DateMilestoneCapital CostUS$Net Cash CostUS$/lbJun 08 Pre Feasibility Study (PFS) $185m $1.43/lbAug 08Bankable Feasibility Studycommenced (<strong>BFS</strong>)Jan 09 Economic <strong>Update</strong> (XPFS) $131m $1.06/lbSep 09 <strong>BFS</strong> Progress <strong>Update</strong> $150m $1.04/lbOct 09 toFeb 10Mar 10Late 11<strong>BFS</strong> Resource updates<strong>BFS</strong> completeConcentrate productionSeptember 200910