28 Chapter 6. Proposed Construction Cycle<br />

6.7 Assembly of CRYRING <strong>and</strong> Injection Beam Lines<br />

6.7.1 Preparation of Magnetic Components: Fiducialization<br />

As network measurements <strong>and</strong> final alignment are based on using Laser Trackers <strong>and</strong> Digital<br />

Levels about 55 magnetic components of the CRYRING <strong>and</strong> two injection beam lines have to be<br />

fiducialized be<strong>for</strong>e assembly. Fiducialization means that the magnetic axes, planes <strong>and</strong> effective<br />

centres of dipole, quadrupole or sextupole magnets have to be transferred to mechanical marks<br />

suitable <strong>for</strong> the final alignment during the assembly of beam lines <strong>and</strong> ring. As the alignment of<br />

12 quadrupole magnets in the injection beam lines will be carried out by telescope, fiducialization<br />

of these components is not necessary <strong>and</strong> a 3D-determination of the actual condition w.r.t. the<br />

global coordinate system will not be possible.<br />

6.7.2 Procurement of Mechanical Parts<br />

The procurement of about 200 additional mechanical supports is necessary <strong>for</strong> lifting the low<br />

energy injection beam line <strong>and</strong> the present beam axis of CRYRING from 1.5 m to 2.0 m which<br />

is the nominal height <strong>for</strong> ion beams in ESR <strong>and</strong> in the Target Hall.<br />

The material <strong>for</strong> the supports of the 20 m long new beam line from the high energy beam<br />

transport to the CRYRING is available from the pool of dismantled systems.<br />

6.7.3 Assembly<br />

Survey Be<strong>for</strong>e starting the mechanical assembly the positions of all bending magnets (beam<br />

lines <strong>and</strong> CRYRING) have to be surveyed precisely. Position marks on the ground floor with an<br />

accuracy of ±0.5 mm will help to achieve a rather good positioning during the assembly work<br />

without the presence of the survey people.<br />

Assembly of CRYRING The assembly of the ring will be per<strong>for</strong>med sector by sector. By<br />

this way assembled sectors can already be connected to power supplies <strong>and</strong> water cooling while<br />

others are still being mechanically assembled. Fine alignment of the ring can be done by means<br />

of laser tracking simultaneously to the mechanical assembly of the injection beam lines.<br />

Assembly of Injection Beam Lines The alignment of the beam lines will be done by applying<br />

conventional methods. There<strong>for</strong>e three pillars with bearings <strong>for</strong> telescopes have to be surveyed in<br />

advance. Targets marking the axes of quadrupoles will allow fine adjustments to about ±0.5 mm<br />

accuracy. Suitable marks on the luminescent screens, applied <strong>for</strong> the determination of the ion<br />

beam axis, can be adjusted by this method to similar accuracy.