Guidelines for constructing and maintaining aquaculture ...

Guidelines for constructing and maintaining aquaculture ...

Guidelines for constructing and maintaining aquaculture ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The steps in this process may be combined to the following final equation:<br />

T = 1000 x 2 / 3 k L<br />

(assumes porosity of 33 per cent)<br />

where the parameters <strong>and</strong> units of measurement are:<br />

T<br />

x<br />

k<br />

L<br />

is the time to pass through liner (days)<br />

is the depth of the impermeable layer (m)<br />

is the predicted saturated hydraulic conductivity (mm/day)<br />

is the distance between the level of the pond surface <strong>and</strong> the level of the base of the <br />

impermeable layer (m) i.e. depth of water + depth of impermeable layer<br />

The volume leaked during the period of ponding may be calculated using the following equation:<br />

V = Q t a<br />

86.4<br />

Where V is the volume leaked during the period the pond is filled (ML/ha),<br />

Q is the flow (m 3 /s),<br />

t a<br />

is the number of days that leakage may occur (the maximum likely filled period of the <br />

containment structure (days) minus the time to pass through the liner (T)),<br />

<strong>and</strong> 86.4 is a unit conversion factor from m 3 /s to ML/day.<br />

36