07.01.2015 Views

Technical and Regulatory Guidance for In Situ Chemical ... - ITRC

Technical and Regulatory Guidance for In Situ Chemical ... - ITRC

Technical and Regulatory Guidance for In Situ Chemical ... - ITRC

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

locations on the downgradient side of the barrier fence at shallow <strong>and</strong> deep depths to monitor the<br />

effectiveness of the remediation. Four of these wells were installed in two pairs of shallow <strong>and</strong> deep<br />

wells, to depths of 23 <strong>and</strong> 35 feet, respectively. The remaining two wells at the ends of the barrier<br />

fence were installed to 28 feet bgs. Since each C-Sparger control panel can operate a maximum of<br />

four sparging wells, two control panels were installed, with one controlling the two middle wells,<br />

<strong>and</strong> the other controlling the four outer wells. The ozone-air mixture was supplied to the sparging<br />

wells (one well per controller at a time) at approximately 2 cubic feet per minute, at pressures of 5-<br />

10 psi, with an ozone concentration of 1.5-2.5 ppm. One SVE vacuum blower was installed <strong>and</strong><br />

connected to all six C-Sparger wells in parallel <strong>for</strong> continuous vapor extraction. System operation<br />

started August 26, 1998.<br />

Operational Per<strong>for</strong>mance<br />

Prior to system startup, on August 17, 1998, baseline samples were taken from four of the six<br />

downgradient monitoring wells. PCE concentrations ranged from 5.82 micrograms per liter (ug/L)<br />

to 21.6 ug/L.<br />

Operation of the KVA C-Sparger system at this site was plagued by the same types of equipment<br />

failures that occurred at the Garden City Laundry site, which used identical control equipment.<br />

Despite the non-continuous operation of the system, follow-up sampling events were conducted in<br />

October <strong>and</strong> December 1999. Dissolved oxygen levels in nearly all of the monitoring wells were<br />

found to have increased by 1 ppm or more (a 50-100% increase) by the December sampling event.<br />

PCE concentrations ranged from non-detect to 19 ug/L in the previously sampled monitoring wells.<br />

Concentrations in wells near the southwest end of the sparge well array showed decreases in both<br />

follow-up sampling events, while other wells showed no clear trend. One well showed a threefold<br />

decrease in concentration between the October <strong>and</strong> December events (15 ug/L to 5 ug/L) that may<br />

be unrelated to the operation of the sparging wells.<br />

Problems<br />

As with the installation of the KV Associates C-Sparger system in Garden City, Kansas, numerous<br />

mechanical <strong>and</strong> electrical problems with the control system resulted in intermittent failures of the<br />

sparging system. These failures resulted from blown fuses, leaks in fittings, split hoses, <strong>and</strong> problems<br />

with electrical <strong>and</strong> electronic components of the controllers. These reliability problems are similar<br />

to those encountered during the pilot test; there<strong>for</strong>e, the ability of this system to carry out a long-term<br />

remediation project is unproven.<br />

<strong>In</strong> addition, a change in contractors midway through the operational phase of the project resulted in<br />

a year-long interruption in sample collection <strong>and</strong> analysis (October 1998 to October 1999). This lack<br />

of data complicates further any evaluation of the system’s per<strong>for</strong>mance.<br />

Costs<br />

<strong>In</strong>stalling <strong>and</strong> operating this barrier-wall sparging <strong>and</strong> SVE array cost $133,500, not including the<br />

costs of the pilot study or previous work to determine the extent of the plume <strong>and</strong> the site<br />

hydrogeology. These costs can be broken down as follows:<br />

C-Sparger controllers <strong>and</strong> downhole components - $50,000<br />

<strong>In</strong>stallation of six monitoring wells <strong>and</strong> six sparge wells - $30,500<br />

SVE system components - $25,000<br />

SVE <strong>and</strong> C-Sparger controller installation - $17,000<br />

Operation, maintenance, <strong>and</strong> repairs - $11,000<br />

B5

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!