Certification Testing of Two Small Wind Turbines
Certification Testing of Two Small Wind Turbines
Certification Testing of Two Small Wind Turbines
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Energy Produced, kWh<br />
S-343 <strong>Testing</strong> Timeline<br />
30,000<br />
25,000<br />
Site Calibration<br />
2/2/11 - 2/20/11<br />
20,000<br />
Duration Test<br />
Power Performance Test<br />
10/19/11 - 10/27/11<br />
7/25/11 - 9/14/12<br />
15,000<br />
Safety & Function Test<br />
7/25/11 - 10/16/12<br />
10,000<br />
Acoustic Test<br />
9/30/12 - 3/13/13<br />
5,000<br />
Installation &<br />
Commissioning<br />
2/24/11<br />
<strong>Testing</strong> Begins<br />
7/11/11<br />
<strong>Testing</strong> Completed<br />
3/13/13<br />
0<br />
2011 Feb May Aug Nov<br />
Feb<br />
2012<br />
May Aug Nov<br />
Feb<br />
2013<br />
2013