the supplier of the waterproofing material used during construction, to attempt additional remediation<br />

work in Tunnel 2 and the Skinker Station in the hopes of making permanent repairs.<br />

Due to the lack of measurable precipitation and the consequent drop in the water table affecting the St.<br />

Louis region over the past year, the tunnels have not leaked enough to allow Gall Zeidler to perform a<br />

meaningful study and propose a plan. Now, however, the Agency is hopeful that changing weather<br />

conditions will permit Gall Zeidler to move ahead within the next several months. With the exception of<br />

an exact start date, which is still to be determined, the Agency has reached agreement on the terms of a<br />

contract with Gall Zeidler and a fixed fee of $234,000.00 to perform a final study and provide a<br />

remediation plan for the leaks in Tunnel 2 and the Big Bend Station. At this time, Travelers Insurance<br />

Company has agreed to reimburse the Agency for at least 25% of this cost. The draft contract is attached<br />

as Exhibit 1.<br />

Analysis:<br />

Since WVS, not the Agency, retained Gall Zeidler as a consultant on the basis of their recognized skill<br />

and experience, and not through the issuance of a request for proposal, and since Gall Zeidler has already<br />

performed an initial study and mapped the leaks in Tunnel 3 and the Big Bend Station, in order to<br />

enhance efficiency and build upon work already done, the Agency is requesting that the Operations<br />

Committee recommend to the Board of Commissioners that it approve a sole source contract with Gall<br />

Zeidler for the development of a final plan of work to remediate the leaks in Tunnel 3 and the <strong>Metro</strong>Link<br />

station at Pershing and Big Bend Boulevard for a not-to-exceed amount of Two Hundred and Thirty-Six<br />

Thousand, Three Hundred and Fifty-six Dollars and Zero Cents ($236,356.00).<br />

Management Recommendation:<br />

Management requests that the Operations Committee review and forward to the Board of Commissioners<br />

for final approval, this request to award a sole source contract to Gail Zeidler Consultant LLC in an<br />

amount not to exceed $236,356.00.<br />

Attachments:<br />

1. Draft Contract with Gall Zeidler