<strong>Our</strong> Changing Hospitals<br />
Phase 4 - Ward 11a & Mortuary<br />
Projects<br />
Full Business Cases<br />
Presentation to FPC<br />
15th December 2010
Ward 11a Reconfiguration Project<br />
Dr Pin Patel<br />
Project Director<br />
Jan-Peter Ling<br />
OCH Project Manager<br />
Tim Pearce<br />
Financial Consultant
Phase 4 Ward 11a reconfiguration<br />
• Rationale: need for <strong>ward</strong> 11a<br />
reconfiguration.<br />
• Maintains phase 4 programme for<br />
consolidation in 2014.<br />
• Allows consolidation of Maternity services<br />
November 2011 – (Gynae)<br />
• Provides decant <strong>ward</strong> for future tower block<br />
reconfiguration projects.<br />
• Increase bed capacity to meet final<br />
consolidation requirements of phase 4.
Phase 4 – <strong>ward</strong> 11a layout drawing
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Benefits Realisation<br />
• Interim space for consolidation of Gynae<br />
services in line with Maternity<br />
consolidation Nov 2011<br />
• Decant facility for refurbishment of other<br />
areas<br />
• Increase in single side rooms <strong>and</strong> ensuites<br />
• Improved segregation of sexes (privacy &<br />
dignity)<br />
• Improved DDA access
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Risk to Trust if we do not proceed<br />
• No decant space for tower block reconfiguration<br />
<strong>ward</strong>s 10a, 7a <strong>and</strong> ICU Phase 4<br />
• Delay to consolidation of maternity services<br />
(Phase 2) Nov 2011<br />
• No improvement in bed capacity to achieve<br />
consolidation<br />
• No long term solution for future Tower Block<br />
developments
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Project Costs<br />
• Total Cost (inc. VAT) £2,224m<br />
• Contingency & Optimism Bias (inc VAT)<br />
£238k = 13.2% of works Also includes<br />
£262k enablers<br />
• Net Present Cost of scheme = £2.277m<br />
(over 30 years)
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Option Appraisal<br />
• the following options were considered<br />
• Do nothing – would not provide bed capacity or allow consolidation<br />
of maternity services (phase 2) onto Lister site<br />
• New build – cost was outside of affordability envelope, no area has<br />
been identified on the Lister site<br />
• Refurbishment – considered to be the appropriate option as will<br />
provide both future bed capacity <strong>and</strong> allow full consolidation of<br />
phase 4 programme
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Affordability<br />
Ward 11a is an enabler <strong>and</strong> as such no<br />
savings have been assigned to the<br />
scheme.<br />
Capital charges <strong>and</strong> interest are estimated<br />
to be £176,000k in first year
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Funding of scheme<br />
• To be resourced by Interest bearing debt<br />
with March Draw Down
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Project Management<br />
• Project lead by service end users<br />
(clinicians & support services)<br />
• The 1:50 design signed off by users<br />
• Equipment requirements signed off by<br />
users<br />
• OCH PM responsible for delivering project<br />
on time & budget
Phase 4 – <strong>ward</strong> 11a reconfiguration<br />
Programme<br />
• Consideration by Trust Board – 22 nd December 2010<br />
• Loan agreed by DH – March 2011<br />
• Sign contract with PSCP – March 2011<br />
• Enabling works commence – 13 th December 2010<br />
• Enabling works completed – 3 rd February 2011<br />
• PSCP Commence asbestos removal – 4 th February 2011 (Stage 3<br />
works)<br />
• PSCP commence main construction works – 24 th March 2011 (27<br />
weeks)<br />
• Ward fully operational – 22 nd August 2011<br />
• Post Project Evaluation – November 2011
Phase 4 - Mortuary Project<br />
Dr Samita Agarwal<br />
Lead Consultant Histopathologist<br />
Eilish Midlane<br />
Diagnostic Services Manager<br />
M<strong>and</strong>y Shoben<br />
Assistant Project Manager
Phase 4 - Mortuary Project<br />
Rationale<br />
• Exp<strong>and</strong> Lister <strong>mortuary</strong> to support acute<br />
consolidation<br />
• Increase body spaces <strong>and</strong> provides bariatric<br />
facilities<br />
• New tables reduce health <strong>and</strong> safety issues<br />
• Compliance with HTA <strong>and</strong> CPA requirements<br />
• Continue to support coroner contract<br />
• Reduced revenue spend on agency staff
Phase 4 - Mortuary Project<br />
Description<br />
• Provide 24 new body storage spaces inc 4<br />
bariatric<br />
• Relocate <strong>and</strong> enlarge viewing room within<br />
department<br />
• Partitioning off the waiting area for<br />
increase privacy<br />
• Installation of two new (existing) PM tables
Phase 4 - Mortuary Project<br />
• Project Stages<br />
• Stage 1 – Changes to Lister <strong>mortuary</strong> to<br />
allow PM’s to be centralised<br />
• Stage 2 – Migration of services to Lister<br />
• Stage 3 – Full <strong>mortuary</strong> consolidation
Phase 4 - Mortuary Project<br />
Changes from Pathology OBC<br />
• Fridge configuration increasing fridges by<br />
1 (to 24)<br />
• Reconfiguration of ventilation to to meet<br />
HTM <strong>and</strong> HBN<br />
• Partitioning waiting area<br />
• Extent of building works reduced <strong>and</strong><br />
equipment costs increase
Phase 4 - Mortuary Project<br />
Capital costs summary<br />
<strong>FBC</strong> OBC<br />
£'000 £'000<br />
Works cost 34 246<br />
Fees 6 30<br />
Equipment 37 12<br />
Contingency 14 53<br />
Optimism bias 13 50<br />
VAT 18 69<br />
Total cost at current MIPS 122 460<br />
Inflation -3 -15<br />
Total cost @ outturn 119 445<br />
Contingency <strong>and</strong> Optimism Bias @ £27K = 35% of works costs inc<br />
equipment & fees
Phase 4 - Mortuary Project<br />
Benefits of early delivery<br />
• Revenue benefits delivered on final<br />
consolidation<br />
• Reduction current dept revenue<br />
overspends<br />
• Tests activity modelling on body storage<br />
• Installation of new adjustable tables<br />
reducing health <strong>and</strong> safety issues
Phase 4 - Mortuary Project<br />
Programme<br />
• Relies on Interest Bearing Debt <strong>and</strong> March<br />
draw down<br />
• Commence works in April 2011<br />
• Works complete June 2011<br />
• Final consolidation 2013
Phase 4 - Mortuary Project<br />
Project Management<br />
• Project lead by clinicians <strong>and</strong> <strong>mortuary</strong><br />
team<br />
• The 1:50 design signed off by users<br />
• Equipment requirements signed off by<br />
users<br />
• OCH team responsible for delivering<br />
project on time & budget