Quaity control in CMRL Depot works at Koyambedu<br />
A specific Project Quality Plan (PQP) has been approved and followed for Koyambedu Depot<br />
work. Required Quality Control Team to ensure quality of work has been engaged by contractors<br />
and General Consultants. An independent audit wing of General Consultants also established to<br />
audit the quality of works.<br />
Earth filling & Ground Improvement works:<br />
As per the scope of work a huge earth filling work about 4 lakhs cum is involved in the Koyambedu<br />
work including ground improvement work. The contract provides details of quality control<br />
tests to be conducted for selecting the fill material as well as for earth filling work. The samples of<br />
fill material are tested for particle size distribution, liquid limit, plasticity index, coefficient of uniformity,<br />
free swelling index, sulphate content, optimum moisture content, and maximum dry density<br />
as per PQP. The samples are tested for the moisture content and relative compactions<br />
(FDD) as per contract provisions.<br />
* 294 samples from 23 quarries have been tested for fill material to ascertain the suitability of<br />
the soil as per specifications;<br />
* 3004 samples of soil have been tested for FDD (Field Dry Density) to ensure 98/95% of<br />
MDD as the case may be;<br />
* The settlement of the soil filling is monitored by measuring the settlement through the settlement<br />
marker installed at prescribed spacing; and<br />
* Similarly the pore water pressure of the water in the soft day layer is measured by means of<br />
Piezometers.<br />
Concrete for piling work<br />
Piling work of 600mm dia.(driven cast in-situ) is in progress. Quality control test for concrete in<br />
the field has been conducted as per PQP.<br />
* 645 concrete cubes have been cast so far and it is a continuous process as the concreting in<br />
progress. So far 243 cubes are tested (7 th and 28 th day) as per specifications.<br />
Piezometer Reading in progress Plate Settlement Marker reading in Progress<br />
Progress of Depot work<br />
The up-to-date progress in Depot work is as follows:<br />
Sl. No. Description Unit Qty<br />
1 Earth filling Cum 142787<br />
2 Installation of Prefabricated Vertical Drain(PVD) RMT 880955<br />
3 Surcharge filling Cum 64297<br />
4 Test piles of 600 mm dia (Admn. Bldg. and shed) No 4<br />
5 Working piles of 600 mm dia (Admn. Building) No. 88<br />
Page 2 Chennai Metro Rail Newsletter