Prisma Plus - error
Prisma Plus - error
Prisma Plus - error
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Slick changeover<br />
keeps fish fresh<br />
When the mains switchboard at one of<br />
the world’s largest tuna-processing<br />
plants began feeling its age, Schneider<br />
Electric NZ and Napier’s Electrotech<br />
Controls Ltd teamed up to design, build<br />
and supply a more efficient replacement.<br />
The COS Samoa Packing Company in<br />
Pago Pago, American Samoa, processes<br />
some 300 tonnes of tuna a day and in<br />
global terms is second in size only to the<br />
neighboring StarKist plant.<br />
COS runs a 24-hour operation, and its<br />
major electrical demand is for refrigeration,<br />
water pumps and generating steam. In<br />
recent years power reliability had become<br />
an issue as a result of an increasingly<br />
fragile mains switchboard. After a tendering<br />
process, the plant’s management<br />
appointed Electrotech to design, build and<br />
supply a replacement, and Schneider<br />
Electric supplied much of the hardware.<br />
“A major problem with the equipment,”<br />
says Electrotech project manager Steve<br />
Pardoe, “was the environment in which it<br />
operated. There were a few leaks in the<br />
roof of the building, and that had caused<br />
quite a bit of corrosion. As a result,<br />
the local crews were replacing the<br />
switchboard’s ACBs on a regular basis –<br />
as a kind of preventative maintenance.”<br />
Electrotech’s design of the new switchboard<br />
was governed by the power feed into the<br />
plant – delivered from two 2MVA<br />
transformers.That was complemented by<br />
three 940kW standby, diesel-generating<br />
sets. Designed as standby units, in practice<br />
the generating sets ran continuously, in<br />
parallel with the electricity supply.<br />
“Essentially,” says Pardoe, “we were dealing<br />
with three separate switchboards mounted<br />
side by side.The generator board – for the<br />
three standby generators – and two for the<br />
main distribution board.The two main<br />
switchboards were linked by power cables.<br />
“Because of the potential fault current<br />
associated with paralleling two 2MVA<br />
transformers, we had to keep our design<br />
similar: two switchboards that would be<br />
kept totally separate – but interconnected<br />
– for the transformers, and one for the<br />
generating sets.”<br />
DESIGN<br />
Optimising and monitoring the<br />
performance of the new switchboards<br />
was one of the project’s major drivers.<br />
“The old control system was fraught with<br />
difficulties,” says Pardoe. “It was totally<br />
manual and there was no monitoring. Even<br />
synchronizing the three generators was a<br />
manual operation. Operators had no way<br />
of tracking power consumption.”<br />
The new <strong>Prisma</strong> switchboards were<br />
designed and built at Electrotech’s Napier<br />
plant. The design team from Electrotech<br />
specified a full distribution and automation<br />
system complete with SCADA and power<br />
factor correction.<br />
Among the challenges the team faced was<br />
designing and specifying equipment that<br />
complied with US regulations. “We had to<br />
take virtually everything we needed with<br />
us, because the US system still uses<br />
imperial measurements.”<br />
In addition, the team had to factor different<br />
voltage system into their design – 110<br />
volts, a 240-volt system as well as a 24-volt<br />
DC system for all controls.<br />
Schneider-Electric’s Bruce Morrison says<br />
highly specialised Merlin Gerin breakers<br />
were fitted to the <strong>Prisma</strong> switchboards.<br />
“As a standard feature, all source breakers<br />
were equipped with ammeters to facilitate<br />
easier power monitoring.This included full<br />
modbus communication with energy<br />
management and preventative<br />
maintenance monitoring achieved. In<br />
addition, all 24 x 800A feeder breakers<br />
were supplied with PM500 power monitors.”<br />
INSTALLATION<br />
The project ran over a five-week period<br />
in April and May this year, and installing<br />
the two switchboards was by far the most<br />
difficult part of the project because of the<br />
very tight time limit. “The fish is kept in<br />
freezers and the factory can only survive<br />
for about 24 hours – tops – without<br />
electricity,” says Pardoe. “And that’s what<br />
we were given for the changeover.”<br />
As it happened, the installation crew<br />
only needed 21 hours. “Apart from the<br />
success of meeting the time-limit, it was<br />
particularly gratifying to witness the<br />
improved efficiency of the switchboards.<br />
Tests conducted after the installation<br />
showed the boards were running at a<br />
significantly lower load than the previous<br />
equipment. We believe a lot of the<br />
‘excess’ load on the old boards was<br />
attributable to heat losses and<br />
poor connections.”<br />
Control is also much easier. It’s entirely<br />
automatic, and operators now monitor<br />
the switchboards’ performance on a PC<br />
screen. Being able to monitor load in real<br />
time, Pardoe points out, “also allows<br />
operators to consider strategies such<br />
as peak load sharing for the first time –<br />
and improve the plant’s overall<br />
energy efficiency.”<br />
THE HARDWARE<br />
Schneider-Electric supplied the majority of the components used in the two<br />
switchboards. Below is a selection of the Merlin Gerin items:<br />
2 x 3200A 3P 85kA Masterpact NW ACB Mains Breakers<br />
2 x 3200A 3P ACB Masterpact NW Generator Feeders<br />
3 x 2000A ACB Masterpact NW Generator Breakers<br />
2 x 3200A ACB Masterpact NW Bus Ties<br />
24 x 800A MCCB Compact NS Sub Circuit Feeders<br />
24 x PM 500 Powerlogic power meters<br />
5 x PM 850 Powerlogic power meters<br />
For more information contact your<br />
local Sales Engineer