Side Assembly<br />
SECTION-1<br />
Tools Required: -7/16” Box Wrench.<br />
Side parts Pack<br />
(1) Side Cill (Item # 1).<br />
(1) Gutter (Item # 2).<br />
(2) Side Brace (Item # 4). NOTE:- The Side Brace is distinguishable from the<br />
end brace by its length . The side brace is the longer of the two.<br />
Glazing bars (For required number see chart ).<br />
ASSEMBLY<br />
STEP-1 Lay out parts see (PIC-1) Gutter to the top cill at the bottom.<br />
STEP-2 Install “T” bolts in to gutter as (PIC-3) leve lose as shown.<br />
STEP-2 Assemble Glazing bars to the gutter section using bolts from (STEP-2).<br />
STEP-3 place “T” bolts into open end of glazing bar aprox ½” in from end<br />
(see PIC-4) and mount to cill using second hole in from the end, because<br />
this is the outside glazing bar place one end of the side brace onto the<br />
“T” bolt before installing the nut. Install all remaining G/bars repeat the<br />
procedure for the last G/bar using the remaining side brace, remember the<br />
inside face must face out.<br />
NOTE:- The inside face of the brace should face towards the end of the<br />
side wall.<br />
STEP-4 Secure the remaining (2) lose ends of the brace to the end slots in the gutter<br />
section using a ”T” bolt, this is to temporarily support the brace to stop<br />
damage until installing in (SECTION-4 Main assembly)<br />
NOTE:- DO NOT TIGHTEN BOLTS AT THIS TIME “ SNUG UP ONLY”.<br />
REPEAT ABOVE FOR THE SECOND SIDE.