Investment Analysts / Fund Managers<br />

<strong>Visit</strong> to<br />

Potgietersrust <strong>Platinum</strong>s Limited<br />

24 August 2004<br />

Potgietersrust <strong>Platinum</strong>s Limited


Agenda<br />

• Location & Infrastructure Layout<br />

• Safety & Environment<br />

• Geology<br />

• Resources and Reserves<br />

• Mining and development<br />

• Production<br />

• Working Cost<br />

• Capex<br />

• HR<br />

Potgietersrust <strong>Platinum</strong>s Limited


Location & Infrastructure<br />

Layout<br />

Potgietersrust <strong>Platinum</strong>s Limited


Legend<br />

Bushveld Complex<br />

<strong>Anglo</strong> <strong>Platinum</strong><br />

<strong>Anglo</strong> <strong>Platinum</strong> - Joint Venture<br />

Impala <strong>Platinum</strong> Mines<br />

Lonmin PLC<br />

Northam <strong>Platinum</strong> Limited<br />

POTGIETERSRUST<br />

PLATINUMS LIMITED<br />

MOKOPANE (POTGIETERSRUS)<br />

POLOKWANE (PIETERSBURG)<br />

%U<br />

%U<br />

ð<br />

Polokwane Smelter<br />

LEBOWA PLATINUM MINES<br />

UNKI PROJECT<br />

Namibia<br />

Botswana<br />

Zimbabwe<br />

Republic<br />

of<br />

South Africa<br />

Mozambique<br />

Southern Era<br />

Merensky<br />

UG2<br />

Platreef<br />

AMANDELBULT<br />

NORTHAM<br />

LIMPOPO<br />

PASCHASKRAAL JV<br />

TWICKENHAM<br />

MODIKWA<br />

%U<br />

BURGERSFORT<br />

BELA BELA (WARMBATHS)<br />

%U<br />

UNION<br />

BAFOKENG/RASIMONE<br />

STYLDRIFT JV<br />

NORTH-WEST<br />

DER BROCHEN<br />

BOOYSENDAL JV<br />

LYDENBURG<br />

%U<br />

RUSTENBURG<br />

GAUTENG<br />

%U<br />

RUSTENBURG<br />

PANDORA JV<br />

%U<br />

PRETORIA<br />

MPUMALANGA<br />

WITBANK<br />

%U<br />

±<br />

%U<br />

JOHANNESBURG<br />

0 10 20<br />

Kilometres<br />

Potgietersrust <strong>Platinum</strong>s Limited


Tweefontein Hill<br />

Tweefontein North<br />

Sandsloot<br />

Zwartfontein South<br />

<strong>PPRust</strong> North


<strong>PPRust</strong> - Infrastructure<br />

Protection<br />

Services<br />

Mining<br />

Main Stores<br />

Main Offices<br />

Concentrator<br />

Crushed ore<br />

stockpile<br />

Explosive<br />

Magazine<br />

Main Water<br />

Reservoir<br />

Main Crusher


Sandsloot<br />

Concentrator<br />

Tweefontein Hill Pit<br />

Tweefontein North Pit<br />

Sandsloot Pit<br />

Zwartfontein South Pit<br />

<strong>PPRust</strong> North Pit<br />

Ore Flow Diagram


Safety & Environment<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s - Lost Time Injuries<br />

25<br />

20<br />

15<br />

10<br />

5<br />

21<br />

14<br />

9 8<br />

0<br />

2000 2001 2002 2003<br />

number of injuries<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s – fatal accident<br />

1<br />

0<br />

2000 2001 2002 2003<br />

number of fatals<br />

Potgietersrust <strong>Platinum</strong>s Limited


2004 Safety Challenges<br />

• Integration of Behavior Based Safety into line-<br />

function;<br />

• Continue with “Unembeza“<br />

and OTTO” campaign;<br />

• Adherence to <strong>Platinum</strong> Rules;<br />

• Electronic Business Management System;<br />

• Edutouch training;<br />

• OSHAS 18000 Accreditation;<br />

• Occupational Hygiene.<br />

Potgietersrust <strong>Platinum</strong>s Limited


Environmental Challenges for 2004<br />

• Employee training on environmental issues;<br />

• Maintain ISO 14001 certification;<br />

• Improve on waste management (general, oil<br />

spillages, contaminated soil);<br />

• First phase of waste rock dump<br />

rehabilitation;<br />

Potgietersrust <strong>Platinum</strong>s Limited


Geology<br />

Potgietersrust <strong>Platinum</strong>s Limited


Potgietersrust <strong>Platinum</strong>s Limited


OVERYSEL 815 LR<br />

ZWARTFONTEIN 818 LR<br />

Sandsloot Pit<br />

VAALKOP 819 LR<br />

SANDSLOOT 236 KR<br />

KNAPDAAR 234 KR<br />

TWEEFONTEIN 238 KR<br />

´<br />

RIETFONTEIN 240 KR<br />

0 2.5<br />

Kilometers<br />

Potgietersrust <strong>Platinum</strong>s Limited


Sandsloot<br />

Potgietersrust <strong>Platinum</strong>s Limited


Main Faults at Sandsloot CUT 6<br />

N<br />

Potgietersrust <strong>Platinum</strong>s Limited


Structure of Sandsloot Pit<br />

Potgietersrust <strong>Platinum</strong>s Limited


Example <strong>Section</strong> through SandSloot-pit<br />

Potgietersrust <strong>Platinum</strong>s Limited


Zwartfontein South<br />

Potgietersrust <strong>Platinum</strong>s Limited


Zwartfontein South - Fault Blocks at Final Design<br />

Potgietersrust <strong>Platinum</strong>s Limited


Exploration Drilling Grid for Zwartfontein South<br />

50m x 50m<br />

LOOKING SOUTH<br />

Potgietersrust <strong>Platinum</strong>s Limited<br />

LOOKING<br />

NORTH


Example section through<br />

Zwartfontein South pit<br />

•Gvp**grade<br />

mod.gvp<br />

Potgietersrust <strong>Platinum</strong>s Limited


Core Drilling Statistics: : 2003/4<br />

Area<br />

No. of<br />

holes<br />

drilled<br />

Meters<br />

drilled<br />

No. of<br />

assays<br />

Drill status<br />

Sandsloot<br />

18<br />

16,036<br />

5,926<br />

completed<br />

Zwartfontein<br />

South<br />

172<br />

78,697<br />

40,332<br />

Completed<br />

(Apr 04)<br />

<strong>PPRust</strong> North<br />

232<br />

77,861<br />

47,443<br />

completed<br />

Potgietersrust <strong>Platinum</strong>s Limited


Exploration status at <strong>PPRust</strong><br />

Potgietersrust <strong>Platinum</strong>s Limited


Resources and Reserves<br />

Potgietersrust <strong>Platinum</strong>s Limited


Resource / Reserve Statement<br />

Sandsloot (31/12/2003)<br />

Category<br />

Tonnes<br />

(X 1000)<br />

4E<br />

(g/t)<br />

Pt Oz<br />

(X 1000)<br />

Measured Resource<br />

11,900.0<br />

1.74<br />

234.3<br />

Indicated Resource<br />

27,600.0<br />

2.33<br />

727.8<br />

Inferred Resource<br />

64,210.0<br />

2.96<br />

2,150.9<br />

Total Resource<br />

103,710.0<br />

2.65<br />

3,113.0<br />

Proven Reserve<br />

3,950.0<br />

3.03<br />

135.5<br />

Probable Reserve<br />

9,610.0<br />

3.25<br />

353.6<br />

Total Reserve<br />

13,570.0<br />

3.19<br />

489.1<br />

Note: Reserve quoted in addition to Resource statement<br />

Potgietersrust <strong>Platinum</strong>s Limited


Resource / Reserve Statement<br />

Zwartfontein South (31/12/2003)<br />

Category<br />

Tonnes<br />

(X 1000)<br />

4E<br />

(g/t)<br />

Pt Oz<br />

(X 1000)<br />

Measured Resource<br />

-<br />

-<br />

0<br />

Indicated Resource<br />

-<br />

-<br />

0<br />

Inferred Resource<br />

89,360.0<br />

2.06<br />

2,083.3<br />

Total Resource<br />

89,360.0<br />

2.06<br />

2,083.3<br />

Proven Reserve<br />

-<br />

-<br />

0<br />

Probable Reserve<br />

33,290.0<br />

3.32<br />

1,250.7<br />

Total Reserve<br />

33,290.0<br />

3.32<br />

1,250.7<br />

Note: Reserve quoted in addition to Resource statement<br />

Potgietersrust <strong>Platinum</strong>s Limited


Resource / Reserve Statement<br />

Total <strong>PPRust</strong> (31/12/2003)<br />

Category<br />

Tonnes<br />

(X 1000)<br />

4E<br />

(g/t)<br />

Pt Oz<br />

(X 1000)<br />

Measured Resource<br />

11,900.0<br />

1.74<br />

234.3<br />

Indicated Resource<br />

338,890.0<br />

2.36<br />

9,063.2<br />

Inferred Resource<br />

153,570.0<br />

2.44<br />

4,234.2<br />

Total Resource<br />

504,360.0<br />

2.37<br />

12,531.8<br />

Proven Reserve<br />

3,950.0<br />

3.03<br />

135.5<br />

Probable Reserve<br />

311,270.0<br />

2.65<br />

9,349.1<br />

Total Reserve<br />

315,230.0<br />

2.66<br />

9,484.6<br />

Note: Reserve quoted in addition to Resource statement<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong> Prill Split<br />

Pt factor<br />

Pd factor<br />

Rh factor<br />

Au factor<br />

% Cu<br />

%Ni<br />

Sandsloot<br />

0.445<br />

0.459<br />

0.033<br />

0.064<br />

0.098<br />

0.193<br />

Zwartfontein<br />

South<br />

0.440<br />

0.469<br />

0.033<br />

0.059<br />

0.083<br />

0.171<br />

Potgietersrust <strong>Platinum</strong>s Limited


Mining & Development<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Sandsloot pit<br />

Potgietersrust <strong>Platinum</strong>s Limited<br />

•32 500 000 t in 2004<br />

•90 000 t per day<br />

•bench height 15 m<br />

•current depth 210,<br />

(320)m<br />

•current length 1700 m<br />

•current width 600 m<br />

•ramp gradient 10 %<br />

•ramp width 35 m<br />

•strip ratio 7.9 : 1


<strong>PPRust</strong>’s Zwartfontein South pit<br />

•25 000 000 t in 2004<br />

•68 500 t per day<br />

•bench height 10 m<br />

•current depth 60, (245)m<br />

•current length 650,<br />

(1630)m<br />

•current width 300, (690)m<br />

•ramp gradient 10 %<br />

•ramp width 35 m<br />

•strip ratio 11 : 1<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Truck and Shovel operation<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Truck and Shovel operation<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Drill & Blast operations<br />

Potgietersrust <strong>Platinum</strong>s Limited


MINE DESIGN – Sandsloot CUT 6<br />

Potgietersrust <strong>Platinum</strong>s Limited


MINE DESIGN – Zwartfontein South CUT 5<br />

Potgietersrust <strong>Platinum</strong>s Limited


Production<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s tons mined<br />

50<br />

40<br />

30<br />

20<br />

30.18 29.61<br />

39.67<br />

48.44<br />

10<br />

0<br />

2000 2001 2002 2003<br />

million tons mined (ex pits)<br />

• Steady state level around 50 million tons per annum<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s milling performance<br />

5,000<br />

4,000<br />

3,000<br />

2,000<br />

4,177 4,270 4,375 4,465<br />

1,000<br />

0<br />

2000 2001 2002 2003<br />

k tons milled<br />

• Milling capacity limit of 385 000 tons per month<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Concentrator Recoveries<br />

82<br />

80<br />

78<br />

76<br />

81.94 81.96<br />

74<br />

79.09<br />

72<br />

74.57<br />

70<br />

2000 2001 2002 2003<br />

PGM Recoveries<br />

• Recovery in 2004 steady around 80%<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Grade<br />

4.5<br />

4.0<br />

3.5<br />

3.0<br />

2.5<br />

2.0<br />

1.5<br />

1.0<br />

0.5<br />

0.0<br />

4.3 4.4<br />

4.0<br />

3.5<br />

2000 2001 2002 2003<br />

built-up head grade (g/t PGM)<br />

• Grade steady around 4 grams per ton<br />

Potgietersrust <strong>Platinum</strong>s Limited


<strong>PPRust</strong>’s Pt-Production<br />

Production<br />

250,000<br />

200,000<br />

150,000<br />

100,000<br />

202,600 211,400<br />

164,700<br />

191,800<br />

50,000<br />

0<br />

2000 2001 2002 2003<br />

equivalent refined Pt production<br />

Potgietersrust <strong>Platinum</strong>s Limited


Operating Costs<br />

Potgietersrust <strong>Platinum</strong>s Limited


Cash on-mine costs<br />

200.0<br />

183.0<br />

60,000.0<br />

180.0<br />

160.0<br />

140.0<br />

126.0<br />

139.0<br />

147.0<br />

50,000.0<br />

40,000.0<br />

R/ton milled<br />

120.0<br />

100.0<br />

80.0<br />

30,000.0<br />

Tons mined<br />

60.0<br />

20,000.0<br />

40.0<br />

10,000.0<br />

20.0<br />

0.0<br />

2000 2001 2002 2003<br />

0.0<br />

R/ton milled<br />

tons mined<br />

Potgietersrust <strong>Platinum</strong>s Limited


Cash on-mine costs<br />

4,500.0<br />

4,000.0<br />

3,500.0<br />

3,000.0<br />

2,500.0<br />

2,000.0<br />

1,500.0<br />

1,000.0<br />

500.0<br />

0.0<br />

3,903<br />

4,249<br />

2,605 2,815<br />

2000 2001 2002 2003<br />

R / Pt oz equiv. refined<br />

• Cost increase in 2004 expected at CPI target (5,5%)<br />

Potgietersrust <strong>Platinum</strong>s Limited


On Mine cost split<br />

15%<br />

17%<br />

6%<br />

Labour<br />

Stores<br />

Utilities<br />

Sundries<br />

14%<br />

6%<br />

42%<br />

Contractors<br />

Amort<br />

Potgietersrust <strong>Platinum</strong>s Limited


Tons mined / Pt oz<br />

60,000.0<br />

250,000<br />

50,000.0<br />

48,444.0<br />

200,000<br />

tons mined ('000)<br />

40,000.0<br />

30,000.0<br />

20,000.0<br />

30,183.0 29,631.0<br />

39,672.0<br />

150,000<br />

100,000<br />

Pt oz refined<br />

10,000.0<br />

50,000<br />

0.0<br />

2000 2001 2002 2003<br />

0<br />

tons mined<br />

Pt ounces<br />

Potgietersrust <strong>Platinum</strong>s Limited


Capital Expenditure<br />

350.0<br />

300.0<br />

250.0<br />

200.0<br />

150.0<br />

100.0<br />

50.0<br />

109.4<br />

161.9<br />

231.9<br />

338.6<br />

0.0<br />

2000 2001 2002 2003<br />

Capex (R mill)<br />

• Ongoing capex level of R250 - R300 m per annum<br />

• Planned spend of R400m (unapproved) in 2005 on relocation and water w<br />

Potgietersrust <strong>Platinum</strong>s Limited


Human Resources<br />

Potgietersrust <strong>Platinum</strong>s Limited


Human Resources<br />

• Attraction and Retention<br />

– Desirability of Area<br />

– Schooling<br />

• Employment Equity<br />

• HIV/AIDS<br />

• SED<br />

– Lower Prevalence rate<br />

– Mining Charter<br />

– BEE<br />

– Village Relocation<br />

Potgietersrust <strong>Platinum</strong>s Limited


Key Business Issues<br />

• Safety, Health and Environment<br />

• Cost Optimisation<br />

• Improving Unit Costs<br />

• Improving Concentrator Performance<br />

• Mining Flexibility<br />

Contribution to the Group<br />

Potgietersrust <strong>Platinum</strong>s Limited


Dr. Hans Merensky (1927):<br />

… it is evident that the Potgietersrus <strong>Platinum</strong>s Limited are indeed in an excellent<br />

position, in that a large tonnage can be developed in a short time and without much<br />

capital expenditure; and that the mining can be done for a long time cheaply in open<br />

quarries; the milling and producing stages can be reached in a short time, and …<br />

I feel convinced that the Potgietersrus <strong>Platinum</strong>s Limited will<br />

develop into a highly payable concern.