The depth of the liner and gravel will be varied as needed to account for the excavations for the<br />

trees and footings.<br />

The EC will require similar levels of maintenance as the Town budget presently provides for.<br />

The site will consist primarily of grassy and landscaped areas which will be maintained as<br />

recreational ball fields. The uppermost surface of the EC will be inspected quarterly and<br />

repairs will occur within a reasonable amount of time following discovery of any breaches<br />

which would impair the integrity of the EC.<br />

An ELUR will be placed on the site restricting disturbance of soil beneath the impermeable<br />

liner. The site sprinkler system piping will be located in fill material above the impermeable<br />

membrane. There is no anticipated vapor intrusion pathway, and no enclosed structures will be<br />

constructed on top of the EC. There are no surface water bodies or wetlands located on the site<br />

that would be expected to interfere with the EC.<br />

4.2.2 Engineered Control Design<br />

The EC will be constructed in six layers, as follows:<br />

<br />

<br />

<br />

<br />

<br />

<br />

A 6-inch thick soil cushion, to be placed on or about the existing ground surface/grade<br />

(or at the base of excavations for trees, posts or footings);<br />

A 40 MIL HDPE impermeable membrane (less than 1 x 10-6 cm/sec permeability);<br />

A 6-inch layer of gravel;<br />

A permeable geotextile fabric to protect the gravel layer from siltation;<br />

A 6-inch layer of common fill;<br />

A top layer consisting of either a 6-inch layer of topsoil covered with grass (thicker<br />

topsoil will be used around root balls for trees), or a 6-inch layer that includes 3 inches<br />

of subbase (gravel) and 3 inches of concrete pavement.<br />

Existing subsurface utilities will be abandoned in place prior to beginning construction.<br />

Drainage layer piping will be laid around the perimeter of the site and will discharge into the<br />

existing storm sewer in the northwest corner of the parcel. Because the EC construction<br />

includes raising the grade by 2 ft, a brick retaining wall and fence will be constructed along the<br />

perimeter of the field.<br />

Six of the existing groundwater monitoring wells will be maintained for future monitoring (RF-<br />

HA108-MW, RF-HA108-MWD, RF-HA207-MW, RF-HA123-MW, RF-HA115-MW and RF-<br />

HA110-MW). The wells will be protected during construction, and extended 2 ft to meet the<br />

finish grade. One new groundwater monitoring well (RF-HA301-MW) will be installed in the<br />

southwestern portion of the park. The wells will be completed with flush-mounted, locking<br />

caps. If wells are lost during construction, they will be replaced before the end of construction.<br />

Refer to Figure 2B for well locations.<br />