Delay Caused By The Owner<br />
(g)<br />
(h)<br />
(i)<br />
(j)<br />
(k)<br />
(l)<br />
(m)<br />
Excessive changes in requirements or design;<br />
Defective or insufficient plans and specifications;<br />
Owner interference;<br />
Failure to provide adequate access to the site;<br />
Failure to obtain necessary permits for the work;<br />
Failure to coordinate the job when there are separate contracts awarded;<br />
Failure of the consultant to provide or approve drawings in a reasonable time;<br />
Delay Caused By The Contractor<br />
(n)<br />
(o)<br />
(p)<br />
(q)<br />
(r)<br />
(s)<br />
Contractor management and performance problems;<br />
Failure to properly man and perform the job;<br />
Poor workmanship;<br />
Failure to order materials and equipment in a timely fashion;<br />
Delays due to the fault of the contractor;<br />
Unavailability of labour, material or equipment;<br />
Delay Not Caused By A Party<br />
Delay not caused by a party is often referred to as excusable (as opposed to inexcusable) delay,<br />
or non-compensable (as opposed to compensable) delay:<br />
• An excusable delay is one that will serve to justify an extension of the contract<br />
performance time – it excuses the party from meeting a contractual deadline;<br />
• Inexcusable delay is one for which the party assumes the risk of the cost and<br />
consequences, including the resulting impact on others, such as delay due to a<br />
contractor’s own mismanagement;<br />
• Generally, whether a delay is excusable or inexcusable is a matter of contract.<br />
The question asked is, does the contract permit the delay in question<br />