Mid-term Evaluation Report Sri Lanka - Unido
Mid-term Evaluation Report Sri Lanka - Unido
Mid-term Evaluation Report Sri Lanka - Unido
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
53<br />
Refocus this activity towards a higher demand-orientation and reschedule and<br />
implement as soon as possible the remaining tasks. Finalise as soon as possible<br />
the contracting process of the international consultant on test procedures, so that<br />
its delivery to the project can commence soonest. It is recommended that the<br />
contracting process is fully finalised before the end of May 2001.<br />
Communication between UNIDO and NERDC has to be improved and both<br />
parties need to be involved in drafting TORs, specification of equipment, etc. as<br />
early and as much as possible, in order to avoid differences in scope and<br />
understanding.<br />
Document, publish and disseminate results to an audience (equipment suppliers)<br />
as appropriate in order for the testing procedures to be of any effective use. And<br />
finally fine tune future hydro activities with CEB and ITDG; for example to use<br />
the test rig at NERDC for testing models of turbines proposed for local<br />
manufacturing, thereby complementing ITDG's and CEB’s activities.<br />
On the basis of the current status of the work still ahead for this activity the<br />
evaluation team recommends to extent this activity with a period of 3 months,<br />
thus with an ending date of 31 March 2002.<br />
5.7 Project level findings, conclusions and recommendations<br />
In addition to the above findings presented findings, conclusions and<br />
recommendations the same issues are also presented at project level. Most of the<br />
below is an aggregation from the activity level and hence it is presented in a manner<br />
less extensive as done in section 5.1 to 5.6:<br />
• The lack of smooth and timely communication between the various actors<br />
involved in the programme has often caused delays, misunderstandings, incorrect<br />
decisions and an amount of work done double or not done at all. Therefore by<br />
introducing a communication protocol combined with for example a list server<br />
that automatically copies everyone on the project correspondence will greatly<br />
assist in improving the project communication. Both UNDP and UNIDO are in the<br />
position to organise this and it is recommended by the evaluation team that this<br />
will be discussed and decided upon during the next TPR to be held late May 2002<br />
(see below);<br />
• In contrary to the UNDP staff in Colombo the involvement of UNIDO staff in the<br />
project has been considered very formal by the <strong>Sri</strong> <strong>Lanka</strong> project stakeholders.<br />
This contributed to the fact that early involvement for draft TOR's, CV's,<br />
specification equipment and technical backstopping by UNIDO has hardly taken<br />
place. It is suggested that for the time remaining for the project a working<br />
relationship will be established with the UNIDO project manager that will be as<br />
open as considered appropriate for the more effective involvement and<br />
contribution of UNIDO to the project. Thus it is recommended that UNIDO is<br />
considered a team member, rather than a clearing house for TORs, contracting<br />
Final report, 4 May 2001<br />
<strong>Mid</strong>-<strong>term</strong> evaluation report: 'Renewable energy and energy capacity building'