The Armagh Road construction works are the only remaining works<br />
that require significant traffic management. The extent of traffic<br />
management will be kept to a minimum, and in any case should not<br />
be required after early February 2006.<br />
We have also programmed to finish<br />
all side road construction<br />
works, including the accommodation<br />
works for adjacent landowners<br />
by March 2006. This includes<br />
works to the Ballymascanlan<br />
area. These works will<br />
not have any significant interference<br />
with traffic.<br />
On the main motorway we are currently<br />
carrying out other improvement<br />
works which include a major<br />
upgrade to the tolling system at the<br />
plaza, traffic counter installation and<br />
anti-skid surfacing. The toll system<br />
upgrade will further improve the<br />
driver experience passing through<br />
the plaza. Some minor traffic alterations<br />
will be utilised and these will<br />
be notified to the roadusers by our<br />
variable message sign boards and<br />
extra advance signage. We are also<br />
applying anti-skid surfacing to the<br />
interchange slip roads to improve<br />
safety on the off ramp approaches to<br />
the secondary roads. These works will be<br />
carried out off-peak on a phased basis over the coming weeks, again advance<br />
warning signage will be in place to advise motorists. These works are in addition<br />
to our ongoing routine maintenance programme which includes a comprehensive<br />
winter maintenance service.