CHAPTER 8 PROJECT TIME-COST TRADE-OFF
CHAPTER 8 PROJECT TIME-COST TRADE-OFF
CHAPTER 8 PROJECT TIME-COST TRADE-OFF
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
CostCrash duration&Crash costNormal duration&Normal costTimeFigure 8.2: Illustration of non-linear time/cost trade-off for an activityCostCrash duration&Crash costNormal duration&Normal costTimeFigure 8.3: Illustration of discrete time/cost trade-off for an activityExample 8.1A subcontractor has the task of erecting 8400 square meter of metal scaffolds. Thecontractor can use several crews with various costs. It is expected that the production willvary with the crew size as given below:Construction Management 167 Dr. Emad Elbeltagi