17. DISPUTE AND SETTLEMENT:<br />

In case of any dispute with respect to the terms of Agreement, the matter<br />

may be represented to DG <strong>Tourism</strong> by the selected Consultant after giving a<br />

notice of 30 days. The matter shall be examined and put up to Principal<br />

Secretary, <strong>Tourism</strong>, Govt. of U.P. for decision. In case the dispute is not<br />

resolved at the level of Principal Secretary, <strong>Tourism</strong>, Govt. of U.P. the<br />

matter shall be referred to Infrastructure and Industrial Development<br />

Commissioner (I.I.D.C).<br />

If after 30 days from the commencement of such direct negotiations at the<br />

level of I.I.D.C the dispute is not resolved it shall be settled by arbitrator<br />

under the Arbitration and Conciliation Act, 1996 and his decision would be<br />

final, binding on both the parties.<br />

The Arbitration and Conciliation Act 1996 and the rules made there under<br />

and any statutory modification or re-enactments thereof, shall apply to the<br />

arbitration proceedings.<br />

The venue of the arbitration shall be Lucknow, U.P.<br />

Pending the submission of and/or decision on a dispute, difference or claim<br />

or until the arbitral award is published; the Consultant shall continue to<br />

perform all its obligations under this agreement without prejudice of final<br />

adjustment in accordance with such award.<br />

18. LEGAL JURISDICTION:<br />

Any legal dispute arising out of the contract shall be settled at the Court of<br />

Law located at Lucknow.<br />