April 2007.pdf - Electrical Business Magazine
April 2007.pdf - Electrical Business Magazine
April 2007.pdf - Electrical Business Magazine
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
From the Legal Desk<br />
Non-compliant bids and fairness<br />
And other specific tender questions<br />
By Stephen<br />
Tatrallyay<br />
Do the rules of fairness in tendering apply to<br />
relations between a GC and a subtrade, or just<br />
between owners and contractors<br />
The Supreme Court of Canada answered this in Ellis Don<br />
v. Naylor Electric. 1 There was clear evidence that Ellis was<br />
bid shopping among the electrical trades while it waited for<br />
a decision from the owner as to whether the project would<br />
proceed. Ellis told one subtrade, Naylor, that it could base<br />
its price on non-union workers, although Ellis knew there<br />
was an application against it at the Labour Relations Board<br />
(LRB) wherein the IBEW claimed bargaining rights for all<br />
electrical workers on Ellis projects in Ontario.<br />
Ellis continued to negotiate with Naylor, carrying its<br />
price in the final submission to the owner, which was made<br />
some time after an adverse LRB ruling declaring the IBEW<br />
Collective Agreement covered all electricians employed by<br />
both Ellis and Naylor on Ellis projects. In the end, Ellis<br />
contracted with a union electrical subtrade and Naylor sued,<br />
claiming it had been unfairly treated by Ellis.<br />
Ellis argued that a clause in the contract gave it the right to<br />
refuse to deal with Naylor if it had a “reasonable objection”<br />
to using them. Apart from the fact that the clause was clearly<br />
drawn to protect the owner, the court held that Ellis—by its<br />
actions in inviting Naylor’s bid and negotiating with Naylor,<br />
not to mention carrying Naylor’s price in its final tender<br />
with full knowledge of Naylor’s affiliation with another<br />
union—had waived any right of objection it may have had<br />
under this clause.<br />
This was further reinforced by the fact that Ellis had continued<br />
to use Naylor’s price, especially to get better prices<br />
from other subtrades, even after it learned of the LRB’s decision<br />
against it. Ultimately, Naylor was awarded damages for<br />
breach of the duty of fairness in Contract A, leading to the<br />
reasonable conclusion that such a duty exists between GCs<br />
and subtrades, as well as owners and GCs.<br />
What about when all bids are non-compliant<br />
This situation often arises in circumstances where there is an<br />
upset price for an improvement. A fixed price is allocated to<br />
part of the improvement—say, the gymnasium in a school—<br />
and the architect designs it to a performance specification.<br />
The trades tender to what the architect has designed, and all<br />
the prices come in way over budget.<br />
There are two theories as to what should be done in this<br />
situation. The first says you reject all bids, tear up the specs<br />
and try to design something cheaper, then allow all previous<br />
tenderers to provide a new price. The other says you<br />
negotiate with the lowest bidder complying with the original<br />
specs. (The Canadian Construction Documents Committee<br />
[CCDC] takes this position in its Document 23.)<br />
In Dominion Construction v. Keewatin-Patricia District<br />
School Board, 2 the lowest price—which was still more than<br />
the upset limit—came from a contractor who found a different<br />
way of doing the work. In essence, both the work and<br />
the price he proposed were non-compliant. When the owner<br />
let all trades re-tender on the basis of the revised specs, then<br />
awarded the contract to another trade (whose original price<br />
was non-compliant but at least based on the specs), the first<br />
contractor sued.<br />
Justice Zielinski held that since all bids were non-compliant,<br />
the owner could essentially do what it wanted. It did<br />
not have to comply with CCDC Document 23 (which, in<br />
any event, is only a suggestion). The fact that the owner<br />
did let the non-compliant bidder back into the rebidding<br />
process made no difference: once non-compliant, always<br />
non-compliant.<br />
Most recent decision: are the times a-changin’<br />
On 25 January 2007, the Supreme Court of Canada rendered<br />
its decision in Double N Earthmoving v. City of<br />
Edmonton. 3 This decision signals a change in the nature<br />
of the way the majority of the court thinks tendering fairness<br />
claims should be treated, and suggests that the owner’s<br />
duty to tenderers is much less substantial than previously<br />
thought. We will explore this decision, and hopefully early<br />
judicial reaction to it, in the next column.<br />
The information contained in this column is not a legal opinion.<br />
For more specific interpretations, feel free to contact the author or<br />
consult your own legal counsel.<br />
Notes<br />
1. [2001] 2 SCR 943.<br />
2. An unreported decision of the Ontario Superior Court<br />
(Zielinski J) released 4 June 2004, Court File No. Thunder<br />
Bay 010758).<br />
3. Not yet reported, [2007] SCC 3.<br />
Stephen Tatrallyay is a prominent Toronto construction lawyer and can<br />
be reached via e-mail at statrallyay@rogers.com or by calling (416)<br />
482-5164. He is also a member of EB’s Editorial Advisory Board.<br />
The new, stay-safe<br />
Ballast Disconnect<br />
for 347V lighting<br />
No-twist push-in for quicker connections<br />
Meets CEC 30-308(4) code changes<br />
Perfect for OEM or retro t lighting<br />
Wide wire range: 12-18 AWG<br />
LUMINAIRE DISCONNECT<br />
3HME<br />
INFO NO. 24<br />
Permanent safety<br />
standard labels included<br />
with PowerPlug<br />
IDEAL INDUSTRIES (CANADA), CORP.<br />
Customer Service 800 824-3325<br />
www.idealindustries.ca<br />
16 • APRIL 2007 • www. mag.com<br />
Ideal_PowerPlug_EB_<strong>April</strong>07.indd 1 3/19/07 11:38:15 AM