pre planning submission op05 derryduff ... - Organic Power
pre planning submission op05 derryduff ... - Organic Power
pre planning submission op05 derryduff ... - Organic Power
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Intake structures<br />
A sluiced water intake/fill structure will be constructed at each reservoirs from re-inforced concrete to allow<br />
water to be drained pumped between reservoirs. The intake structure for the bottom reservoir will be located at<br />
least 15m below the lowest point of the lower reservoir to provide sufficient back <strong>pre</strong>ssure on the pump-turbine<br />
to eliminate cavitation. The intake structure of the upper reservoir will be located at the level of the base of the<br />
upper reservoir. Appropriate sluice controls and trashracks will be included<br />
Penstock<br />
A penstock pipe will transport the water at a rate of 25m 3 /s between reservoirs. This pipe will be situated partly<br />
over-ground and partly underground, making maximum use of the topographical features of the site. The pipe<br />
will be composed of <strong>pre</strong>-manufactured section of 18m long which are bolted together in series of 3 sections.<br />
Each series is linked to the next by a massed concrete foundation haunch. Haunches will be soaced 54m apart.<br />
Turbine<br />
• Pump-turbine (Voith Siemens)<br />
• 1 no.<br />
• Rated output: 45 MW<br />
• Turbine rated net head: 210m<br />
• Required flow rate 25 m³/s<br />
• Max. pump Head: 231m<br />
• The power plant will run fully automatically.<br />
Fig. 2 Pump Turbine Schematic Drawing (Indicative Only)<br />
2.3.8 Construction Traffic<br />
Project generated traffic will include deliveries of plant and machinery and of oversized loads. The oversized<br />
loads will not require public road alterations. The transportation of these loads will require special permit and<br />
the consent of ‘An Garda Siochana’. Once these have been obtained the components will be transported from<br />
Ringaskiddy port to site. There will also be daily commutes of plant operators, office staff, electricians, engineers<br />
and trades people. Assuming 30 no. workers, all travelling in their own vehicles, there will be an increase of 30<br />
vehicles commuting daily.<br />
14<br />
Fig. 1 <strong>Power</strong>house - “White Tank” (Indicative Only)<br />
<strong>Power</strong>house<br />
A pit containing a wet cylindrical well approximately 37.5m deep will house the pumpturbine on the northern<br />
side of the lower reservoir. The building pit will be enclosed by a bored piled curtain wall (~1m thick) forming a a<br />
waterproof “white tank”. This structure will be underground, and covered by a low building (See Fig. 6).<br />
Turbine Hall<br />
The structural skeleton of the building will be erected, roofed, and clad once placing of the turbine plant<br />
elements by gantry crane is complete.<br />
2.3.5 External Service Pipes And Ducts<br />
All telecommunicatons and electrical cables for the proposed development will be buried underground under<br />
the access roads on site with a minimum of 1 meter cover from ground level, labeled with suitable yellow<br />
warning tape at 0.5m from ground surface and 0.8m from ground surface at the top of the surround gravel<br />
to warn off future excavations. Electrical cables will be run to a substation adjacent to the turbine hall. A<br />
110kV underground cable will follow the route of the access road to the public road at the Unicorn foundation<br />
entrance, and then follow under the public road over the Derryduff bridge to Rangaroe, Coomhola, Dromduff<br />
west to Ballylickey Bridge and the connection at the ESB 110kV substation.<br />
2.3.6 Site Works Surfacing<br />
The access roads will be paved with tarmac or finished with crushed stone, and have kerb and gullies to collect<br />
storm water runoff to sedimentation basins.<br />
2.3.7 Plant Operational Technology Installation And Mechanical And Electrical Fit-Out<br />
Design parameters:<br />
• Location to minimize bends in the penstock pipes<br />
• Location of turbine below lake bottom<br />
• Deeper Pool at <strong>Power</strong> House containing outflow/intake structures<br />
2.3.9 Construction Health and Safety<br />
Relevant legislation includes, ‘The Safety, Health and Welfare at Work Act 1993-2003, Irish Construction<br />
regulations 2001, and all of the other up to date Safety, Health and Welfare best practice Guidance Documents.<br />
A number of these relevant documents include PPE, Manual Handling, Working with ladders, working at night,<br />
quarrying and surface mining operations, quarry vehicles, working on in or near excavations, signage, slips<br />
trips and falls at work, working at heights. This is not an exhaustive list however these are all relevant to a large<br />
project such as a PHES development. Hazards identified associated with this project include, oversized loads,<br />
lifting materials, pipe sections and turbine components to heights, working at heights, underground power<br />
lines, electricity at commissioning, excavations, slips, trips and falls, moving vehicles and plant, etc. A 2.4m high<br />
perimeter chain link fence will be carried out around the reservoir perimeters.<br />
2.3.10 Land Use Requirements During Construction Phase<br />
The approximate total land take required for the proposed project is given below. This area re<strong>pre</strong>sents less than<br />
12% of the existing upland site, which is defined as lands within the site boundaries of the property involved in<br />
the project, which are not forested or improved for grazing (116ha).<br />
Item Area [m2]<br />
Access Road to Site 10000<br />
Area of Surfaced Roads 33670.3<br />
Buildings 3840<br />
Upper Reservoir 30072.5<br />
Lower Reservoir 41288.5<br />
Penstock 4629.4<br />
Stillin Basins 2699.4<br />
Peat stock pile 1 8720.8<br />
Peat stock pile 2 2690.9<br />
Total land use requirement 133771.8