Phase 4 – <strong>ward</strong> 11a reconfiguration<br />

Programme<br />

• Consideration by Trust Board – 22 nd December 2010<br />

• Loan agreed by DH – March 2011<br />

• Sign contract with PSCP – March 2011<br />

• Enabling works commence – 13 th December 2010<br />

• Enabling works completed – 3 rd February 2011<br />

• PSCP Commence asbestos removal – 4 th February 2011 (Stage 3<br />

works)<br />

• PSCP commence main construction works – 24 th March 2011 (27<br />

weeks)<br />

• Ward fully operational – 22 nd August 2011<br />

• Post Project Evaluation – November 2011