AGENDA<br />
WATER ISSUES COMMITTEE MEETING<br />
WITH BOARD OF DIRECTORS*<br />
ORANGE COUNTY WATER DISTRICT<br />
18700 Ward Street, Fountain Valley (714) 378-3200<br />
Wednesday, April 10, 2013, 8 a.m., Boardroom<br />
* The OCWD Water Issues Committee meeting is noticed as a joint meeting with the Board of Directors for<br />
the purpose of strict compliance with the Brown Act <strong>and</strong> to allow all Board members to hear the<br />
presentations <strong>and</strong> participate in the discussions. OCWD Directors receive no additional compensation or<br />
stipend as a result of simultaneously convening this Board of Directors meeting. Items recommended for<br />
approval at this meeting will be placed on the Consent Calendar at the April 17, 2013 Board meeting.<br />
ROLL CALL<br />
VISITOR PARTICIPATION<br />
Members of the audience wishing to address the Board on items of interest to the public are requested to<br />
identify themselves. If the matter on which they wish to comment is an Agenda item, the visitor will be<br />
called on when that matter comes up for consideration on the Agenda. If the item is on the Consent<br />
Calendar, it will be removed from the Consent Calendar for separate consideration. Visitors are requested<br />
to limit comments to three minutes.<br />
ITEMS RECEIVED TOO LATE TO BE AGENDIZED<br />
RECOMMENDATION:<br />
Determine need to take action on item(s) which arose subsequent to posting<br />
of the Agenda (ROLL CALL VOTE: Adoption of this recommendation requires<br />
two-thirds vote of the Board/Committee, or, if less than two-thirds of the<br />
members are present, a unanimous vote)<br />
CONSENT CALENDAR (ITEM NO. 1 - 5)<br />
All matters on the Consent Calendar are to be approved by one motion unless Director or staff<br />
request separate action on a specific item.<br />
1. MINUTES OF WATER ISSUES COMMITTEE MEETING HELD MARCH 13, 2013<br />
RECOMMENDATION:<br />
Approve minutes as presented<br />
2. CONTRACT NO. B-2013-1: BURRIS PUMP STATION PROJECT PHASE I CONSTRUCTION<br />
NOTICE INVITING BIDS<br />
RECOMMENDATION:<br />
Agendize for April 17 Board meeting: Authorize publication of Notice<br />
Inviting Bids for Contract No. B-2013-1: Burris Pump Station <strong>Project</strong><br />
Phase I Construction<br />
3. CONTRACT NO. SAR-2013-2: UPPER AND LOWER FIVE COVES REHABILITATION<br />
PROJECT – NOTICE INVITING BIDS<br />
RECOMMENDATION:<br />
Agendize for April 17 Board meeting: Authorize Publication of Notice<br />
Inviting Bids for Contract No. SAR-2013-2: <strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> <strong>Rehabilitation</strong> <strong>Project</strong>
4. REQUEST FOR PROPOSALS FOR DESIGN OF THE SANTIAGO BASINS SADDLE<br />
REPAIR PROJECT<br />
RECOMMENDATION:<br />
Agendize for April 17 Board meeting: Authorize issuance of Request<br />
for Proposals for engineering services for design of the Santiago<br />
Basins Saddle Repair <strong>Project</strong><br />
5. WATER QUALITY REGULATION STUDY BY CALIFORNIA COUNCIL FOR ENVIRONMENTAL<br />
AND ECONOMIC BALANCE<br />
RECOMMENDATION:<br />
Agendize for April 17 Board meeting: Authorize continued participation<br />
<strong>and</strong> funding in the amount of $10,000 in the California Council for<br />
Environmental <strong>and</strong> Economic Balance study project for improved<br />
California water quality regulation<br />
MATTERS FOR CONSIDERATION<br />
END OF CONSENT CALENDAR<br />
6. FY2013-14 CAPITAL IMPROVEMENT PROGRAM BUDGET<br />
RECOMMENDATION:<br />
Provide comments <strong>and</strong> direction to staff<br />
7. ACCELERATION OF OCWD FUNDING FOR PRADO BASIN FEASIBILITY STUDY<br />
RECOMMENDATION:<br />
Agendize for April 17 Board meeting: Approve accelerating funding in<br />
the amount of $530,000 to the United States Army Corps of Engineers<br />
for the Prado Basin California Study, <strong>and</strong> authorize staff to transfer<br />
said funding to the federal government<br />
DETERMINATION OF ADDITIONAL ITEMS TO BE PLACED ON CONSENT CALENDAR FOR<br />
APRIL 17 BOARD MEETING<br />
DIRECTORS’ ANNOUNCEMENTS/REPORTS<br />
GENERAL MANAGER’S ANNOUNCEMENTS/REPORTS<br />
ADJOURNMENT
WATER ISSUES COMMITTEE MEMBERS<br />
Cathy Green - Chair<br />
Denis Bilodeau - Vice Chair<br />
Vincent Sarmiento<br />
Shawn Dewane<br />
Philip Anthony<br />
Alternates:<br />
Steve Sheldon Alternate 1<br />
Kathryn Barr Alternate 2<br />
Harry Sidhu Alternate 3<br />
Roger Yoh Alternate 4<br />
Bruce Whitaker Alternate 5<br />
In accordance with the requirements of California Government Code Section 54954.2, this agenda has been<br />
posted in the main lobby of the Orange County Water District, 18700 Ward Street, Fountain Valley, CA not<br />
less than 72 hours prior to the meeting date <strong>and</strong> time above. All written materials relating to each agenda<br />
item are available for public inspection in the office of the District Secretary. Backup material for the Agenda is<br />
available at the District offices for public review <strong>and</strong> can be viewed online at the District’s website:<br />
www.ocwd.com<br />
Pursuant to the Americans with Disabilities Act, persons with a disability who require a disability-related<br />
modification or accommodation in order to participate in a meeting, including auxiliary aids or services, may<br />
request such modification or accommodation from the District Secretary at (714) 378-3234, by email at<br />
jkarlsen@ocwd.com by fax at (714) 378-3373. Notification 24 hours prior to the meeting will enable District<br />
staff to make reasonable arrangements to assure accessibility to the meeting.<br />
As a general rule, agenda reports or other written documentation has been prepared or organized with<br />
respect to each item of business listed on the agenda, <strong>and</strong> can be reviewed at www.ocwd.com. Copies of<br />
these materials <strong>and</strong> other disclosable public records distributed to all or a majority of the members of the<br />
Board of Directors in connection with an open session agenda item are also on file with <strong>and</strong> available for<br />
inspection at the Office of the District Secretary, 18700 Ward Street, Fountain Valley, California, during regular<br />
business hours, 8:00 am to 5:00 pm, Monday through Friday. If such writings are distributed to members of<br />
the Board of Directors on the day of a Board meeting, the writings will be available at the entrance to the<br />
Board of Directors meeting room at the Orange County Water District office.
MINUTES OF BOARD OF DIRECTORS MEETING<br />
WITH WATER ISSUES COMMITTEE<br />
ORANGE COUNTY WATER DISTRICT<br />
March 13, 2013 @ 8 a.m.<br />
Water Issues Committee Chair Director Green called the meeting to order in the Boardroom of<br />
Orange County Water District in Fountain Valley, CA. The Assistant District Secretary called the<br />
Roll as follows:<br />
Committee Members<br />
Cathy Green<br />
Denis Bilodeau (arrived 8:20 am)<br />
Vincent Sarmiento<br />
Shawn Dewane (arrived 8:05 am)<br />
Philip Anthony<br />
Alternates<br />
Steve Sheldon<br />
Kathryn Barr<br />
Harry Sidhu<br />
Roger Yoh<br />
Bruce Whitaker<br />
CONSENT CALENDAR<br />
(not present)<br />
OCWD Staff<br />
Mike Markus, General Manager<br />
Joel Kuperberg, General Counsel<br />
Judy-Rae Karlsen, Assistant District Secretary<br />
Paula Bouyounes, Bill Dunivin, R<strong>and</strong>y Fick,<br />
Jason Dadakis, Roy Herndon, Bonnie Howard,<br />
Bill Hunt, John Kennedy, Dave Mark,<br />
Chris Olsen, Ben Peralta, Nate Scheevel,<br />
S<strong>and</strong>y Scott-Roberts, Mike Wehner,<br />
Marsha Westropp, Greg Woodside<br />
Others<br />
Michael Ho - City of Seal Beach<br />
Nabil Saba - City of Santa Ana<br />
Don Calkins - City of Anaheim<br />
Chris Davis - City of Huntington Beach<br />
Robert Hanford - Golden State Water Company<br />
Greg Heiertz - Irvine Ranch Water District<br />
Rick Shintaku - City of Anaheim<br />
Keith Lyon - Municipal Water District of Orange County<br />
Paul Schoenberg - Mesa Water District<br />
Howard Johnson - Brady Associates<br />
Director Anthony requested the removal of Item No. 4, Contract No. W-2013-1: Field<br />
Headquarters <strong>and</strong> Annex Remodel <strong>Project</strong>- Publish Notice Inviting Bids from the Consent<br />
Calendar. The remainder of the Consent Calendar was then approved upon motion by Director<br />
Anthony, seconded by Director Barr <strong>and</strong> carried [5-0] as follows.<br />
1. Minutes of Previous Meeting<br />
The Minutes of the Water Issues Committee meeting held February 13, 2013 are approved<br />
as presented.<br />
2. Weir Pond <strong>Rehabilitation</strong> <strong>Project</strong> Design - Request for Proposals<br />
Recommended for approval at March 20 Board meeting: Authorize issuance of Request for<br />
Proposals to design the Weir Pond <strong>Rehabilitation</strong> <strong>Project</strong>.<br />
3. Contract No. Tal-2013-1: Talbert Barrier Well Redevelopment – Publish Notice Inviting<br />
Bids<br />
Recommended for approval at March 20 Board meeting: Authorize publication of Notice<br />
Inviting Bids for Contract No. TAL-2013-1, FY 2013-14 Talbert Barrier Well Redevelopment<br />
<strong>Project</strong>.
3/13/2013<br />
4. Contract No. W-2013-1: Field Headquarters <strong>and</strong> Annex Remodel <strong>Project</strong>- Publish Notice<br />
Inviting Bids<br />
This matter was removed from the Consent Calendar for further discussion.<br />
5. Amendment to Agreement with CH2M HILL for Computer Model of Recharge System<br />
<strong>and</strong> Contract Extension<br />
Recommended for approval at March 20 Board meeting: Authorize issuance of Amendment<br />
No. 2 to Agreement No. 538 with CH2M HILL, for an amount not to exceed $24,082 for<br />
updates to the recharge facilities computer model <strong>and</strong> extending the contract to<br />
June 30, 2014.<br />
6. Contract GBM-2012-2: Destruction of Monitoring Well OCWD-SA22 <strong>and</strong> Construction of<br />
Replacement Monitoring Well OCWD-SA22r <strong>Project</strong> – Award Contract to Cascade Drilling<br />
Recommended for approval at March 20 Board meeting: 1) Receive <strong>and</strong> file Affidavit of<br />
Publication of Notice Inviting Bids for Contract GBM 2012-2; <strong>and</strong> 2) Accept bid <strong>and</strong> award<br />
Contract No. GBM-2012-2 to lowest responsive bidder, Cascade Drilling, L.P. for $170,419.<br />
7. Contract No. GA-2013-1: Green Acres <strong>Project</strong> Jamboree Road Bridge Crossing San<br />
Diego Creek Repair <strong>Project</strong> – Publish Notice Inviting Bids <strong>and</strong> File Categorical Exemption<br />
Recommended for approval at March 20 Board meeting: 1) Authorize filing of a Categorical<br />
Exemption for the removal of pipe, pipeline repairs <strong>and</strong> construction in compliance with<br />
the California Environmental Quality Act guidelines; <strong>and</strong> 2) Authorize publication of Notice<br />
Inviting Bids for Contract No. GA-2013-1: Green Acres <strong>Project</strong> Jamboree Road Bridge<br />
Crossing San Diego Creek Repair project.<br />
Director Dewane arrived at 8:05 during discussion of the following item.<br />
ITEM REMOVED FROM CONSENT CALENDAR<br />
4. Contract No. W-2013-1: Field Headquarters <strong>and</strong> Annex Remodel <strong>Project</strong>- Publish Notice<br />
Inviting Bids<br />
Director Anthony requested that staff present the scope of work associated with the remodeling<br />
project. General Manager Mike Markus reported the buildings at Field Headquarters in Anaheim are<br />
in need of new paint, new flooring, <strong>and</strong> there are functional repairs/improvements needed in the<br />
restroom <strong>and</strong> kitchen areas. The Committee then took the following action.<br />
Recommended for approval at March 20 Board meeting: Authorize publication of Notice<br />
Inviting Bids for Contract No. W-2013-1: Field Headquarters <strong>and</strong> Annex Remodel <strong>Project</strong>.<br />
MATTERS FOR CONSIDERATION<br />
Director Bilodeau arrived at 8:20 a.m. during the discussion on the following item.<br />
2
3/13/2013<br />
8. Alamitos Barrier Improvement <strong>Project</strong> – Geology/Engineering Report, Environmental<br />
Impact Report, Publish Notice Inviting Bids for Design, <strong>and</strong> Request for Proposals for<br />
Drilling <strong>and</strong> Construction<br />
Principal Hydrologist Dave Mark highlighted the District’s involvement in the Alamitos Barrier<br />
Improvement <strong>Project</strong>. He presented the data that demonstrates potential seawater migration into<br />
the groundwater basin <strong>and</strong> the threat to downgradient production wells <strong>and</strong> potable groundwater<br />
supplies. He stated the Geologist/Engineer’s Report <strong>and</strong> the Environmental Impact Report (EIR)<br />
outline issues, describe potential impacts <strong>and</strong> contain recommendations to address seawater<br />
intrusion in the current Alamitos Barrier alignment. Mr. Mark reported the staff has complied with<br />
California Environmental Quality Act (CEQA) requirements <strong>and</strong> the draft EIR was circulated for<br />
public comment during November 26, 2012 to January 1, 2013. He noted that staff received <strong>and</strong><br />
responded to 4 comment letters. Mr. Mark advised that staff has prepared a Statement of<br />
Overriding Consideration that identifies the Alamitos Barrier Improvement <strong>Project</strong> as critical to<br />
OCWD’s ability to maintain the water quality of the groundwater basin, to reduce dependence on<br />
imported water supplies, <strong>and</strong> that the project is a regional benefit to over 2.3 million Orange<br />
County residents with the regional benefits outweighing the temporary unavoidable significant<br />
short-term noise impacts generated by construction activity. Director Anthony requested that staff<br />
inform him of meetings with the residents of Seal Beach.<br />
Following a lengthy discussion on the project schedule, CEQA guidelines, mitigation activities,<br />
<strong>and</strong> projected costs, the Committee took the following actions.<br />
Upon motion by Director Anthony, seconded by Director Barr <strong>and</strong> carried [5-0], the<br />
Committee recommended that the Board at its March 20 Board meeting: 1) Adopt the<br />
resolution Certifying the Final Environmental Impact Report (State Clearinghouse<br />
#2012031027) for the Orange County Water District Alamitos Barrier Improvement <strong>Project</strong>;<br />
2) Approve the Geologist/Engineers’ Report; 3) Authorize issuance of Request for<br />
Proposals for engineering design; <strong>and</strong> 4) Authorize publication of Notice Inviting Bids for<br />
Drilling <strong>and</strong> Well Construction.<br />
9. Contract No. SAR-2013-1: Riverbed Filtration Desilting Demonstration <strong>Project</strong> –<br />
Amendment to Agreement with RMC Water <strong>and</strong> Environment <strong>and</strong> Publish Notice Inviting Bids<br />
Senior Engineer S<strong>and</strong>y Scott-Roberts reported the District has invested in the evaluation of various<br />
technologies for filtering Santa Ana river water <strong>and</strong> increasing recharged water percolation rates.<br />
She reported the initial study of the Riverbed Filtration Desilting Demonstration project successfully<br />
filtered Santa Ana River water <strong>and</strong> staff recommends modifying the project for greater efficiencies in<br />
the desilting process. Ms. Scott-Roberts reviewed the layout of the project <strong>and</strong> presented anticipated<br />
results for a period of two years for river water diverted to Olive Basin using the newly designed<br />
subsurface collection gallery. She reports the quality of filtered water from this project is equal to the<br />
Groundwater Replenishment System effluent water. The Committee discussed the project <strong>and</strong> then<br />
took the following actions.<br />
Upon motion by Director Dewane, seconded by Director Anthony <strong>and</strong> carried [5-0], the<br />
Committee recommended that the Board at its March 20 Board meeting: 1) Authorize<br />
issuance of Amendment No. 1 to Agreement No. 836 with RMC Water <strong>and</strong> Environment for an<br />
amount not to exceed $14,970 for an amended total of $73,762; <strong>and</strong> 2) Authorize publication<br />
of Notice Inviting Bids for Contract No. SAR-2013-1: Riverbed Filtration Desilting<br />
Demonstration <strong>Project</strong>.<br />
3
3/13/2013<br />
10. Proposed Fiscal Year 2013-14 Water Purchase Budget<br />
Executive Director John Kennedy reviewed the various components of the Water Purchase<br />
Budget. He stated that the Fiscal Year 2013-14 Water Budget is projected to be $20 million which<br />
provides for the purchase of 30,500 acre-feet of water with the largest expense the purchase of<br />
20,000 acre-feet of Metropolitan Water District (MWD) untreated full service water. Mr. Kennedy<br />
advised that water rates from the MWD terminated replenishment program were used to develop<br />
the proposed water budge <strong>and</strong> the purchase of MWD water will help support the recommended<br />
70% Basin Production Percentage. He reported the District is considering participation in the<br />
MWD Storage Incentive Program but more information from MWD is required to make that<br />
determination.<br />
The Committee discussed the Municipal Water District of Orange County surcharge rate <strong>and</strong> the<br />
overall water purchase budget items.<br />
11. Prepurchase of Fiscal Year 2013-14 Metropolitan Water District Water<br />
General Manager Mike Markus briefly discussed the District’s strategy for prepurchasing MWD<br />
water to avoid paying the MWD capacity charge. He noted that staff recommends the purchase of<br />
an additional 6,000 to 10,000 acre-feet of water if recharge capacity is available during the<br />
remainder of the fiscal year 2012-13. The Committee took the following action.<br />
Upon motion by Director Anthony, seconded by Director Dewane <strong>and</strong> carried [5-0], the<br />
Committee recommended that the Board at its March 20 Board meeting: Authorize staff to<br />
purchase fiscal year 2013-14 Metropolitan Water District water supplies if recharge<br />
capacity exists during the remainder of fiscal year 2012-13<br />
DETERMINATION OF ADDITIONAL ITEMS TO BE PLACED ON CONSENT CALENDAR FOR<br />
MARCH 20 BOARD MEETING<br />
The Committee recommended that Items No. 2-9,11 be placed on the Consent Calendar for the<br />
March 20 Board meeting.<br />
DIRECTOR COMMENTS<br />
Director Dewane reported the Colored Water Facility Dedication would be held at Mesa Water<br />
District on March 21, 2013<br />
Director Green reported Orange County Sanitation District has distributed invitations for the March<br />
27 retirement party for General Manager Jim Ruth.<br />
ADJOURNMENT<br />
There being no further business, the meeting was adjourned at 9:10 a.m.<br />
__________________________<br />
Cathy Green, Chair<br />
4
AGENDA ITEM SUBMITTAL<br />
Meeting Date: April 10, 2013<br />
Budgeted: Yes<br />
Budgeted Amount: $2,000,000<br />
To: Water Issues Committee Cost Estimate: $2,000,000<br />
Board of Directors<br />
Funding Source: R&R<br />
Program/Line Item No. R12034<br />
From: Mike Markus<br />
General Counsel Approval: NA<br />
Engineers/Feasibility Report: NA<br />
Staff Contact: J. Kennedy/ N. Scheevel CEQA Compliance: In Progress<br />
Subject:<br />
CONTRACT NO. B-2013-1: BURRIS PUMP STATION PROJECT PHASE I<br />
CONSTRUCTION – NOTICE INVITING BIDS<br />
SUMMARY<br />
Staff is proposing to construct the new Burris Pump Station in two phases in order to keep<br />
the existing pump station in operation during the FY2013 –14 storm season. The design of<br />
the Burris Pump Station Phase I <strong>Project</strong> is now complete <strong>and</strong> the bid documents are being<br />
prepared.<br />
Attachment(s): DRAFT NOTICE INVITING BIDS<br />
RECOMMENDATION<br />
Agendize for April 17 Board meeting: Authorize publication of Notice Inviting Bids for<br />
Contract No. B-2013-1: Burris Pump Station <strong>Project</strong> Phase I Construction<br />
BACKGROUND/ANALYSIS<br />
The Burris Pump Station was constructed in 1989 as part of what was referred to as the<br />
“Santiago Creek Replenishment <strong>Project</strong>”. The project included the purchase of the Santiago<br />
Basins, the construction of a 66” discharge pipeline, <strong>and</strong> the construction of the Burris Pump<br />
Station. These facilities allow the District to pump captured storm water from the Santa Ana<br />
River through the 66” pipeline for recharge at the Santiago Basins. The pump station <strong>and</strong><br />
pipeline were designed to deliver up to 200 cubic feet per second (cfs) to the Santiago<br />
Basins.<br />
Operation of the Burris Pump Station to capture storm flows typically occurs in the winter<br />
following significant rain events. This allows operations to capture <strong>and</strong> recharge water that<br />
would otherwise be lost to the ocean. Additional pumping usually continues until May or<br />
June of each year as base flow declines in the Santa Ana River. Since the winter of 2005-<br />
06, an average of 34,000 acre-feet per year of water has been pumped from Burris Pump<br />
Station to the Santiago Basins <strong>and</strong> Santiago Creek for recharge.<br />
The large pumping units at Burris Pump Station are nearly 23 years old <strong>and</strong> are showing<br />
significant signs of wear. Staff is concerned that failure of one or more of the pumping units<br />
could occur <strong>and</strong> severely impact the District’s ability to pump water from Burris Basin to<br />
Santiago Basin for recharge. An engineering evaluation of the existing pump station
performed by Black & Veatch revealed long term benefits of replacing the existing pump<br />
station.<br />
Design of the new pump station began in November of 2012. The selected design of the<br />
new pump station includes vertical turbine pumps installed in a vertical wet well (or sump).<br />
It was determined early in design that in order to construct the new pump station without<br />
having the basin out of operation for an entire storm season, a 2 phase construction<br />
approach would be required. Phase I involves draining Burris Basin <strong>and</strong> constructing a<br />
portion of the building site <strong>and</strong> an earthen berm. The berm will protect the construction site<br />
from being inundated with water while the existing pump station continues to operate. This<br />
will allow Phase II construction, the final construction of the wet well <strong>and</strong> pump station, to<br />
occur throughout the FY2013-14 storm season.<br />
Figure 1<br />
Burris Pump Station <strong>Project</strong><br />
Site Plan<br />
New Pump<br />
Station<br />
Building Site<br />
Burris<br />
Basin<br />
Existing Pump<br />
Station<br />
Santa<br />
Ana<br />
River<br />
N<br />
CEQA <strong>and</strong> regulatory permitting is underway for the project <strong>and</strong> is expected be completed<br />
prior to awarding the Phase I construction contract. An additional benefit of the 2 phase<br />
construction approach is that it allows the District to avoid significant impacts to nesting<br />
birds in Burris Basin. This is achieved by only having the basin dewatered outside of<br />
nesting season.<br />
The overall construction schedule for the new pump station is approximately 1.5 years. The<br />
Phase I construction is primarily earthwork which will provide a building site to allow OCWD<br />
to operate the existing pump station while constructing the remainder of the new pump<br />
station.
Table 1 shows the current schedule for Phase I of the project. It is anticipated that Phase II<br />
construction will begin in January or February of 2014 <strong>and</strong> be complete in early 2015.<br />
Table 1<br />
Burris Pump Station <strong>Project</strong><br />
Phase I Construction Schedule<br />
Description<br />
Date<br />
Advertise for Construction April 2013<br />
Award Construction July 2013<br />
Complete Construction December 2013<br />
Funds for the Burris Pump Station <strong>Project</strong> are included in the FY 2013-14 R&R Budget.<br />
Staff anticipates that approximately $5,000,000 will be spent in FY 2013-14 with the<br />
remainder of the project expenditures occurring in FY 14-15. A summary of the project<br />
budget can be seen in Table 2.<br />
Table 2<br />
Burris Pump Station <strong>Project</strong><br />
Budget<br />
Description<br />
<strong>Project</strong>ed Expenses<br />
Design<br />
Design Contract $990,980<br />
Construction<br />
Construction Contract<br />
Phase I<br />
Phase II<br />
Construction Management<br />
Construction Inspection Services<br />
Testing Services<br />
$2,000,000<br />
$18,000,000<br />
$200,000<br />
$50,000<br />
$50,000<br />
<strong>Project</strong> Contingency $2,000,000<br />
Total $23,290,980<br />
PRIOR RELEVANT BOARD ACTION(S):<br />
October 17, 2012, R12-10-126 - Authorize Agreement to Tetra Tech for an amount not to exceed<br />
$990,980 for the design of the Burris Pump Station<br />
July 18, 2012, M12-111 - Issue Request for Proposals for the Burris Pump Station design<br />
January 18, 2012, R12-1-5 – Agreement to Black & Veatch for an amount not to exceed $98,800 for<br />
engineering services for evaluation of the Burris Pump Station
NOTICE INVITING BIDS<br />
BURRIS PUMP STATION PHASE 1 - CONSTRUCTION<br />
CONTRACT NO. B-2013-1<br />
PLEASE TAKE NOTICE that sealed bids will be received at the office of the Contracts<br />
Administrator of the Orange County Water District ("District"), 18700 Ward Street,<br />
Fountain Valley, CA 92708 (mailing address: P.O. Box 8300, Fountain Valley, CA<br />
92728-8300), until 2:00 p.m. local time on ***, at which time the bids will be publicly<br />
opened <strong>and</strong> read aloud for performing all work <strong>and</strong> furnishing all labor, materials <strong>and</strong><br />
equipment for:<br />
The Work is to be done in accordance with the plans, specifications <strong>and</strong> contract<br />
documents on file in the District office, 18700 Ward Street, Fountain Valley, California,<br />
which plans <strong>and</strong> specifications are designated as above, <strong>and</strong> which documents are by<br />
this reference incorporated herein.<br />
PREBID CONFERENCE: A prebid conference will be held at the District office, 18700<br />
Ward Street, Fountain Valley, CA on *** at 10:00 a.m. All potential bidders, contractors<br />
<strong>and</strong> other interested parties are encouraged to attend this conference conducted by the<br />
District <strong>and</strong> Engineer. Any potential bidder that does not attend the prebid conference<br />
will be charged with knowledge of all information that was available at the prebid<br />
conference.<br />
COMPLETION OF WORK AND LIQUIDATED DAMAGES: All Work must be<br />
substantially completed within *** consecutive calendar days from the date of the Notice<br />
to Proceed issued by the District. Failure to complete the Work within the time set forth<br />
herein will result in the imposition of liquidated damages for each day of delay, in the<br />
amount set forth in the Information for Bidders.<br />
OBTAINING CONTRACT DOCUMENTS: Plans <strong>and</strong> specifications <strong>and</strong> all contract<br />
documents may be purchased at the District office for $*** per set. Payment will not be<br />
refunded <strong>and</strong> the plans <strong>and</strong> specifications <strong>and</strong> contract documents are not required to<br />
be returned.<br />
BID GUARANTEE: Each Bid shall be accompanied by one of the following: a certified<br />
or cashier's check, or bid bond in an amount not less than ten percent (10%) of the total<br />
bid price, payable to the Orange County Water District, as a guarantee that the Bidder,<br />
if its Bid is accepted, shall promptly execute the Agreement, furnish a satisfactory<br />
Faithful Performance Bond in an amount not less than one hundred percent (100%) of<br />
the total bid price, furnish a Labor <strong>and</strong> Material Bond in an amount not less than one<br />
hundred percent (100%) of the total bid price, <strong>and</strong> furnish certificates evidencing that<br />
the required insurance is in effect in the amounts set forth in the Insurance Conditions.<br />
The Faithful Performance Bond shall remain in full force <strong>and</strong> effect through the
guarantee period as specified in the General Provisions. All surety companies shall be<br />
admitted surety insurers <strong>and</strong> shall comply with the provisions of Code of Civil Procedure<br />
Section 995.630.<br />
WAGE RATE: As required by Section 1773 of the California Labor Code, the Director<br />
of the Department of Industrial Relations of the State of California has determined the<br />
general prevailing rates of wages in the locality in which the Work is to be performed.<br />
Copies of these wage rate determinations, entitled PREVAILING WAGE SCALE, are<br />
maintained at the principal office of the District, 18700 Ward Street, Fountain Valley,<br />
California, <strong>and</strong> are available to any interested party upon request. The Contractor shall<br />
post a copy of this document at each job site. The Contractor <strong>and</strong> any subcontractor<br />
under it shall pay not less than the specified prevailing rates of wages to all workers<br />
employed in the execution of the Contract.<br />
PROJECT ADMINISTRATION: All questions relative to this project prior to the opening<br />
of bids shall be directed, in writing, to the Engineer for the project:<br />
ORANGE COUNTY WATER DISTRICT<br />
18700 Ward Street<br />
Fountain Valley, CA 92708<br />
Mailing Address:<br />
P.O. Box 8300<br />
Fountain Valley, CA 92728-8300<br />
Attention: Nate Scheevel, P.E.<br />
Telephone: 714/378-3200<br />
Facsimile: 714/378-3373<br />
SUBSTITUTION OF SECURITIES: At the request <strong>and</strong> expense of the successful<br />
bidder, the District will pay the amounts retained pursuant to the contract documents as<br />
security for the completion of the Work in compliance with the requirements of Public<br />
Contract Code Section 22300 <strong>and</strong> the provisions of the General Provisions pertaining to<br />
"Substitution of Securities."<br />
CONTRACTOR'S LICENSE SPECIFICATION: In accordance with the provisions of<br />
California Public Contract Code Section 3300, the District requires that the bidder<br />
possess the following classification of contractor's license at the time that the bid<br />
proposal is submitted: Class A. If the license classification specified hereinabove is that<br />
of a "specialty contractor" as defined in Section 7058 of the California Business <strong>and</strong><br />
Professions Code, the specialty contractor awarded the Contract for this Work shall<br />
itself construct a majority of the Work, in accordance with the provisions of California<br />
Business <strong>and</strong> Professions Code Section 7059. Each bidder shall clearly write or type<br />
their contractor’s license number on the outside of the bidding envelope.
SHEETING, SHORING AND BRACING: Pursuant to the provisions of California Labor<br />
Code Section 6707, each bid submitted in response to this Notice Inviting Bids shall<br />
contain, as a bid item, adequate sheeting, shoring, <strong>and</strong> bracing, or equivalent method,<br />
for the protection of life <strong>and</strong> limb in trenches <strong>and</strong> open excavation, which shall conform<br />
to applicable safety orders.<br />
DISTRICT'S RIGHTS RESERVED: The Orange County Water District reserves the<br />
right to reject any or all bids, <strong>and</strong> to waive any informality in any bid.<br />
Dated: ____________________________<br />
ORANGE COUNTY WATER DISTRICT<br />
By:<br />
_____________________________<br />
Michael R. Markus, P.E., D.WRE<br />
General Manager
AGENDA ITEM SUBMITTAL<br />
Meeting Date: April 10, 2013<br />
Budgeted: Yes<br />
Budgeted Amount: $1,200,000<br />
To: Water Issues Committee Cost Estimate: $1,200,000<br />
Board of Directors<br />
Funding Source: R&R<br />
Program/Line Item No. R13020<br />
From: Mike Markus<br />
General Counsel Approval: NA<br />
Engineers/Feasibility Report: NA<br />
Staff Contact: J. Kennedy/ N. Scheevel CEQA Compliance: Yes<br />
Subject:<br />
CONTRACT NO. SAR-2013-2: UPPER AND LOWER FIVE COVES<br />
REHABILITATION PROJECT – NOTICE INVITING BIDS<br />
SUMMARY<br />
The <strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basins provide de-silting <strong>and</strong> conveyance for Santa Ana<br />
River water into Burris Basin. Ultimately, a portion of this water is pumped to Santiago<br />
Basins <strong>and</strong> Santiago Creek. The transfer structures <strong>and</strong> drain tubes in the <strong>Five</strong> <strong>Coves</strong><br />
Basins are at the end of their useful life <strong>and</strong> are in need of repair <strong>and</strong> replacement.<br />
Attachment(s):<br />
Draft Notice Inviting Bids<br />
Presentation<br />
RECOMMENDATION<br />
Agendize for April 17 Board meeting: Authorize Publication of Notice Inviting Bids for<br />
Contract No. SAR-2013-2: <strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> <strong>Rehabilitation</strong> <strong>Project</strong><br />
BACKGROUND/ANALYSIS<br />
The <strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basins receive water diverted by the <strong>Five</strong> <strong>Coves</strong><br />
Inflatable Rubber Dam, as well as water from the end of the Off River. Water enters <strong>Upper</strong><br />
<strong>Five</strong> <strong>Coves</strong> through pipelines that go underneath Carbon Canyon Diversion Channel. Water<br />
then surface transfers from <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> into <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basin (Figure 1).<br />
Water then leaves <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basin <strong>and</strong> is conveyed into Lincoln Basin by reinforced<br />
concrete pipes buried under Lincoln Avenue. From Lincoln Basin the water is conveyed into<br />
Burris Basin <strong>and</strong> onto Santiago Basins <strong>and</strong> Santiago Creek.<br />
There are multiple structures <strong>and</strong> pipelines that convey water through the basins <strong>and</strong> allow<br />
the basins to be drained <strong>and</strong> cleaned. The existing structures <strong>and</strong> pipelines were installed<br />
between 1989 <strong>and</strong> 1990. In December of 2008 the transfer structure between <strong>Upper</strong> <strong>and</strong><br />
<strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basins partially collapsed due to corroded corrugated metal pipe (CMP).<br />
Subsequent inspections of the other facilities identified a number of the structures <strong>and</strong><br />
pipelines that need repair or replacement.
The items that have been identified for repair or replacement are:<br />
1) Flow control gate rehabilitation <strong>and</strong> construction of a new flow measurement<br />
structure at the end of the Off River.<br />
2) Flow control gate rehabilitation at the 60” intertie tubes between the Santa Ana River<br />
<strong>and</strong> <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> Basin.<br />
3) Drain tube replacement between <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basins.<br />
4) Surface transfer structure replacement between <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> Basins.<br />
5) Flow control gate replacement <strong>and</strong> drain tube rehabilitation between <strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> Basin <strong>and</strong> Lincoln Basin.<br />
Figure 1<br />
<strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Basins <strong>Rehabilitation</strong> <strong>Project</strong><br />
Site Plan<br />
N<br />
Off River Flow<br />
Control Gates<br />
<strong>and</strong> Flow<br />
Measurement<br />
Structure<br />
Off River<br />
<strong>Upper</strong> <strong>Five</strong><br />
<strong>Coves</strong> Drain<br />
Tube <strong>and</strong> Flow<br />
Control Gate<br />
<strong>Upper</strong> <strong>Five</strong><br />
<strong>Coves</strong> Basin<br />
<strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> Drain<br />
Tube <strong>and</strong> Flow<br />
Control Gate<br />
Lincoln<br />
Basin<br />
<strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> Basin<br />
Santa<br />
Ana<br />
River<br />
SAR to <strong>Upper</strong><br />
<strong>Five</strong> <strong>Coves</strong><br />
Intertie Flow<br />
Control Gates<br />
<strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong><br />
to <strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> Transfer<br />
Structure<br />
Lincoln Avenue<br />
Burris Basin
Table 1 shows the current schedule for this project. The scheduling of this work coincides<br />
with the Phase I earthwork work scheduled for the Burris Pump Station <strong>Project</strong>. The <strong>Five</strong><br />
<strong>Coves</strong>, Lincoln <strong>and</strong> Burris Basins will be taken out of service in the summer of 2013 to allow<br />
for the proposed rehabilitation project to be completed <strong>and</strong> to prepare a building site for the<br />
construction of the new Burris Pump Station.<br />
Table 1<br />
<strong>Five</strong> <strong>Coves</strong> <strong>Rehabilitation</strong> <strong>Project</strong><br />
Schedule<br />
Description<br />
Date<br />
Advertise for Construction April 2013<br />
Award Construction June 2013<br />
Complete Construction November 2013<br />
Design is complete for the <strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> <strong>Rehabilitation</strong> <strong>Project</strong>. This design<br />
work was originally done along with the <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline<br />
<strong>Project</strong> in 2010. OCWD’s consultant is updating the drawings <strong>and</strong> technical specifications<br />
with the remaining design budget from the <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline<br />
<strong>Project</strong> <strong>and</strong> staff is preparing the remaining bid documents. The project expenses are<br />
presented in Table 2 below.<br />
Table 2<br />
<strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> <strong>Rehabilitation</strong> <strong>Project</strong><br />
Budget<br />
Description<br />
<strong>Project</strong>ed Expenses<br />
Design<br />
Design Contract $24,000<br />
Construction<br />
Construction Contract<br />
$1,200,000<br />
Construction Management<br />
$0<br />
Testing Services<br />
$18,400<br />
<strong>Project</strong> Contingency $120,000<br />
Total $1,362,400<br />
OCWD staff will perform the construction management activities for this project.<br />
PRIOR RELEVANT BOARD ACTION(S):<br />
6/16/2010 – R10-6-95: Rejecting all bids for Contract SAR-2010-1; <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins<br />
Bypass Pipeline <strong>Project</strong><br />
4/21/2010 – M10-59: Authorize publication of Notice Inviting Bids for Contract No. SAR-2010-1, <strong>Five</strong><br />
<strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline <strong>Project</strong>
3/17/2010 – R10-3-00: Authorize issuance of Amendment No. 1 to Professional Services Agreement<br />
No. 0595 with Stantec Consulting Inc. for an amount not to exceed $78,790 for additional services<br />
required for the design of the <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline<br />
2/17/2010 – R10-2-30: Adopt <strong>and</strong> Certify the Final Initial Study/Mitigated Negative Declaration<br />
(IS/MND) for the <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline <strong>Project</strong><br />
2/17/2010 – R10-2-30: Approve the Engineer’s Report (Revised): <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins<br />
Bypass Pipeline<br />
9/16/2009 – R09-09-148: Authorize issuance of Professional Services Agreement to Stantec<br />
Consulting Inc. for an amount not to exceed $347,900 for engineering services for the design of the<br />
<strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline <strong>Project</strong><br />
7/17/2009 – R09-4-118: Determine the <strong>Five</strong> <strong>Coves</strong> <strong>and</strong> Lincoln Basins Bypass Pipeline <strong>Project</strong><br />
feasible, necessary, <strong>and</strong> of general benefit to the l<strong>and</strong>s of the District, <strong>and</strong> declare the project duly<br />
instituted<br />
7/17/2009 – R09-7-118: Approve Engineer’s Report <strong>and</strong> authorize issuance of a Request for<br />
Proposals for design services
NOTICE INVITING BIDS<br />
UPPER AND LOWER FIVE COVES BASIN REHABILITATION<br />
CONTRACT NO. SAR-2013-2<br />
PLEASE TAKE NOTICE that sealed bids will be received at the office of the Contracts<br />
Administrator of the Orange County Water District ("District"), 18700 Ward Street,<br />
Fountain Valley, CA 92708 (mailing address: P.O. Box 8300, Fountain Valley, CA<br />
92728-8300), until 2:00 p.m. local time on ***, at which time the bids will be publicly<br />
opened <strong>and</strong> read aloud for performing all work <strong>and</strong> furnishing all labor, materials <strong>and</strong><br />
equipment for:<br />
The Work is to be done in accordance with the plans, specifications <strong>and</strong> contract<br />
documents on file in the District office, 18700 Ward Street, Fountain Valley, California,<br />
which plans <strong>and</strong> specifications are designated as above, <strong>and</strong> which documents are by<br />
this reference incorporated herein.<br />
PREBID CONFERENCE: A prebid conference will be held at the District office, 18700<br />
Ward Street, Fountain Valley, CA on *** at 10:00 a.m. All potential bidders, contractors<br />
<strong>and</strong> other interested parties are encouraged to attend this conference conducted by the<br />
District <strong>and</strong> Engineer. Any potential bidder that does not attend the prebid conference<br />
will be charged with knowledge of all information that was available at the prebid<br />
conference.<br />
COMPLETION OF WORK AND LIQUIDATED DAMAGES: All Work must be<br />
substantially completed within *** consecutive calendar days from the date of the Notice<br />
to Proceed issued by the District. Failure to complete the Work within the time set forth<br />
herein will result in the imposition of liquidated damages for each day of delay, in the<br />
amount set forth in the Information for Bidders.<br />
OBTAINING CONTRACT DOCUMENTS: Plans <strong>and</strong> specifications <strong>and</strong> all contract<br />
documents may be purchased at the District office for $*** per set. Payment will not be<br />
refunded <strong>and</strong> the plans <strong>and</strong> specifications <strong>and</strong> contract documents are not required to<br />
be returned.<br />
BID GUARANTEE: Each Bid shall be accompanied by one of the following: a certified<br />
or cashier's check, or bid bond in an amount not less than ten percent (10%) of the total<br />
bid price, payable to the Orange County Water District, as a guarantee that the Bidder,<br />
if its Bid is accepted, shall promptly execute the Agreement, furnish a satisfactory<br />
Faithful Performance Bond in an amount not less than one hundred percent (100%) of<br />
the total bid price, furnish a Labor <strong>and</strong> Material Bond in an amount not less than one<br />
hundred percent (100%) of the total bid price, <strong>and</strong> furnish certificates evidencing that<br />
the required insurance is in effect in the amounts set forth in the Insurance Conditions.<br />
The Faithful Performance Bond shall remain in full force <strong>and</strong> effect through the
guarantee period as specified in the General Provisions. All surety companies shall be<br />
admitted surety insurers <strong>and</strong> shall comply with the provisions of Code of Civil Procedure<br />
Section 995.630.<br />
WAGE RATE: As required by Section 1773 of the California Labor Code, the Director<br />
of the Department of Industrial Relations of the State of California has determined the<br />
general prevailing rates of wages in the locality in which the Work is to be performed.<br />
Copies of these wage rate determinations, entitled PREVAILING WAGE SCALE, are<br />
maintained at the principal office of the District, 18700 Ward Street, Fountain Valley,<br />
California, <strong>and</strong> are available to any interested party upon request. The Contractor shall<br />
post a copy of this document at each job site. The Contractor <strong>and</strong> any subcontractor<br />
under it shall pay not less than the specified prevailing rates of wages to all workers<br />
employed in the execution of the Contract.<br />
PROJECT ADMINISTRATION: All questions relative to this project prior to the opening<br />
of bids shall be directed, in writing, to the Engineer for the project:<br />
ORANGE COUNTY WATER DISTRICT<br />
18700 Ward Street<br />
Fountain Valley, CA 92708<br />
Mailing Address:<br />
P.O. Box 8300<br />
Fountain Valley, CA 92728-8300<br />
Attention: Nate Scheevel<br />
Telephone: 714/378-3200<br />
Facsimile: 714/378-3373<br />
SUBSTITUTION OF SECURITIES: At the request <strong>and</strong> expense of the successful<br />
bidder, the District will pay the amounts retained pursuant to the contract documents as<br />
security for the completion of the Work in compliance with the requirements of Public<br />
Contract Code Section 22300 <strong>and</strong> the provisions of the General Provisions pertaining to<br />
"Substitution of Securities."<br />
CONTRACTOR'S LICENSE SPECIFICATION: In accordance with the provisions of<br />
California Public Contract Code Section 3300, the District requires that the bidder<br />
possess the following classification of contractor's license at the time that the bid<br />
proposal is submitted: Class A. If the license classification specified hereinabove is that<br />
of a "specialty contractor" as defined in Section 7058 of the California Business <strong>and</strong><br />
Professions Code, the specialty contractor awarded the Contract for this Work shall<br />
itself construct a majority of the Work, in accordance with the provisions of California<br />
Business <strong>and</strong> Professions Code Section 7059. Each bidder shall clearly write or type<br />
their contractor’s license number on the outside of the bidding envelope.
SHEETING, SHORING AND BRACING: Pursuant to the provisions of California Labor<br />
Code Section 6707, each bid submitted in response to this Notice Inviting Bids shall<br />
contain, as a bid item, adequate sheeting, shoring, <strong>and</strong> bracing, or equivalent method,<br />
for the protection of life <strong>and</strong> limb in trenches <strong>and</strong> open excavation, which shall conform<br />
to applicable safety orders.<br />
DISTRICT'S RIGHTS RESERVED: The Orange County Water District reserves the<br />
right to reject any or all bids, <strong>and</strong> to waive any informality in any bid.<br />
Dated: ____________________________<br />
ORANGE COUNTY WATER DISTRICT<br />
By:<br />
_____________________________<br />
Michael R. Markus, P.E., D.WRE<br />
General Manager
<strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong><br />
<strong>Rehabilitation</strong> <strong>Project</strong><br />
Water Issues Committee Meeting<br />
April 10, 2013
<strong>Five</strong> <strong>Coves</strong> Basins Overview<br />
5. Drain<br />
Tube<br />
3. Drain Tube<br />
4.<br />
Transfer<br />
Structure<br />
Lincoln<br />
Basin<br />
<strong>Lower</strong> <strong>Five</strong><br />
<strong>Coves</strong> Basin<br />
1.<br />
Transfer<br />
Structure<br />
<strong>Upper</strong> <strong>Five</strong><br />
<strong>Coves</strong> Basin<br />
Santa Ana River<br />
2. SAR<br />
Intertie<br />
Transfer Structure<br />
Lincoln Avenue<br />
Rubber<br />
Dam<br />
Off<br />
River<br />
• <strong>Five</strong> <strong>Coves</strong> Basins are located along<br />
the Santa Ana River (SAR),<br />
southwest of the SAR/Glassell<br />
Street crossing<br />
• <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> Basin is the<br />
primary diversion point to capture<br />
SAR water for delivery to Burris<br />
Basin, Santiago Basin <strong>and</strong> Santiago<br />
Creek<br />
• <strong>Five</strong> <strong>Coves</strong> Basins provide de-silting<br />
<strong>and</strong> some percolation capacity
<strong>Project</strong> Scope<br />
1. Off River transfer, flow control gates <strong>and</strong> flow<br />
measurement structure<br />
2. SAR/<strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> 60” diameter intertie flow<br />
control gates<br />
3. <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> flow control gate <strong>and</strong> drain tube<br />
4. <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> to <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> transfer<br />
structure<br />
5. <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> flow control gate <strong>and</strong> drain tube
1. Off River Transfer
2. SAR 60” Intertie
3. <strong>Upper</strong> <strong>Five</strong> <strong>Coves</strong> Drain Tube
4. <strong>Five</strong> <strong>Coves</strong> Transfer
5. <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> Drain Tube
<strong>Project</strong> Schedule<br />
Description<br />
Date<br />
Advertise Notice Inviting Bids April 2013<br />
Award Construction June 2013<br />
Complete Construction November 2013
<strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong><br />
<strong>Rehabilitation</strong> <strong>Project</strong> Budget<br />
Description<br />
<strong>Project</strong>ed Expenses<br />
Design<br />
Design Contract $ 24,000<br />
Construction<br />
Construction Contract<br />
Construction Management<br />
Construction Inspection Services<br />
Testing Services<br />
$ 1,200,000<br />
$ 0<br />
$ 0<br />
$ 18,400<br />
<strong>Project</strong> Contingency $ 120,000<br />
Total <strong>Project</strong> Budget $ 1,362,400
Recommendation<br />
• Agendize for April 17 Board meeting:<br />
Authorize Publication of Notice Inviting Bids for Contract No. SAR-<br />
2013-2: <strong>Upper</strong> <strong>and</strong> <strong>Lower</strong> <strong>Five</strong> <strong>Coves</strong> <strong>Rehabilitation</strong> <strong>Project</strong>
AGENDA ITEM SUBMITTAL<br />
Meeting Date: April 10, 2013<br />
Budgeted: Yes<br />
Budgeted Amount: $600,000<br />
To: Water Issues Committee Cost Estimate: $250,000<br />
Board of Directors<br />
Funding Source: R&R, FEMA<br />
Program/Line Item No. R11015<br />
From: Mike Markus<br />
General Counsel Approval: Yes<br />
Engineers/Feasibility Report: Yes<br />
Staff Contact: J. Kennedy,<br />
CEQA Compliance: Yes<br />
S. Scott-Roberts<br />
Subject:<br />
REQUEST FOR PROPOSALS FOR DESIGN OF THE SANTIAGO<br />
BASINS SADDLE REPAIR PROJECT<br />
SUMMARY<br />
The Santiago Basins (Blue Diamond <strong>and</strong> Bond Basin) were connected by a pipeline<br />
located in the berm that separates the two basins, otherwise known as the saddle.<br />
During the 2010-11 storm season, the pipeline <strong>and</strong> a portion of the saddle were washed<br />
out. The saddle in its current condition has several unstable slopes. OCWD would like<br />
to repair this washed out saddle to provide stability to the facilities above <strong>and</strong> to provide<br />
additional water for recharge during the summer months. Therefore staff recommends<br />
issuing a Request for Proposals for design of the Santiago Basins Saddle Repair<br />
<strong>Project</strong>. Staff expects a larger percentage of this project cost to be reimbursed by the<br />
Federal Emergency Management Agency.<br />
Attachment(s): Request for Proposals<br />
RECOMMENDATION<br />
Agendize for April 17 Board meeting: Authorize issuance of Request for Proposals for<br />
engineering services for design of the Santiago Basins Saddle Repair <strong>Project</strong><br />
BACKGROUND/ANALYSIS<br />
Orange County Water District (District) bought the Santiago Basins in 1990. The<br />
Santiago Basins are located in the City of Orange, City of Villa Park, <strong>and</strong> in<br />
unincorporated areas of Orange County. The basins consist of two s<strong>and</strong>-gravel pits<br />
referred to as Bond Basin (south basin) <strong>and</strong> Blue Diamond Basin (north basin). Figure 1<br />
shows the configuration of these basins.<br />
Upon purchase, Blue Diamond <strong>and</strong> Bond Basin were separated by a dirt berm. The<br />
District excavated the narrowest portion of the separating berm down to elevation 245,<br />
referred to as the “saddle”, <strong>and</strong> installed a corrugated metal pipe within the saddle at<br />
elevation 230. During the winter of 2010-11, the rains washed out the corrugated metal<br />
pipe <strong>and</strong> eroded parts of the saddle. The storm left some steep unstable slopes around<br />
the saddle area. These slopes need to be maintained so that the erosion doesn’t<br />
continue <strong>and</strong> wash out facilities <strong>and</strong> roads on top of the berm.
Saddle Area<br />
The District dewatered the basin in 2012 to have a topographic map made of the storm<br />
damage. The District is now looking to repair <strong>and</strong> stabilize the eroded slopes. The<br />
District would also like to grade the saddle to minimize future erosion potential <strong>and</strong><br />
lower the saddle top elevation to allow for more water to come into Bond Basin during<br />
draining. The District has a pump station in Bond Basin that can be used to pump water<br />
to various facilities for recharge. Figure 2 shows a cross section of both basins <strong>and</strong> the<br />
current saddle elevation. If the saddle elevation is lowered, more water from Blue<br />
Diamond will be able to be pumped out of Bond Basin to recharge basins for recharge.<br />
However, the water level in Blue Diamond cannot be dropped drastically due to the 21-<br />
foot diameter inlet from the Orange County Flood Control District which is located on the<br />
north end of Blue Diamond <strong>and</strong> runs underneath Villa Park Road. If the water level in<br />
Blue Diamond is too low, the water will cascade from the 21-foot inlet into Blue Diamond<br />
basin erode the inlet.<br />
Improvements to the Santiago Basins would include stabilizing the eroded dirt slopes to<br />
protect the roads <strong>and</strong> facilities above them, evaluating the optimal berm level to provide<br />
additional water for recharge while still maintaining a pool of water for the inlet at Blue<br />
Diamond, <strong>and</strong> developing a monitoring plan for ensuring the slopes around both basins<br />
remain stable.<br />
Therefore as part of the Request for Proposals (RFP) for the design of the Santiago<br />
Basins Saddle Repair <strong>Project</strong> staff is asking consultants to<br />
Evaluate eroded slopes <strong>and</strong> banks around the Santiago Basins <strong>and</strong><br />
recommend at least three repair alternatives
Develop a monitoring plan describing tests that the District should<br />
undertake to ensure the slopes around both basins remain stable.<br />
Develop construction documents for the repair of the Santiago Basins<br />
saddle <strong>and</strong> evaluate the optimal final saddle elevation to allow for more<br />
water to be pumped to the recharge basins.<br />
The CEQA for this project was completed in July 2012. As part of the CEQA documents<br />
the work to repair the Santiago Basins saddle is considered routine maintenance. The<br />
budget for this project is still preliminary <strong>and</strong> will depend on the recommended repair<br />
alternatives presented in the report to be completed as part of this RFP. However a<br />
preliminary schedule is presented in Table 1 below.<br />
Table 1<br />
Riverbed DDP Schedule<br />
Description<br />
Date<br />
Design Award June 2013<br />
Complete Design November 2013<br />
Advertise for Construction January 2013<br />
Since the damage to the Santiago Basins Saddle was caused by the storms in 2010-11,<br />
the costs for these repairs, including the design <strong>and</strong> construction, will be over 90%<br />
reimbursable by Federal Emergency Management Agency (FEMA).<br />
PRIOR RELEVANT BOARD ACTION(S):<br />
07/18/12 – R12-7-92 - Adopt the Resolution of the Board of Directors of the Orange<br />
County Water District Certifying the Final Environmental Impact Report (State
Clearinghouse #2012011053); <strong>and</strong> adopting the Groundwater Recharge Facilities<br />
Maintenance Plan.
REQUEST FOR PROPOSALS<br />
FOR<br />
ENGINEERING SERVICES FOR DESIGN OF THE<br />
SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
ORANGE COUNTY WATER DISTRICT<br />
PROPOSALS DUE<br />
May 14, 2013<br />
11:00 A.M.
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
INTRODUCTION<br />
Orange County Water District (OCWD) is seeking proposals from qualified firms that<br />
are interested in providing Engineering Services for the preparation of the final<br />
construction documents for the SANTIAGO BASINS SADDLE REPAIR PROJECT.<br />
This Request for Proposals (RFP) describes the project, the scope of work, the<br />
schedule, the elements of the proposal, <strong>and</strong> the selection process. Failure to submit<br />
information in accordance with these requirements <strong>and</strong> procedures may be cause<br />
for disqualification.<br />
PROJECT BACKGROUND AND DESCRIPTION<br />
Orange County Water District (District) bought the Santiago Basins in 1990. The<br />
Santiago Basins are located in the City of Orange, City of Villa Park, <strong>and</strong> in<br />
unincorporated areas of Orange County. The basins consist of two s<strong>and</strong>-gravel pits<br />
referred to as Bond Basin (south basin) <strong>and</strong> Blue Diamond Basin (north basin).<br />
Figure 1 shows the configuration of these basins.<br />
Upon purchase, Blue Diamond <strong>and</strong> Bond Basin were separated by a dirt berm. The<br />
District excavated the narrowest portion of the separating berm down to elevation<br />
245, referred to as the “saddle”, <strong>and</strong> installed a corrugated metal pipe within the<br />
saddle at elevation 230. During the winter of 2010-11, the rains washed out the<br />
corrugated metal pipe <strong>and</strong> eroded parts of the saddle. The storm left some steep<br />
unstable slopes around the saddle area. These slopes need to be maintained so that<br />
the erosion doesn’t continue <strong>and</strong> wash out facilities <strong>and</strong> roads on top of the berm.<br />
1
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
The District dewatered the basin in 2012 to have a topographic map made of the<br />
storm damage. The District is now looking to repair <strong>and</strong> stabilize the eroded slopes.<br />
The District would also like to grade the saddle to minimize future erosion potential<br />
<strong>and</strong> lower the saddle top elevation to allow for more water to come into Bond Basin<br />
during draining. The District has a pump station in Bond Basin that we can use to<br />
pump water to various basins for recharge. Figure 2 shows a cross section of both<br />
basins <strong>and</strong> the current saddle elevation. If the saddle elevation is lowered, more<br />
water from Blue Diamond will be able to be pumped out of Bond Basin to recharge<br />
basins for recharge. However, the water level in Blue Diamond cannot be dropped<br />
drastically due to the 21-foot diameter inlet from the Orange County Flood Control<br />
District which is located on the north end of Blue Diamond <strong>and</strong> runs underneath Villa<br />
Park Road. If the water level in Blue Diamond is too low, the water will cascade from<br />
the 21-foot inlet into Blue Diamond basin erode the inlet.<br />
2
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
Improvements to the Santiago Basins would include stabilizing the erroded dirt<br />
slopes to protect the roads <strong>and</strong> facilities above them, evaluating the optimal berm<br />
level to provide additional water for recharge while still maintaining a pool of water<br />
for the inlet at Blue Diamond, <strong>and</strong> developing a monitoring plan for ensuring the<br />
slopes around both basins remain stable.<br />
The purpose of this RFP is to complete a study <strong>and</strong> design documents for the<br />
Santiago Basins Saddle Repair <strong>Project</strong>. In general, the study <strong>and</strong> the final design<br />
should include the following:<br />
<br />
<br />
<br />
<br />
<br />
Evaluate Eroded Areas – Evaluate eroded banks around each of the Santiago<br />
Basins <strong>and</strong> recommend at least three repair alternatives for slope failure<br />
areas around the basin <strong>and</strong> on the saddle.<br />
Evaluate Inlet into Blue Diamond - Evaluate erosion potential of the 21-feet<br />
diameter inlet into Blue Diamond Basin <strong>and</strong> recommend design alternatives to<br />
prevent erosion of the inlet.<br />
Evaluate the Cost of Alternative – Evaluate the cost of the repair alternatives<br />
for the basin slopes <strong>and</strong> the saddle.<br />
Establish Excavation & Backfill Plans – Recommend the optimal excavation<br />
slopes during construction to safely stabilize the saddle slopes.<br />
Prepare contract documents – Prepare plans <strong>and</strong> specifications for the<br />
excavation of the basin <strong>and</strong> the backfill of the basin. Prepare plans <strong>and</strong><br />
specifications for final grades of the saddle <strong>and</strong> the basin inlet. Provide<br />
engineer’s estimate of probable cost of construction.<br />
3
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
Bid & Construction Support – Provide support to OCWD during the both<br />
bidding <strong>and</strong> construction of the project. This shall include review of<br />
submittals/shop drawings, response to RFIs <strong>and</strong> preparation of record<br />
drawings.<br />
SCOPE OF WORK<br />
The following outline describes the anticipated scope of services:<br />
1.0 DESIGN PHASE<br />
1.1 - <strong>Project</strong> Management<br />
1.2 - Design<br />
A. 30% Design Submittal<br />
B. 75% Design Submittal<br />
C. 100% Design Submittal<br />
D. Final Design Submittal<br />
2.0 BID PHASE<br />
2.1 - <strong>Project</strong> Management<br />
2.2 - Technical Support During Bid Phase<br />
2.3 – Prepare <strong>Project</strong> Addenda<br />
3.0 CONSTRUCTION PHASE<br />
3.1 - <strong>Project</strong> Management<br />
3.2 - Submittal/Shop Drawing Review<br />
3.3 - RFI Response<br />
`<br />
3.4 - O & M Manual<br />
3.5 - Record Drawings<br />
1.0 DESIGN PHASE<br />
1.1 <strong>Project</strong> Management – The Consultant shall conduct project management<br />
activities to ensure adherence to schedule <strong>and</strong> budget, as well as documentation of<br />
communication between the Consultant <strong>and</strong> OCWD. Coordinate <strong>and</strong> attend<br />
approximately ten (10) design meetings with OCWD, such as project kickoff, design<br />
submittal reviews, <strong>and</strong> to review design issues. Provide meeting minutes for each of<br />
these meetings. Consultant shall provide biweekly updates of design progress to<br />
OCWD.<br />
1.2 Final Design – This task will include preparation of drawings <strong>and</strong> specifications<br />
for each design milestone (30%, 75%, 100%, Final).<br />
30% Design Submittal - Review past geotechnical reports <strong>and</strong> the Feasibility Study<br />
for the Santiago Basin <strong>Project</strong>. Using the recommendations from the reports<br />
indicated produce a report detailing repair alternatives <strong>and</strong> their associated costs, for<br />
the basin slope failures, for the saddle repair, <strong>and</strong> for the inlet. Provide conceptual<br />
drawings for the alternatives developed. Please provide three hardcopy copies of the<br />
report with design alternatives <strong>and</strong> a pdf file of the report either via email, ftp site, or<br />
CD.<br />
4
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
75% Design Submittal - Prepare more detailed construction drawings for the<br />
recommended alternative. Prepare specifications for the general construction.<br />
Develop a project schedule <strong>and</strong> estimated construction costs. Provide two sets of<br />
construction plans on full size sheets (22” x 34”), two sets of project specifications,<br />
<strong>and</strong> three sets of half-size (11”x17”) drawings for review. Please also include these<br />
drawing files as a pdf file either via email, ftp site, or CD.<br />
100% Design Submittal - Incorporate revisions from 75% design review <strong>and</strong><br />
prepare draft 100% plans <strong>and</strong> specifications. This submittal should include the<br />
same deliverables as the 75% design submittal.<br />
Final Design Submittal – Incorporate any comments from 100% design submittal.<br />
Prepare final construction plans, specifications <strong>and</strong> technical provisions for the<br />
project. Modify the OCWD Special Provisions, which will be incorporated into the<br />
OCWD st<strong>and</strong>ard contract documents to complete construction-bidding documents.<br />
Provide an engineer’s estimate of probable construction costs. Provide complete set<br />
of signed construction plans <strong>and</strong> specifications on full size (D-Size) reproducible<br />
Mylar drawing sheets <strong>and</strong> on a CD-ROM in both an Adobe Acrobat pdf format <strong>and</strong> in<br />
the 2002 version of AutoCAD dwg format. OCWD will provide duplication of contract<br />
documents for advertisement.<br />
2.0 BID PHASE<br />
The Design Consultant shall provide bid phase services including project<br />
management, bid support, <strong>and</strong> addenda preparation. These services are detailed<br />
below.<br />
2.1 <strong>Project</strong> Management – The Design Consultant shall provide an agenda for<br />
<strong>and</strong> attend the pre-bid meeting.<br />
2.2 Bid Support – The Design Consultant shall provide bidding support as it<br />
pertains to the contract documents <strong>and</strong> drawings of the structures <strong>and</strong> piping<br />
system.<br />
2.3 Addenda – Any addenda will be prepared, issued, <strong>and</strong> documented by the<br />
design consultant. Consultant shall assume three addenda for purposes of<br />
preparing this proposal.<br />
3.0 CONSTRUCTION PHASE<br />
The Design Consultant shall provide construction phase services including project<br />
management, submittal/shop drawing review, response to requests for information,<br />
<strong>and</strong> record drawing preparation. These services are detailed below.<br />
3.1 <strong>Project</strong> Management – Attend construction meetings as needed to support<br />
OCWD <strong>and</strong> OCWD’s construction management consultant. Consultant shall assume<br />
ten construction meetings for purposes of preparing this proposal.<br />
5
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
3.2 Submittal/Shop Drawing Review – Review Contractor submittals for<br />
completeness <strong>and</strong> conformity with the contract documents. Review any deviations<br />
or substitutions submitted by the contractor <strong>and</strong> make recommendations to OCWD.<br />
3.3 Requests for Information (RFIs) – Review contractors request for<br />
information <strong>and</strong> prepare responses to the contractor. Prepare any revisions to<br />
contract documents necessary to resolve conflicts.<br />
3.4 O & M Manual – Prepare a complete O & M Manual. Provide four complete<br />
operation <strong>and</strong> maintenance manuals which will include O&M procedures,<br />
maintenance schedules, material <strong>and</strong> equipment literature, specifications <strong>and</strong><br />
warranty information. Consultant will be responsible for collecting <strong>and</strong> compiling all<br />
equipment <strong>and</strong> product information <strong>and</strong> specifications from the contractor, which will<br />
then be incorporated into the O&M manual.<br />
3.5 Record Drawing Preparation – As appropriate, incorporate OCWD<br />
comments <strong>and</strong>/or revisions to draft documents <strong>and</strong> finalize all record documents.<br />
Provide two copies each of the final documents in digital <strong>and</strong> hardcopy. All drawings<br />
shall be completed <strong>and</strong> provided in Mylar format at the end of the project. A CD-<br />
ROM shall be provided at the end of the project containing the drawings in both the<br />
most recent versions of Autocad (dwg format) <strong>and</strong> Adobe Acrobat (pdf format).<br />
SCHEDULE<br />
The proposed project schedule is as follows:<br />
Design RFP Issued April 24, 2013<br />
Preproposal Meeting, 9:00 A.M. May 2, 2013<br />
Proposals Due, 11:00 A.M. May 14, 2013<br />
Board Approval for Consultant Agreement June 19, 2013<br />
Final <strong>Project</strong> Documents October 24, 2013<br />
ELEMENTS OF PROPOSAL<br />
Please include the following in your proposal:<br />
1. Cover letter.<br />
2. <strong>Project</strong> approach, exp<strong>and</strong>ing or revising the scope of services provided herein<br />
if necessary. Any deviations from the scope herein shall be clearly<br />
designated in the proposal, including associated man-hours. Include <strong>and</strong><br />
describe all sub-consultant services you believe are necessary.<br />
3. <strong>Project</strong> team description (with resumes at the back of the proposal),<br />
emphasizing similar project experience <strong>and</strong> capabilities of designated project<br />
manager, project engineers, <strong>and</strong> support staff related to the outlined scope of<br />
work. Indicate the percentage of time each member will contribute to the<br />
6
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
project. Provide an organizational chart showing the proposed staff for these<br />
services that illustrates the relationship between OCWD, the proposed project<br />
manager, key personnel, <strong>and</strong> sub-consultants. The Consultant shall also<br />
include the home office <strong>and</strong> location of each project team member.<br />
4. Provide a matrix table of the estimated man-hours for each project task <strong>and</strong><br />
subtask broken down by individual project staff <strong>and</strong> any sub-consultants.<br />
5. Description of the project team’s past record of performance on similar<br />
projects for which your firm has provided services. Also include client<br />
references that may be contacted by OCWD.<br />
6. <strong>Project</strong> schedule with milestones <strong>and</strong> completion deadlines, modifying the<br />
proposed schedule herein, based on your project approach <strong>and</strong> experience.<br />
7. Fee proposal submitted in a separate sealed envelope. The fee proposal shall<br />
show estimated hours <strong>and</strong> cost for each task <strong>and</strong> subtask, including meeting<br />
obligations. The fee proposal shall be based on services provided on an<br />
hourly-rate basis, with a total not-to-exceed fee. Provide a rate schedule for<br />
proposed services.<br />
The proposal is limited to 10 pages, exclusive of cover letter, resumes, <strong>and</strong><br />
preprinted materials.<br />
SELECTION PROCESS<br />
Selection of the Consultant will be based on the proposal contents, prior experience<br />
of the firm, <strong>and</strong> specific experience <strong>and</strong> capabilities of the designated project<br />
manager <strong>and</strong> support staff. The firm, <strong>and</strong> in particular the project manager, must be<br />
fully capable in all areas outlined under the scope of work above. Key personnel<br />
shall have the professional license(s) issued by the State of California as required<br />
for these services. Based upon this information, OCWD staff will recommend a firm<br />
to OCWD’s Board of Directors for award of contract. The selected firm must be able<br />
to begin work immediately upon award of contract <strong>and</strong> must be able to maintain the<br />
required level of effort to meet the proposed schedule.<br />
PRE-PROPOSAL ACTIVITIES<br />
Questions Concerning Request for Proposals<br />
All questions regarding the RFP should be presented to:<br />
Orange County Water District<br />
18700 Ward Street<br />
Fountain Valley, CA 92708<br />
Phone: (714) 378-3292<br />
Fax: (714) 378-3381<br />
Attn: S<strong>and</strong>y Scott-Roberts, P.E.<br />
7
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
sscott@ocwd.com<br />
Pre-Proposal Meeting<br />
A Pre-Proposal meeting <strong>and</strong> subsequent site tour of the Santiago Basins will<br />
be held at OCWD at the above listed address. This meeting will be held at<br />
9:00 AM on Thursday, May 2, 2013. All potential proposers are strongly<br />
encouraged to attend this meeting <strong>and</strong> tour.<br />
Revision to the Request for Proposals<br />
OCWD reserves the right to revise the RFP prior to the date the Proposals<br />
are due. Revisions to the RFP shall be mailed to all potential Proposers.<br />
OCWD reserves the right to extend the date by which the Proposals are due.<br />
PROPOSAL SUBMITAL<br />
Proposals are due no later than 11:00 A.M., May 14, 2013 at the OCWD<br />
office listed below. Please provide three hard copies of the proposal<br />
document as well as a pdf document of the proposal.<br />
(If sent by courier):<br />
(If sent by regular mail):<br />
SPECIAL CONDITIONS<br />
Orange County Water District<br />
Attention: S<strong>and</strong>y Scott-Roberts, P.E.<br />
18700 Ward Street<br />
Fountain Valley, CA 92708<br />
Orange County Water District<br />
Attention: S<strong>and</strong>y Scott-Roberts, P.E.<br />
P.O. Box 8300<br />
Fountain Valley, CA 92728-8300<br />
Reservations<br />
This RFP does not commit OCWD to award a contract, to defray any costs<br />
incurred in the preparation of a Proposal pursuant to this RFP or to procure or<br />
contract for work.<br />
Public Records<br />
All Proposals submitted in response to this RFP become the property of<br />
OCWD <strong>and</strong> are public records <strong>and</strong> as such may be subject to public review.<br />
Right to Cancel<br />
OCWD reserves the right to cancel, for any or no reason, in part or in its<br />
entirety, this RFP including but not limited to: selection schedule, submittal<br />
date, <strong>and</strong> submittal requirements. If OCWD cancels or revises the RFP,<br />
OCWD will notify all the Proposers in writing.<br />
8
REQUEST FOR PROPOSALS FOR THE SANTIAGO BASINS SADDLE REPAIR PROJECT<br />
Additional Information<br />
OCWD reserves the right to request additional information <strong>and</strong>/or<br />
clarifications from any or all Proposers.<br />
Public Information<br />
Release of Public Information selection announcements, contract awards,<br />
<strong>and</strong> all data provided by OCWD shall be protected from public disclosure.<br />
Proposers desiring to release information to the public must receive prior<br />
written approval from OCWD.<br />
Professional Services Agreement<br />
The selected consultant will be required to sign the attached Professional<br />
Services Agreement (Exhibit A) <strong>and</strong> to provide the Insurance Certificates <strong>and</strong><br />
all other required documentation within 10 calendar days of notice of award.<br />
Insurance Requirements<br />
The minimum insurance requirements are $2 million ($4 million aggregate) for<br />
comprehensive general liability insurance, $1 million for workers<br />
compensation, $1 million for comprehensive automobile liability insurance <strong>and</strong><br />
$1 million for professional liability insurance. OCWD requires contractors,<br />
consultants <strong>and</strong> vendors doing business with it to obtain Errors <strong>and</strong><br />
Omissions insurance as shown in the Professional Services Agreement.<br />
OCWD must also be named as additional insured. The required insurance<br />
certificates must comply with all requirements of the st<strong>and</strong>ards as shown in<br />
the Agreement <strong>and</strong> must be provided (original copy) within 10 calendar days<br />
of notice of award <strong>and</strong> prior to the commencement of any work on the project.<br />
Equal Employment Opportunity <strong>and</strong> Affirmative Action Requirements<br />
The Proposers shall provide a Statement of Equal Employment<br />
Opportunity/Affirmative Action. The Consultant <strong>and</strong> each subcontractor shall<br />
not discriminate in the employment of persons on the work because of race,<br />
religious creed, color, national origin, ancestry, physical h<strong>and</strong>icap, medical<br />
condition, marital status, sexual preference or sex of such persons except as<br />
permitted by Section 12940 of the California government Code. The<br />
Consultant is expected to maintain policies similar to those of OCWD<br />
regarding equal employment opportunities <strong>and</strong> affirmative action as set forth<br />
in OCWD’s Administrative Policies.<br />
9
EXHIBIT A<br />
SAMPLE PROFESSIONAL SERVICES AGREEMENT
EXHIBIT B<br />
OCWD PROPOSAL EVALUATION FORM
AGENDA ITEM SUBMITTAL<br />
Meeting Date: April 10, 2013<br />
Budgeted: Yes<br />
Budgeted Amount: $10,000<br />
To: Water Issues Committee Cost Estimate: $10,000<br />
Board of Directors<br />
Funding Source: General Fund<br />
Program/ Line Item No. 1046.53001<br />
From: Mike Markus<br />
General Counsel Approval: NA<br />
Staff Contact: M. Wehner/G.<br />
Woodside<br />
Engineers/Feasibility Report: NA<br />
CEQA Compliance: NA<br />
Subject:<br />
WATER QUALITY REGULATION STUDY BY CALIFORNIA COUNCIL<br />
FOR ENVIRONMENTAL AND ECONOMIC BALANCE<br />
SUMMARY<br />
OCWD is participating in a project by the California Council for Environmental <strong>and</strong><br />
Economic Balance (CCEEB) on improving water quality regulation in California. The<br />
purpose of the project is to evaluate the recommendations of a 2009 Little Hoover<br />
Commission Report on ways to improve the governance of water quality regulation in<br />
California by focusing on the biggest threats to water quality. Other public agencies,<br />
including Orange County Sanitation District (OCSD) <strong>and</strong> Los Angeles County Sanitation<br />
Districts are participating, along with businesses. CCEEB has requested an additional<br />
contribution from the participants to fund the completion of the study <strong>and</strong> outreach to<br />
stakeholders.<br />
Attachment(s): Invoice from CCEEB dated March 25, 2013<br />
RECOMMENDATION<br />
Agendize for April 17 Board meeting: Authorize continued participation <strong>and</strong> funding in<br />
the amount of $10,000 in the California Council for Environmental <strong>and</strong> Economic<br />
Balance study project for improved California water quality regulation.<br />
BACKGROUND/ANALYSIS<br />
In 2009, the Little Hoover Commission found that “California’s current system for<br />
ensuring water quality does not rank the biggest threats to water quality <strong>and</strong><br />
systematically match its finite resources to address the most serious of them using the<br />
tools of scientific <strong>and</strong> economic analysis.” The Commission went on to make a series of<br />
recommendations on how to improve water quality regulation in California. The<br />
California Council for Environmental <strong>and</strong> Economic Balance (CCEEB) recognized the<br />
importance of following up the Little Hoover Commission Report with a project to<br />
determine which of the Commission’s recommendations are achievable now (without<br />
legislation) <strong>and</strong> to help establish priorities to obtain the greatest water quality<br />
improvement possible with available resources.
The Board approved participation in the study in March 2012 <strong>and</strong> authorized<br />
contributing $10,000 to help fund the study.<br />
The study began in 2012 <strong>and</strong> a draft report has been prepared. The study is being<br />
prepared by Dr. Susan Paulsen of Flow Science, who is well qualified to perform the<br />
analyses to identify the changes in water quality regulation in California that would yield<br />
the most significant water quality benefits from the investment of currently available<br />
resources.<br />
The funding request, if approved by the Board, would bring the District’s total cash<br />
contribution to the study up to $20,000. The funding would be used to complete the<br />
study <strong>and</strong> outreach to stakeholders regarding the study. This will include working with<br />
State Water Resources Control Board members <strong>and</strong> staff, the Secretary of Cal EPA <strong>and</strong><br />
staff, the Governor’s office, legislative staff, <strong>and</strong> regional board staff.<br />
Participation in the study is beneficial to OCWD since the District is very much affected<br />
by water quality regulation through the State Water Resources Control Board <strong>and</strong> the<br />
Santa Ana Regional Board, as a regulated entity, as a partner with another regulated<br />
entity (OCSD) <strong>and</strong> as a downstream agency that depends on water discharged by other<br />
agencies upstream. Participation in the study gives OCWD an opportunity to assure<br />
that the study includes an Orange County perspective on costs <strong>and</strong> benefits of water<br />
quality regulation. Prioritization of regulation to address the most critical needs is<br />
consistent with OCWD goals <strong>and</strong> objectives.<br />
CCEEB is a non-partisan, non-profit coalition of business, labor <strong>and</strong> public leaders that<br />
has advanced strategies for a sound economy <strong>and</strong> healthy environment since 1973.<br />
Jerry Secundy is the president <strong>and</strong> CEO of CCEEB. Robert Lucas is a consultant <strong>and</strong><br />
lobbyist for CCEEB <strong>and</strong> leads the advocacy effort for the recommendations developed<br />
by the study. .<br />
PRIOR RELEVANT BOARD ACTION(S)<br />
3-21-2012, M12-44 - Authorize participation in California Council for Environmental <strong>and</strong><br />
Economic Balance study project to improve California water quality regulation <strong>and</strong><br />
provide financial support in the amount of $10,000.
California Council for Environmental <strong>and</strong> Economic Balance<br />
100 Spear Street, Suite 805<br />
San Francisco, CA 94105<br />
Phone (415) 512-7890 Fax (415) 512-7897<br />
Greg Woodside<br />
Orange County Water District<br />
3/25/2013<br />
Invoice Date<br />
711M<br />
Invoice #<br />
INVOICE<br />
2013 Water Quality Task Force $10,000.00<br />
Contributions or gifts to CCEEB are not tax deductible as charitable contributions.<br />
Pursuant to the Omnibus Budget Reconciliation Act of 1993, 11%<br />
of your membership dues are not deductible as a business<br />
expense.<br />
Tax I.D. 94-2210145
AGENDA ITEM SUBMITTAL<br />
Meeting Date: April 10, 2013<br />
To: Water Issues Committee<br />
Board of Directors<br />
From: Mike Markus<br />
Staff Contact: J. Kennedy<br />
Budgeted: N/A<br />
Budgeted Amount: $65.6 M<br />
Cost Estimate: N/A<br />
Funding Source: Long Term Debt, Grants,<br />
Litigation Settlements, State Loans &<br />
Operating Revenues<br />
Program/Line Item No: N/A<br />
General Counsel Approval: N/A<br />
Engineers/Feasibility Report: N/A<br />
CEQA Compliance: N/A<br />
Subject:<br />
FY2013-14 CAPITAL IMPROVEMENT PROGRAM BUDGET<br />
SUMMARY<br />
The proposed FY2013-14 Capital Improvement Program (CIP) budget totals $ 65.6 million<br />
for 21 projects. The CIP section (Section 8) from the March 6, 2013 draft FY2013-14<br />
OCWD Budget document provided to the Board is attached. An Engineer’s Report must be<br />
approved by the Board of Directors for each project before it can proceed forward with<br />
design <strong>and</strong> construction.<br />
Attachment(s):<br />
OCWD Budget—Section 8—Capital Improvement Program<br />
CIP Program Summary<br />
Presentation<br />
RECOMMENDATION<br />
Provide comments <strong>and</strong> direction to staff.<br />
DISCUSSION/ANALYSIS<br />
The FY2013-14 Capital Improvement Program (CIP) is provided on the following pages.<br />
The CIP projects are funded by debt proceeds, water quality lawsuit settlements, state<br />
loans, grants <strong>and</strong> $5 million from operating revenues (Pay-as-you-go Program). The total<br />
proposed CIP cost for the FY2013-14 budget is $65.6 million <strong>and</strong> includes 21 projects.<br />
The CIP is primarily driven by the following objectives: (1) increasing the District’s recharge<br />
capacity to allow for increased sustainable production out of the groundwater basin;<br />
(2) protecting water quality by removing contaminated groundwater from the basin; <strong>and</strong><br />
(3) protecting the coastal portion of the groundwater basin.<br />
Budgeting of project expenditures does not authorize staff to proceed with a project. Each<br />
budgeted project must be individually reviewed <strong>and</strong> formally approved by the Board via the<br />
1
preparation of an Engineer’s Report. In addition, the Board of Directors would need to<br />
approve the design <strong>and</strong> the construction contracts as/if the project progresses forward.<br />
The expenditures for each project are shown in the fiscal year they are anticipated to occur<br />
in. The District has many multi-year projects that require several years to process <strong>and</strong><br />
construct.<br />
PRIOR RELEVANT COMMITTEE/BOARD ACTION(S):<br />
April 3, 2013<br />
March 14, 2013<br />
March 13, 2013<br />
March 6, 2013<br />
January 16, 2013<br />
December 13, 2012<br />
Review proposed FY2013-14 General Fund Budget<br />
Review proposed FY2013-14 R&R Budget<br />
Review proposed FY2013-14 Water Budget <strong>and</strong> Water Reserves<br />
Receive proposed FY2013-14 Budget<br />
RA & BPP <strong>Project</strong>ions<br />
Establish budget schedule <strong>and</strong> process<br />
2
CAPITAL IMPROVEMENT PROGRAM<br />
The fiscal year (FY) 2013-14 Capital Improvement Program (CIP) is provided on the<br />
following pages. The CIP projects are funded by debt proceeds, grants, litigation<br />
settlements, state loans <strong>and</strong> $5 million from operating revenues. The assets created by<br />
the CIP projects typically have a useful life of between five to seventy years.<br />
The total proposed CIP cost for the FY 2013-14 budget is $65.57 million <strong>and</strong> it includes<br />
21 projects. The life span of various CIP projects varies from project to project <strong>and</strong> it<br />
can be three years or longer. The District will fund $5 million of the $65.57 million dollar<br />
CIP budget from the operating revenues. This District practice is very useful in keeping<br />
the debt service cost to the minimum <strong>and</strong> maintenance coverage targets.<br />
The CIP is primarily driven by the following objectives: (1) increasing the District’s<br />
recharge capacity to allow for increased sustainable production out of the groundwater<br />
basin; (2) protecting water quality by removing contaminated groundwater from the<br />
basin <strong>and</strong> providing additional wetl<strong>and</strong>s treatment for Santa Ana River flows; <strong>and</strong><br />
(3) protecting the coastal portion of the groundwater basin.<br />
Budgeting of project expenditures does not authorize staff to proceed with a project.<br />
Each budgeted project must be individually reviewed <strong>and</strong> formally approved by the<br />
Board via the preparation of an Engineer’s Report. In addition, the Board would need to<br />
approve the design <strong>and</strong> the construction contracts as/if the project progresses forward.<br />
The expenditures for each project are shown in the fiscal year they are anticipated to<br />
occur in. The District has many multi-year projects that require several years to process<br />
<strong>and</strong> construct. Table 8-1 provides a broad summary of the projects in the CIP. A brief<br />
description <strong>and</strong> status of each project are provided on the attached Capital <strong>Project</strong>s<br />
Information sheet.<br />
TABLE 8-1<br />
SUMMARY OF PROJECTS IN CAPITAL IMPROVEMENT PROGRAM<br />
PROJECT TYPE<br />
WATER SUPPLY<br />
WATER QUALITY<br />
COASTAL<br />
OBJECTIVE<br />
PROVIDE FOR INCREASED GROUNDWATER PRODUCTION AND CREATE<br />
SUPPLIES WHERE ECONOMICAL AS COMPARED WITH MWD RATES.<br />
Construct facilities to increase recharge capacity <strong>and</strong><br />
percolation rates to allow for increased groundwater pumping<br />
Improve existing facilities to increase percolation rates<br />
Create new water supply<br />
PROTECT THE QUALITY OF THE GROUNDWATER BASIN SUPPLIES.<br />
Protect groundwater in north basin by extracting <strong>and</strong> treating<br />
wells threatened by VOC contamination in Anaheim <strong>and</strong><br />
Fullerton<br />
Protect groundwater in south basin by extracting <strong>and</strong> treating<br />
wells threatened by VOC contamination in Santa Ana<br />
MITIGATE FOR EXISTING AND PROJECTED FUTURE PROBLEMS ALONG<br />
Orange County Water District<br />
FY 2013-14 Budget Report
PROJECT TYPE<br />
IMPROVEMENTS<br />
OBJECTIVE<br />
THE COAST.<br />
Construct barrier facilities to prevent seawater intrusion<br />
The cost information for multi-year debt <strong>and</strong> operating reserve funded projects is<br />
summarized in Table 8-2.<br />
The OCWD staff works closely with the Board of Directors in processing capital<br />
projects. Formal Board approval is required at various stages of a project’s life as<br />
shown below:<br />
1. Inclusion in OCWD annual budget;<br />
2. Issuance of Request for Proposals for hiring of consultants for fees greater<br />
than $20,000 to assist in processing project documents;<br />
3. Awarding consultant contracts greater than $20,000;<br />
4. Approval of Feasibility Study Report, if so directed by General Manager;<br />
5. Approval of necessary CEQA documents;<br />
6. Approval of project Engineer’s Report;<br />
7. Approval of any agreements (i.e. grant funding, interagency);<br />
8. Approval of advertising construction contracts;<br />
9. Award of construction contracts;<br />
10. Approval of change orders greater than 5% of construction budget; <strong>and</strong><br />
11. Approval of Notice of Completion<br />
The District primarily uses long-term debt to fund capital projects. The District policy for<br />
using long-term debt was established in October 2000. The policy calls for the following:<br />
Preliminary project expenses related to direct research are to be paid from<br />
the General Fund;<br />
<strong>Project</strong> expenses for such items as feasibility reports, pilot studies, engineer’s<br />
reports, compliance with CEQA, <strong>and</strong> project design <strong>and</strong> construction may be<br />
capitalized <strong>and</strong> funded with long-term debt; <strong>and</strong><br />
<strong>Project</strong> expenses that are capitalized <strong>and</strong> funded with long-term debt <strong>and</strong> to<br />
which do not lead to construction of a project will require an adjustment by the<br />
Accounting Department to pay off the long-term debt incurred using cash<br />
reserves.<br />
Orange County Water District<br />
FY 2013-14 Budget Report
Orange County Water District<br />
FY 2013-14 Budget Report
Fiscal Year 2013-14<br />
Capital Improvement Program<br />
Budget Review<br />
Water Issues Committee<br />
April 10, 2013
FY 2013-14 Budget Schedule<br />
Date Meeting Topic<br />
December 13, 2012 Admin/Finance Cte Budget preparation overview <strong>and</strong> kick-off<br />
January 16, 2013 Board Provide preliminary BPP <strong>and</strong> RA estimates to Producers<br />
March 6, 2013 Board Present Draft Budget<br />
March 13, 2013 Water Issues Cte Review Water Budget<br />
Review Water Reserves<br />
March 13, 2013 Producers Present Draft Budget<br />
March 14, 2013 Admin/Finance Cte Review R&R Fund Budget<br />
April 3, 2013 Board Review General Fund Budget<br />
April 10, 2013 Water Issues Cte Review CIP Budget<br />
April 10, 2013 Producers Selected Budget topics<br />
April 11, 2013 Admin/Finance Cte Selected Budget topics<br />
April 17, 2013 Board Public Hearing to set RA & BPP<br />
Consideration to approve budget
Budget Components<br />
Total Budget - $184.7 million<br />
R&R Expenditures<br />
$13.7<br />
Retiree Medical Benefit<br />
$1.2<br />
General Fund<br />
$52.6<br />
CIP<br />
$65.6<br />
New Equipment<br />
$0.6<br />
Water Purchases<br />
$20.0<br />
Debt Service<br />
$31.0 or $32.2
Summary of Proposed 2013-14 CIP<br />
• Total cost of $65.6M<br />
21 CIP projects funded<br />
through long-term debt,<br />
grants, settlement<br />
proceeds, state loans &<br />
operating revenues<br />
(PAYGO)<br />
Pre‐Design<br />
• Feasibility Study<br />
• Engineer’s Report<br />
•CEQA<br />
Design<br />
•Plans<br />
•Specifications<br />
Construction<br />
Board Action<br />
Board Action
FY2013-14 CIP <strong>Project</strong>s<br />
<strong>Project</strong><br />
Amount<br />
GWRS Initial Expansion 40,861,081<br />
South Basin Groundwater Protection 2,576,485<br />
MTBE Remediation <strong>Project</strong> 1,562,568<br />
North Basin Groundwater Protection 6,401,637<br />
Prado Equipment Yard Expansion 29,200<br />
Floating Pump Station Retrofit, Canopy, Ladder 75,000<br />
Desilting Demonstration <strong>Project</strong> 1,500,000<br />
Sunset Gap Seawater Intrusion Monitoring Well 1,021,382<br />
Mid Basin Injection Demonstration <strong>Project</strong> 2,036,024<br />
Fletcher Basin 5,648,948<br />
Continued
FY2013-14 CIP <strong>Project</strong>s<br />
Continued<br />
<strong>Project</strong><br />
Amount<br />
Prado Sediment Management Demonstration <strong>Project</strong> 1,020,069<br />
JD Edward & Maximo Upgrade 500,000<br />
East Newport Mesa Monitoring Wells 460,000<br />
FHQ Operations Management System 140,000<br />
Hallway Educational Panel 1,042,289<br />
River Road Bridge Spillway 20,000<br />
Upsize Lab HVAC Flow Control Valve 224,294<br />
Alamitos Seawater Barrier Improvements 450,603<br />
Total 65,569,580
CIP Summary
GWR System Initial Expansion<br />
• Construct a 30 mgd<br />
expansion to the existing<br />
AWPF<br />
FY 2013-14 Cost: $40,900,000<br />
Total Capital Cost: $142,700,000<br />
<strong>Project</strong>ed 2013-14 Activity<br />
• Construction
Riverbed Filtration Desilting<br />
Demonstration <strong>Project</strong><br />
• Install collection gallery<br />
comprised of 8-inch perforated<br />
pipe <strong>and</strong> collection tanks in<br />
OCWD off-river area in<br />
Anaheim to convey 15 cfs of<br />
filtered water in a 36-inch<br />
pipeline for recharge into Olive<br />
Basin<br />
FY 2013-14 Cost: $1,500,000<br />
Total Capital Cost: $1,500,000<br />
<strong>Project</strong>ed 2013-14 Activity<br />
• Construction
Mid Basin Injection Demonstration<br />
<strong>Project</strong> Phase II Equipping<br />
Injection Well MBI-1 <strong>and</strong><br />
Monitoring Well SAR-10<br />
GWR Pipeline<br />
Santa Ana River<br />
W Edinger Ave<br />
Monitoring Well<br />
SAR-11<br />
Centennial Park<br />
FY 2013-14 Cost: $2,036,024<br />
Total Capital Cost: $7,680,000<br />
N<br />
• Construction, complete<br />
equipping injection well<br />
<strong>and</strong> site improvements<br />
<strong>Project</strong>ed 2013-14 Activity<br />
• Construction
Mid Basin Injection Demonstration<br />
<strong>Project</strong> Phase II Equipping<br />
• Construction, complete<br />
equipping injection well<br />
<strong>and</strong> site improvements<br />
FY 2013-14 Cost: $2,036,024<br />
Total Capital Cost: $7,680,000<br />
<strong>Project</strong>ed 2013-14 Activity<br />
• Construction
Alamitos Barrier<br />
• Construction of<br />
additional injection<br />
wells along Alamitos<br />
Barrier to close gaps in<br />
the seawater barrier<br />
FY 2013-14 Cost: $450,603<br />
Total Capital Cost: $8,200,000<br />
<strong>Project</strong>ed 2013-14 Activity<br />
• Design
Fletcher Basin<br />
• Convert OCFCD-owned<br />
basin into recharge<br />
facility<br />
FY 2013-14 Cost: $5,648,948<br />
Total Capital Cost: $5,708,948<br />
<strong>Project</strong>ed 2013-14 Activity<br />
• Construction
Action<br />
Provide comments <strong>and</strong> direction to staff
AGENDA ITEM SUBMITTAL<br />
Meeting Date: April 10, 2013<br />
Budgeted: Yes<br />
Budgeted Amount: $600,000<br />
To: Water Issues Committee/ Cost Estimate: $530,000<br />
Board of Directors<br />
Funding Source: General Fund<br />
Program/Line Item No. 1044.53001.9900<br />
From: Mike Markus<br />
General Counsel Approval: N/A<br />
Engineers/Feasibility Report: N/A<br />
Staff Contact: G. Woodside<br />
CEQA Compliance: N/A<br />
Subject:<br />
ACCELERATION OF OCWD FUNDING FOR PRADO BASIN<br />
FEASIBILITY STUDY<br />
SUMMARY<br />
The District <strong>and</strong> the Army Corps of Engineers (Army Corps) have executed an<br />
agreement that establishes the District as the non-federal sponsor for the Prado Basin<br />
Feasibility Study. The Board approved accelerating up to $950,000 of District funding to<br />
make up the shortfall in federal funding <strong>and</strong> allow the study to proceed. Staff<br />
recommends that the District accelerate the remaining District funds up to the maximum<br />
50 percent of the total study cost that is allowed by the Agreement with the Army Corps.<br />
Attachment(s): Presentation<br />
RECOMMENDATION<br />
Agendize for April 17 Board meeting: Approve accelerating funding in the amount of<br />
$530,000 to the United States Army Corps of Engineers for the Prado Basin California<br />
Study <strong>and</strong> authorize District staff to transfer said funding to the federal government.<br />
BACKGROUND/ANALYSIS<br />
In March 2012, the Board approved execution of an agreement with the Army Corps of<br />
Engineers (Army Corps) for the Prado Basin Feasibility Study. The Army Corps has also<br />
executed the Agreement. This study is underway <strong>and</strong> will provide the mechanism for the<br />
District <strong>and</strong> the Army Corps to evaluate increased water conservation at Prado <strong>and</strong> also<br />
ecosystem restoration <strong>and</strong> sediment management opportunities. The Feasibility Study<br />
will evaluate increasing the flood season water conservation elevation from the current<br />
498 foot elevation to elevation 505, which will add approximately 10,000 acre-feet of<br />
storage capacity.<br />
For the entire study, the District is obligated to pay for 50 percent of the study cost.<br />
Accelerated funding from the District can be provided up to 50 percent of the study cost.<br />
District staff has been working with our federal consultants to seek federal funding for the<br />
50 percent federal cost share of the study. Additionally, members of the Board have<br />
travelled to Washington, D.C. to seek funding for the project.
Due to the tight federal budget, Congress has not yet allocated funding to the study.<br />
In June 2012, the Board approved accelerating up to $950,000 of District funds to move<br />
the project forward in light of the shortfall in federal funding. The total cost of the study is<br />
estimated to be $2,997,212.00<br />
Staff recommends the Board authorize staff to accelerate $530,000 in District funds for<br />
the Feasibility Study. This would bring the District’s total cash contribution to the<br />
Feasibility Study up to $1,480,000. This amount is approximately $19,000 less than 50<br />
percent of the total study cost, since there is an external independent peer review cost<br />
that is paid for 100 percent by the Army Corps. The District’s current fiscal year budget<br />
includes this funding but the funding is not included in next year’s proposed budget.<br />
Therefore, staff recommends that the money be advanced from the current year budget.<br />
The District’s accelerated funding of $1,480,000 would provide funding to keep the<br />
Feasibility Study moving forward until approximately April 2014, at which time the study<br />
would be out of funds unless the federal government provides funding or the District<br />
contributes funds above <strong>and</strong> beyond the 50 percent non-federal (local) sponsor share.<br />
One issue that will need to be addressed before the flood season water conservation<br />
elevation can be increased is the Dam Safety Action Class (DSAC) of 3 that has been<br />
assigned to Prado Dam. The Dam Safety Action Classification system was implemented<br />
by the Army Corps after Hurricane Katrina. The system is intended to provide consistent<br />
<strong>and</strong> systematic guidelines for appropriate actions to address the dam safety issues <strong>and</strong><br />
deficiencies of Army Corps dams. A rating of 1 is worst, 5 is best. Current Army Corps<br />
policy is that the water control manual for a dam cannot be changed if the DSAC rating is<br />
3 or worse. Prado Dam was assigned a 3.<br />
Completion of the Santa Ana River Mainstem <strong>Project</strong>, including raising the spillway, is<br />
anticipated to address this DSAC rating. Unfortunately, the Mainstem <strong>Project</strong> is not<br />
anticipated to be completed for several years, <strong>and</strong> the District would like to implement<br />
increased flood season water conservation at Prado prior to completion of the Mainstem<br />
<strong>Project</strong>. Therefore, a waiver from Army Corps policy will need to be requested <strong>and</strong><br />
approved, provided that the Feasibility Study determines that increased water<br />
conservation can be implemented without increasing risk to dam safety <strong>and</strong> flooding.<br />
Since Prado Dam temporarily holds water to elevation 505 feet in the non-flood season,<br />
<strong>and</strong> has also held water to much higher elevations for flood control purposes, it is<br />
anticipated that the Feasibility Study will conclude there is no increased safety risk due to<br />
conserving water to elevation 505 year-round.<br />
At the Committee meeting, staff will update the Board on recent progress on the<br />
Feasibility Study. The completion of the study requires reaching five milestones. Last<br />
month, the first milestone was reached, <strong>and</strong> the study is on-schedule.<br />
The attached figure shows the Feasibility Study Timeline.
PRIOR RELEVANT BOARD ACTION(S)<br />
6-20-2012, M-12-97 – Approve accelerating $950,000 in OCWD funding to the United States<br />
Army Corps of Engineers for the Prado Basin California Study <strong>and</strong> authorize District staff to<br />
transfer said funding to the federal government.<br />
3-21-2012, R12-3-28 – Approve <strong>and</strong> authorize execution of revised Agreement with the<br />
Department of the Army for the Prado Basin, California Study for the evaluation of water<br />
conservation <strong>and</strong> ecosystem restoration opportunities in Prado Basin.<br />
9-7-2011, R11-9-129 – Approve <strong>and</strong> authorize execution of Agreement with Department of the<br />
Army for the Prado Basin, California Study’, subject to approval as to form by District legal<br />
counsel; authorize General Manager to accelerate a portion the District’s required cash<br />
contribution for the Prado Basin Feasibility Study for immediate use by the Army Corps of<br />
Engineers, up to a maximum of $800,000.
Accelerated Funding for Prado<br />
Basin Feasibility Study<br />
Water Issues Committee<br />
April 10, 2013
Prado Basin Feasibility Study<br />
• Agreement with Army Corps establishes District as<br />
non-federal (local) sponsor<br />
• Feasibility Study includes<br />
– Ecosystem restoration<br />
– Water conservation (temporary stormwater capture)<br />
– Sediment management<br />
• City of Ontario interested in ecosystem restoration<br />
component
Alternatives Evaluated in<br />
Feasibility Study<br />
• Alternatives include several measures, including:<br />
– increasing flood season water conservation elevation from<br />
current 498 foot elevation to elevation 505, which will add<br />
approximately 10,000 acre-feet of storage capacity<br />
– Invasive species removal<br />
– Habitat enhancement for endangered species<br />
– Wetl<strong>and</strong>s creation<br />
– Sediment removal
Feasibility Study Timeline<br />
SCOPING<br />
ALTERNATIVE<br />
FORMULATION<br />
& ANALYSIS<br />
FEASIBILITY‐<br />
LEVEL<br />
ANALYSIS<br />
CHIEF’S<br />
REPORT<br />
AUG<br />
2012<br />
Tentatively<br />
Selected Plan<br />
Milestone<br />
MAR<br />
2014<br />
Final Report Milestone<br />
JAN<br />
2015<br />
AUG<br />
2015<br />
Alternatives Milestone<br />
MAR<br />
2013<br />
Agency Decision<br />
Milestone<br />
SEP<br />
2014
Feasibility Study Funding<br />
• 50/50 federal/non-federal cost share<br />
• $3 million study<br />
• Congress has not yet allocated money to study<br />
• District has accelerated $950,000
Accelerated Funding for<br />
Feasibility Study<br />
• Staff recommends District accelerate additional $530,000<br />
in District funds for Feasibility Study<br />
• This would bring the District’s total cash contribution to<br />
the Feasibility Study up to $1,480,000<br />
– Approximately $19,000 less than 50% of total study cost, since<br />
there is an external independent peer review cost paid for 100%<br />
percent by Army Corps<br />
• District’s current fiscal year budget includes this funding<br />
but the funding is not included in next year’s proposed<br />
budget
Recommendation<br />
• Agendize for April 17 Board meeting:<br />
Approve accelerating funding in the amount of $530,000<br />
to the United States Army Corps of Engineers for the<br />
Prado Basin California Study <strong>and</strong> authorize staff to<br />
transfer said funding to the federal government