

CEPG8029 – Network Management Plan<br />

CEPG8030 – Electrical Safety Rules<br />

CEPG8032 – Design Guidelines for Transmission and Zone Substations<br />

CEPG8046 – Easement Requirements<br />

Accreditation Scheme – Level 1<br />

Accreditation Scheme – Level 3<br />

AS/NZS3000 – The Wiring Rules<br />

Code of Practice Contestable Work<br />

Electricity Supply (Safety and Network Management) Regulation 2002<br />

Environmental Planning and Assessment Act 1979<br />

Independent Pricing and Regulatory Tribunal Determination 5.4<br />

NSW Electricity Safety Act 1945<br />

NSW Electricity Supply Act 1995<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 20 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED


UNCLASSIFIED<br />

OPERATIONAL PROCEDURE - General Terms And Conditions<br />

For The Supply Of Electricity To New<br />

Subdivisions And Site Developments<br />

<strong>CEOP2015</strong><br />

NSW Service and Installation Rules<br />

6 REVISIONS<br />

Issue Number Section Details of Changes in this Revision<br />

2 All Update to new template<br />

3 All sections Rebranding template<br />

29 March 2011 - Issue No. 3<br />

Approved By: Group General Manager Networks and Infrastructure<br />

Page 21 of 21<br />

UNCLASSIFIED<br />

UNCONTROLLED COPY IF PRINTED