9.3 Length<br />

It is anticipated that the Main Body of the EIS will run to approximately 50 pages of A3 text not including<br />

graphics, and that the appendices will run to several hundred A3 pages.<br />

10 Membership and management of the EIA team<br />

Erm21c Ltd Project Management, EIA management, and EIS production<br />

Project Manager: Axel Fabritius<br />

Energy Engineering James J. Nolan, Sean Wyse<br />

Civil Engineering Brian Walsh, Niall Fitzsimons & Co.<br />

Soils and Geology Robert Meehan<br />

Hydrology Robert Meehan<br />

Archaeologist Maurice Hurley<br />

Noise & Vibration Dixon Brosnan<br />

Ecology Dixon Brosnan<br />

11 Work plan and resourcing for the environmental studies<br />

• Baseline studies commenced June 2008<br />

• Project defined June 2008<br />

• Pre-<strong>planning</strong> consultations to be completed 30th September 2008<br />

• EIS to be completed 30th September 2008<br />

• Anticipated Planning Application 1st week October 2008<br />