1.2 Operating Performance :<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
<br />
Jaduguda Mine<br />
This is the first and the oldest uranium mine of the country. With the depletion of ore reserves<br />
in the upper levels, production is now being carried out from the deeper levels. However,<br />
the performance of the mine has improved during the year registering 58.06% capacity<br />
utilization as against 52.73% during previous year.<br />
Bhatin Mine<br />
It is small mine with limited production capacity. Due to depletion of the ore reserves in the<br />
upper levels the capacity utilization of the mine during the year was 57.45%, a marginal fall<br />
compared to 59.74% during previous year.<br />
Narwapahar Mine<br />
This mine has the distinction of being the most modern and highly mechanized mine in the<br />
country using diesel-powered trackless mining equipment. During the year, the performance<br />
of the mine improved substantially registering 122.70% capacity utilization compared to<br />
110.65% in the previous year.<br />
Turamdih Mine:<br />
This is the second mine of its kind after Narwapahar using state-of-the-art mining technology.<br />
In order to augment the production capacity of your company, this mine was reopened in<br />
November 2002 and commissioned in September 2003. During the year, capacity utilization<br />
of the mine was 83.12% as against 85.28% in the previous year.<br />
Jaduguda Mill<br />
During the year, the performance of Jaduguda Mill improved considerably, achieving 115.88%<br />
capacity utilization compared to 110.39% in the previous year.<br />
Banduhurang Opencast Mine:<br />
This is the first opencast mine of your company located west of Turamdih mine in Singhbhum<br />
(East) district of Jharkhand. All parameters of this mine have been optimised using advanced<br />
software. This mine has been commissioned on 25.06.2007. Further expansion of its production<br />
capacity has now been taken up.<br />
Turamdih Mill<br />
Your company has constructed the second Uranium Ore Processing Plant at Turamdih for<br />
processing the ore of Turamdih, Banduhurang and proposed Mohuldih mines. This plant<br />
was commissioned for trial run on 25.06.2007. The plant is expected to be ready for operation<br />
shortly.<br />
By-product Recovery Plant<br />
The only By-product Recovery Plant producing magnetite has registered capacity utilization<br />
of 71.33% compared to 84.64% during last year.<br />
1.3 New Projects and Expansion Schemes :<br />
<br />
Bagjata Underground Mine:<br />
This mine, located about 30 km east of Jaduguda is under construction since April ’05. Bagjata<br />
mine has been planned to adopt layout similar to that of Narwapahar and Turamdih.<br />
Construction of this mine is progressing as per schedule. The estimated cost of the project is<br />
Rs.97.05 crore.<br />
9