Request for Qualifications<br />
General <strong>Engineering</strong> Services – RFQ #12-005<br />
City of Key West<br />
CEI Fee: $6,500,000<br />
Estimated Construction Cost: $70,000,000<br />
Project Status: Begin and End dates: March 2007 – June 2012<br />
Key Personnel: Antonio Diaz, PE<br />
Project Name:<br />
SR-5/US-1/<br />
Location:<br />
Boca Chica, Florida<br />
Description:<br />
The scope of this project consisted of RRR improvements for the southernmost 0.7 miles of<br />
SR-5 prior to entering the island of Key West. The project included cross slope corrections,<br />
shoulder improvements, new shoulder construction, drainage improvements, new signing and<br />
pavement markings and new signalization upgrades.<br />
Client:<br />
FDOT District 6<br />
Owner’s Representative:<br />
Jose Barrera, PE<br />
(305) 470-5260<br />
Project Status: Begin and End dates: September 2007 – December 2008<br />
Key Personnel: Charles Alfaro, PE<br />
Project Name:<br />
SR-5/US-1<br />
Location:<br />
Key West, Florida<br />
Description:<br />
The scope of this project consisted of 0.52 miles of RRR improvements for all the ramps<br />
connecting the Naval Base to SR-5/US-1. The project included cross slope corrections,<br />
shoulder improvements, guardrail upgrades and new signing and pavement markings. Mr.<br />
Panellas was the Project Manager and the Engineer of Record for the roadway and signing<br />
and pavement markings for this project<br />
Client:<br />
FDOT District 6<br />
Owner’s Representative:<br />
Jose Barrera, PE<br />
(305) 470-5260<br />
Project Status: Begin and End dates: April 2006 – May 2008<br />
Key Personnel: Charles Alfaro, PE<br />
3-4