02.05.2015 Views

pre planning submission op05 derryduff ... - Organic Power

pre planning submission op05 derryduff ... - Organic Power

pre planning submission op05 derryduff ... - Organic Power

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Intake structures<br />

A sluiced water intake/fill structure will be constructed at each reservoirs from re-inforced concrete to allow<br />

water to be drained pumped between reservoirs. The intake structure for the bottom reservoir will be located at<br />

least 15m below the lowest point of the lower reservoir to provide sufficient back <strong>pre</strong>ssure on the pump-turbine<br />

to eliminate cavitation. The intake structure of the upper reservoir will be located at the level of the base of the<br />

upper reservoir. Appropriate sluice controls and trashracks will be included<br />

Penstock<br />

A penstock pipe will transport the water at a rate of 25m 3 /s between reservoirs. This pipe will be situated partly<br />

over-ground and partly underground, making maximum use of the topographical features of the site. The pipe<br />

will be composed of <strong>pre</strong>-manufactured section of 18m long which are bolted together in series of 3 sections.<br />

Each series is linked to the next by a massed concrete foundation haunch. Haunches will be soaced 54m apart.<br />

Turbine<br />

• Pump-turbine (Voith Siemens)<br />

• 1 no.<br />

• Rated output: 45 MW<br />

• Turbine rated net head: 210m<br />

• Required flow rate 25 m³/s<br />

• Max. pump Head: 231m<br />

• The power plant will run fully automatically.<br />

Fig. 2 Pump Turbine Schematic Drawing (Indicative Only)<br />

2.3.8 Construction Traffic<br />

Project generated traffic will include deliveries of plant and machinery and of oversized loads. The oversized<br />

loads will not require public road alterations. The transportation of these loads will require special permit and<br />

the consent of ‘An Garda Siochana’. Once these have been obtained the components will be transported from<br />

Ringaskiddy port to site. There will also be daily commutes of plant operators, office staff, electricians, engineers<br />

and trades people. Assuming 30 no. workers, all travelling in their own vehicles, there will be an increase of 30<br />

vehicles commuting daily.<br />

14<br />

Fig. 1 <strong>Power</strong>house - “White Tank” (Indicative Only)<br />

<strong>Power</strong>house<br />

A pit containing a wet cylindrical well approximately 37.5m deep will house the pumpturbine on the northern<br />

side of the lower reservoir. The building pit will be enclosed by a bored piled curtain wall (~1m thick) forming a a<br />

waterproof “white tank”. This structure will be underground, and covered by a low building (See Fig. 6).<br />

Turbine Hall<br />

The structural skeleton of the building will be erected, roofed, and clad once placing of the turbine plant<br />

elements by gantry crane is complete.<br />

2.3.5 External Service Pipes And Ducts<br />

All telecommunicatons and electrical cables for the proposed development will be buried underground under<br />

the access roads on site with a minimum of 1 meter cover from ground level, labeled with suitable yellow<br />

warning tape at 0.5m from ground surface and 0.8m from ground surface at the top of the surround gravel<br />

to warn off future excavations. Electrical cables will be run to a substation adjacent to the turbine hall. A<br />

110kV underground cable will follow the route of the access road to the public road at the Unicorn foundation<br />

entrance, and then follow under the public road over the Derryduff bridge to Rangaroe, Coomhola, Dromduff<br />

west to Ballylickey Bridge and the connection at the ESB 110kV substation.<br />

2.3.6 Site Works Surfacing<br />

The access roads will be paved with tarmac or finished with crushed stone, and have kerb and gullies to collect<br />

storm water runoff to sedimentation basins.<br />

2.3.7 Plant Operational Technology Installation And Mechanical And Electrical Fit-Out<br />

Design parameters:<br />

• Location to minimize bends in the penstock pipes<br />

• Location of turbine below lake bottom<br />

• Deeper Pool at <strong>Power</strong> House containing outflow/intake structures<br />

2.3.9 Construction Health and Safety<br />

Relevant legislation includes, ‘The Safety, Health and Welfare at Work Act 1993-2003, Irish Construction<br />

regulations 2001, and all of the other up to date Safety, Health and Welfare best practice Guidance Documents.<br />

A number of these relevant documents include PPE, Manual Handling, Working with ladders, working at night,<br />

quarrying and surface mining operations, quarry vehicles, working on in or near excavations, signage, slips<br />

trips and falls at work, working at heights. This is not an exhaustive list however these are all relevant to a large<br />

project such as a PHES development. Hazards identified associated with this project include, oversized loads,<br />

lifting materials, pipe sections and turbine components to heights, working at heights, underground power<br />

lines, electricity at commissioning, excavations, slips, trips and falls, moving vehicles and plant, etc. A 2.4m high<br />

perimeter chain link fence will be carried out around the reservoir perimeters.<br />

2.3.10 Land Use Requirements During Construction Phase<br />

The approximate total land take required for the proposed project is given below. This area re<strong>pre</strong>sents less than<br />

12% of the existing upland site, which is defined as lands within the site boundaries of the property involved in<br />

the project, which are not forested or improved for grazing (116ha).<br />

Item Area [m2]<br />

Access Road to Site 10000<br />

Area of Surfaced Roads 33670.3<br />

Buildings 3840<br />

Upper Reservoir 30072.5<br />

Lower Reservoir 41288.5<br />

Penstock 4629.4<br />

Stillin Basins 2699.4<br />

Peat stock pile 1 8720.8<br />

Peat stock pile 2 2690.9<br />

Total land use requirement 133771.8

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!