14.11.2012 Views

Prisma Plus - error

Prisma Plus - error

Prisma Plus - error

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Slick changeover<br />

keeps fish fresh<br />

When the mains switchboard at one of<br />

the world’s largest tuna-processing<br />

plants began feeling its age, Schneider<br />

Electric NZ and Napier’s Electrotech<br />

Controls Ltd teamed up to design, build<br />

and supply a more efficient replacement.<br />

The COS Samoa Packing Company in<br />

Pago Pago, American Samoa, processes<br />

some 300 tonnes of tuna a day and in<br />

global terms is second in size only to the<br />

neighboring StarKist plant.<br />

COS runs a 24-hour operation, and its<br />

major electrical demand is for refrigeration,<br />

water pumps and generating steam. In<br />

recent years power reliability had become<br />

an issue as a result of an increasingly<br />

fragile mains switchboard. After a tendering<br />

process, the plant’s management<br />

appointed Electrotech to design, build and<br />

supply a replacement, and Schneider<br />

Electric supplied much of the hardware.<br />

“A major problem with the equipment,”<br />

says Electrotech project manager Steve<br />

Pardoe, “was the environment in which it<br />

operated. There were a few leaks in the<br />

roof of the building, and that had caused<br />

quite a bit of corrosion. As a result,<br />

the local crews were replacing the<br />

switchboard’s ACBs on a regular basis –<br />

as a kind of preventative maintenance.”<br />

Electrotech’s design of the new switchboard<br />

was governed by the power feed into the<br />

plant – delivered from two 2MVA<br />

transformers.That was complemented by<br />

three 940kW standby, diesel-generating<br />

sets. Designed as standby units, in practice<br />

the generating sets ran continuously, in<br />

parallel with the electricity supply.<br />

“Essentially,” says Pardoe, “we were dealing<br />

with three separate switchboards mounted<br />

side by side.The generator board – for the<br />

three standby generators – and two for the<br />

main distribution board.The two main<br />

switchboards were linked by power cables.<br />

“Because of the potential fault current<br />

associated with paralleling two 2MVA<br />

transformers, we had to keep our design<br />

similar: two switchboards that would be<br />

kept totally separate – but interconnected<br />

– for the transformers, and one for the<br />

generating sets.”<br />

DESIGN<br />

Optimising and monitoring the<br />

performance of the new switchboards<br />

was one of the project’s major drivers.<br />

“The old control system was fraught with<br />

difficulties,” says Pardoe. “It was totally<br />

manual and there was no monitoring. Even<br />

synchronizing the three generators was a<br />

manual operation. Operators had no way<br />

of tracking power consumption.”<br />

The new <strong>Prisma</strong> switchboards were<br />

designed and built at Electrotech’s Napier<br />

plant. The design team from Electrotech<br />

specified a full distribution and automation<br />

system complete with SCADA and power<br />

factor correction.<br />

Among the challenges the team faced was<br />

designing and specifying equipment that<br />

complied with US regulations. “We had to<br />

take virtually everything we needed with<br />

us, because the US system still uses<br />

imperial measurements.”<br />

In addition, the team had to factor different<br />

voltage system into their design – 110<br />

volts, a 240-volt system as well as a 24-volt<br />

DC system for all controls.<br />

Schneider-Electric’s Bruce Morrison says<br />

highly specialised Merlin Gerin breakers<br />

were fitted to the <strong>Prisma</strong> switchboards.<br />

“As a standard feature, all source breakers<br />

were equipped with ammeters to facilitate<br />

easier power monitoring.This included full<br />

modbus communication with energy<br />

management and preventative<br />

maintenance monitoring achieved. In<br />

addition, all 24 x 800A feeder breakers<br />

were supplied with PM500 power monitors.”<br />

INSTALLATION<br />

The project ran over a five-week period<br />

in April and May this year, and installing<br />

the two switchboards was by far the most<br />

difficult part of the project because of the<br />

very tight time limit. “The fish is kept in<br />

freezers and the factory can only survive<br />

for about 24 hours – tops – without<br />

electricity,” says Pardoe. “And that’s what<br />

we were given for the changeover.”<br />

As it happened, the installation crew<br />

only needed 21 hours. “Apart from the<br />

success of meeting the time-limit, it was<br />

particularly gratifying to witness the<br />

improved efficiency of the switchboards.<br />

Tests conducted after the installation<br />

showed the boards were running at a<br />

significantly lower load than the previous<br />

equipment. We believe a lot of the<br />

‘excess’ load on the old boards was<br />

attributable to heat losses and<br />

poor connections.”<br />

Control is also much easier. It’s entirely<br />

automatic, and operators now monitor<br />

the switchboards’ performance on a PC<br />

screen. Being able to monitor load in real<br />

time, Pardoe points out, “also allows<br />

operators to consider strategies such<br />

as peak load sharing for the first time –<br />

and improve the plant’s overall<br />

energy efficiency.”<br />

THE HARDWARE<br />

Schneider-Electric supplied the majority of the components used in the two<br />

switchboards. Below is a selection of the Merlin Gerin items:<br />

2 x 3200A 3P 85kA Masterpact NW ACB Mains Breakers<br />

2 x 3200A 3P ACB Masterpact NW Generator Feeders<br />

3 x 2000A ACB Masterpact NW Generator Breakers<br />

2 x 3200A ACB Masterpact NW Bus Ties<br />

24 x 800A MCCB Compact NS Sub Circuit Feeders<br />

24 x PM 500 Powerlogic power meters<br />

5 x PM 850 Powerlogic power meters<br />

For more information contact your<br />

local Sales Engineer

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!