<strong>Our</strong> Changing Hospitals<br />

Phase 4 - Ward 11a & Mortuary<br />

Projects<br />

Full Business Cases<br />

Presentation to FPC<br />

15th December 2010


Ward 11a Reconfiguration Project<br />

Dr Pin Patel<br />

Project Director<br />

Jan-Peter Ling<br />

OCH Project Manager<br />

Tim Pearce<br />

Financial Consultant


Phase 4 Ward 11a reconfiguration<br />

• Rationale: need for <strong>ward</strong> 11a<br />

reconfiguration.<br />

• Maintains phase 4 programme for<br />

consolidation in 2014.<br />

• Allows consolidation of Maternity services<br />

November 2011 – (Gynae)<br />

• Provides decant <strong>ward</strong> for future tower block<br />

reconfiguration projects.<br />

• Increase bed capacity to meet final<br />

consolidation requirements of phase 4.


Phase 4 – <strong>ward</strong> 11a layout drawing


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Benefits Realisation<br />

• Interim space for consolidation of Gynae<br />

services in line with Maternity<br />

consolidation Nov 2011<br />

• Decant facility for refurbishment of other<br />

areas<br />

• Increase in single side rooms <strong>and</strong> ensuites<br />

• Improved segregation of sexes (privacy &<br />

dignity)<br />

• Improved DDA access


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Risk to Trust if we do not proceed<br />

• No decant space for tower block reconfiguration<br />

<strong>ward</strong>s 10a, 7a <strong>and</strong> ICU Phase 4<br />

• Delay to consolidation of maternity services<br />

(Phase 2) Nov 2011<br />

• No improvement in bed capacity to achieve<br />

consolidation<br />

• No long term solution for future Tower Block<br />

developments


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Project Costs<br />

• Total Cost (inc. VAT) £2,224m<br />

• Contingency & Optimism Bias (inc VAT)<br />

£238k = 13.2% of works Also includes<br />

£262k enablers<br />

• Net Present Cost of scheme = £2.277m<br />

(over 30 years)


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Option Appraisal<br />

• the following options were considered<br />

• Do nothing – would not provide bed capacity or allow consolidation<br />

of maternity services (phase 2) onto Lister site<br />

• New build – cost was outside of affordability envelope, no area has<br />

been identified on the Lister site<br />

• Refurbishment – considered to be the appropriate option as will<br />

provide both future bed capacity <strong>and</strong> allow full consolidation of<br />

phase 4 programme


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Affordability<br />

Ward 11a is an enabler <strong>and</strong> as such no<br />

savings have been assigned to the<br />

scheme.<br />

Capital charges <strong>and</strong> interest are estimated<br />

to be £176,000k in first year


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Funding of scheme<br />

• To be resourced by Interest bearing debt<br />

with March Draw Down


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Project Management<br />

• Project lead by service end users<br />

(clinicians & support services)<br />

• The 1:50 design signed off by users<br />

• Equipment requirements signed off by<br />

users<br />

• OCH PM responsible for delivering project<br />

on time & budget


Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Programme<br />

• Consideration by Trust Board – 22 nd December 2010<br />

• Loan agreed by DH – March 2011<br />

• Sign contract with PSCP – March 2011<br />

• Enabling works commence – 13 th December 2010<br />

• Enabling works completed – 3 rd February 2011<br />

• PSCP Commence asbestos removal – 4 th February 2011 (Stage 3<br />

works)<br />

• PSCP commence main construction works – 24 th March 2011 (27<br />

weeks)<br />

• Ward fully operational – 22 nd August 2011<br />

• Post Project Evaluation – November 2011


Phase 4 - Mortuary Project<br />

Dr Samita Agarwal<br />

Lead Consultant Histopathologist<br />

Eilish Midlane<br />

Diagnostic Services Manager<br />

M<strong>and</strong>y Shoben<br />

Assistant Project Manager


Phase 4 - Mortuary Project<br />

Rationale<br />

• Exp<strong>and</strong> Lister <strong>mortuary</strong> to support acute<br />

consolidation<br />

• Increase body spaces <strong>and</strong> provides bariatric<br />

facilities<br />

• New tables reduce health <strong>and</strong> safety issues<br />

• Compliance with HTA <strong>and</strong> CPA requirements<br />

• Continue to support coroner contract<br />

• Reduced revenue spend on agency staff


Phase 4 - Mortuary Project<br />

Description<br />

• Provide 24 new body storage spaces inc 4<br />

bariatric<br />

• Relocate <strong>and</strong> enlarge viewing room within<br />

department<br />

• Partitioning off the waiting area for<br />

increase privacy<br />

• Installation of two new (existing) PM tables


Phase 4 - Mortuary Project<br />

• Project Stages<br />

• Stage 1 – Changes to Lister <strong>mortuary</strong> to<br />

allow PM’s to be centralised<br />

• Stage 2 – Migration of services to Lister<br />

• Stage 3 – Full <strong>mortuary</strong> consolidation


Phase 4 - Mortuary Project<br />

Changes from Pathology OBC<br />

• Fridge configuration increasing fridges by<br />

1 (to 24)<br />

• Reconfiguration of ventilation to to meet<br />

HTM <strong>and</strong> HBN<br />

• Partitioning waiting area<br />

• Extent of building works reduced <strong>and</strong><br />

equipment costs increase


Phase 4 - Mortuary Project<br />

Capital costs summary<br />

<strong>FBC</strong> OBC<br />

£'000 £'000<br />

Works cost 34 246<br />

Fees 6 30<br />

Equipment 37 12<br />

Contingency 14 53<br />

Optimism bias 13 50<br />

VAT 18 69<br />

Total cost at current MIPS 122 460<br />

Inflation -3 -15<br />

Total cost @ outturn 119 445<br />

Contingency <strong>and</strong> Optimism Bias @ £27K = 35% of works costs inc<br />

equipment & fees


Phase 4 - Mortuary Project<br />

Benefits of early delivery<br />

• Revenue benefits delivered on final<br />

consolidation<br />

• Reduction current dept revenue<br />

overspends<br />

• Tests activity modelling on body storage<br />

• Installation of new adjustable tables<br />

reducing health <strong>and</strong> safety issues


Phase 4 - Mortuary Project<br />

Programme<br />

• Relies on Interest Bearing Debt <strong>and</strong> March<br />

draw down<br />

• Commence works in April 2011<br />

• Works complete June 2011<br />

• Final consolidation 2013


Phase 4 - Mortuary Project<br />

Project Management<br />

• Project lead by clinicians <strong>and</strong> <strong>mortuary</strong><br />

team<br />

• The 1:50 design signed off by users<br />

• Equipment requirements signed off by<br />

users<br />

• OCH team responsible for delivering<br />

project on time & budget