<strong>Portfolio</strong> Assurance <strong>in</strong> <strong>Rolls</strong>-<strong>Royce</strong><br />

Alex Clark<br />

Head of Programme Management Assurance<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011<br />

The <strong>in</strong><strong>for</strong>mation <strong>in</strong> this document is the property of <strong>Rolls</strong>-<strong>Royce</strong> plc and may not be copied or communicated to a third party, or used <strong>for</strong> any<br />

purpose other than that <strong>for</strong> which it is supplied without the express written consent of <strong>Rolls</strong>-<strong>Royce</strong> plc.<br />

This <strong>in</strong><strong>for</strong>mation is given <strong>in</strong> good faith based upon the latest <strong>in</strong><strong>for</strong>mation available to <strong>Rolls</strong>-<strong>Royce</strong> plc, no warranty or representation is given<br />

concern<strong>in</strong>g such <strong>in</strong><strong>for</strong>mation, which must not be taken as establish<strong>in</strong>g any contractual or other commitment b<strong>in</strong>d<strong>in</strong>g upon <strong>Rolls</strong>-<strong>Royce</strong> plc or<br />

any of its subsidiary or associated companies.


<strong>Rolls</strong>-<strong>Royce</strong> <strong>Portfolio</strong> Assurance<br />

2<br />

• Corporate landscape<br />

• Assurance scope & purpose<br />

• <strong>Project</strong> & Programme <strong>assurance</strong><br />

• Feedback & improvement<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


<strong>Rolls</strong>-<strong>Royce</strong> Corporate Structure<br />

3<br />

We operate <strong>in</strong> 5 extremely competitive, highly technical markets:<br />

Civil Aerospace Defence Aerospace Mar<strong>in</strong>e Energy<br />

Nuclear<br />

Wide-bodied jets<br />

Military aircraft<br />

Commercial<br />

Oil & Gas<br />

Submar<strong>in</strong>es<br />

Narrow-bodied jets<br />

Helicopters<br />

Naval<br />

Power generation<br />

Civil Nuclear<br />

Corporate & Regional<br />

• £58bn order book<br />

• £10bn annual sales<br />

• £915m underly<strong>in</strong>g profit<br />

• 38,000 employees<br />

• Operations <strong>in</strong> 50 Countries<br />

• Customers <strong>in</strong> 160 Countries<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Diverse Global <strong>Project</strong> <strong>Portfolio</strong><br />

4<br />

Ålesund •<br />

Barnoldswick •<br />

Bristol • • Derby<br />

• Dahlewitz<br />

Indianapolis • • Mt Vernon<br />

Madrid •<br />

S<strong>in</strong>gapore •<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Assurance Scope<br />

5<br />

• Assurance scope<br />

based on risk<br />

• Corporate & sector risk<br />

registers<br />

• Major programme list<br />

• Coverage on a regular cycle<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Assurance Types<br />

• Bus<strong>in</strong>ess <strong>assurance</strong><br />

• Gated reviews<br />

• Programme management <strong>assurance</strong><br />

• Quality audit<br />

• Eng<strong>in</strong>eer<strong>in</strong>g technical audit<br />

• HS&E audit<br />

• Purchas<strong>in</strong>g audits of suppliers<br />

Co-ord<strong>in</strong>ated to provide <strong>in</strong>tegrated <strong>assurance</strong><br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Purpose of Assurance<br />

Our aim is to support the<br />

bus<strong>in</strong>ess <strong>in</strong> its management of<br />

risk and to better <strong>in</strong><strong>for</strong>m<br />

decision mak<strong>in</strong>g by provid<strong>in</strong>g a<br />

process, which allows <strong>for</strong> the<br />

identification and assessment<br />

of risk. We report to the board<br />

on the effectiveness of the<br />

<strong>in</strong>ternal control and the risk<br />

management processes across<br />

the group.<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Assurance Tim<strong>in</strong>g<br />

8<br />

• Review areas <strong>in</strong>clude:<br />

• Bus<strong>in</strong>ess Case<br />

• Change Management<br />

• Commitment Acceptance<br />

• Cost Management<br />

• PM Competence<br />

• Programme Governance<br />

• Programme Organisation<br />

• Progress Monitor<strong>in</strong>g & Control<br />

• Requirements & Scope Management<br />

• Risk Management<br />

• Programme Execution Strategy<br />

• Plann<strong>in</strong>g and Resource Management<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


<strong>Project</strong> Audit<br />

• In-depth <strong>in</strong>dependent peer<br />

review<br />

• Exam<strong>in</strong>es project<br />

documentation<br />

• Interviews project team and<br />

key stakeholders<br />

• Produces detailed report<br />

with categorised actions<br />

• Around 10 conducted<br />

annually<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


<strong>Project</strong> Gate Review<br />

• Gate review with panel of doma<strong>in</strong> specialists<br />

• <strong>Project</strong> presents to a panel on basis of<br />

evidence<br />

• Produces report with categorised actions<br />

• Around 130 conducted per year<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


<strong>Project</strong> Health Check<br />

• 1:1 review between project<br />

manager and <strong>assurance</strong><br />

professional / PMO<br />

• Reviews all project products<br />

and processes aga<strong>in</strong>st a<br />

normalised check list<br />

• Produces summary report<br />

• 10 completed centrally, 40-<br />

50 by PMO teams<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Assur<strong>in</strong>g What?<br />

12<br />

• Process<br />

compliance<br />

• Good practice<br />

• Outturns and<br />

delivery<br />

per<strong>for</strong>mance<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Feedback & Improvement<br />

• Report<strong>in</strong>g<br />

• To projects<br />

• To the Corporate PMO<br />

• To the PM function heads<br />

• To the PM Council<br />

• Action track<strong>in</strong>g and resolution<br />

• Process improvement<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Report<strong>in</strong>g<br />

• Audit reports to<br />

projects<br />

• Action closure<br />

reports to<br />

management<br />

• Trend and analysis<br />

report<strong>in</strong>g to the<br />

function<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Value of the Assurance Process<br />

15<br />

• Proven, mature approach through application and<br />

development on projects<br />

• Embedded – <strong>in</strong>tegral part of all projects across all<br />

sectors<br />

• Consistent – applied by central team with tra<strong>in</strong>ed<br />

process practitioners<br />

• Leverages corporate knowledge and experience<br />

by shar<strong>in</strong>g and identify<strong>in</strong>g best practice<br />

• Stimulates improvement<br />

© <strong>Rolls</strong>-<strong>Royce</strong> plc 2011


Questions<br />

alex.clark@rolls-royce.com<br />

©2011 <strong>Rolls</strong>-<strong>Royce</strong> plc<br />

The <strong>in</strong><strong>for</strong>mation <strong>in</strong> this document is the property of <strong>Rolls</strong>-<strong>Royce</strong> plc and may not be copied or communicated to a third party, or used <strong>for</strong> any purpose<br />

other than that <strong>for</strong> which it is supplied without the express written consent of <strong>Rolls</strong>-<strong>Royce</strong> plc.<br />

This <strong>in</strong><strong>for</strong>mation is given <strong>in</strong> good faith based upon the latest <strong>in</strong><strong>for</strong>mation available to <strong>Rolls</strong>-<strong>Royce</strong> plc, no warranty or representation is given<br />

concern<strong>in</strong>g such <strong>in</strong><strong>for</strong>mation, which must not be taken as establish<strong>in</strong>g any contractual or other commitment b<strong>in</strong>d<strong>in</strong>g upon <strong>Rolls</strong>-<strong>Royce</strong> plc or any of<br />

its subsidiary or associated companies.<br />