12.07.2015 Views

Drillpipe Presentation - Drilling Engineering Association

Drillpipe Presentation - Drilling Engineering Association

Drillpipe Presentation - Drilling Engineering Association

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

~8\.\'b\nte HiP ipeJCl~Q'~OC.k8Steering~ ~~~cC~.~~~\~~Technology Summary25 February 2003www.intelliserv.net


ENABLING TECHNOLOGY FOR THE ENERGY INDUSTRYIn today’s economic and political climate it isessential for the energy industry to maximize assetproductivity. Accurate placement of the wellbore isrecognized as one important key to maximizing theproductivity of the well. Even more important isprecise knowledge of where pay zones (and hazardzones) are located. The cost of imprecise drilling orinaccurate geologic information ranges from smalllosses in productivity to complete loss of the well.Even small losses in productivity can translate intounrecoverable resources worth millions of dollars.Other more sobering costs of incorrect drillinginclude loss of human life.In order to avoid such losses, timely informationregarding the targeted resource, the trajectory of thewellbore, and the safety and stability of the well isessential to the drilling process. However, theseverity of conditions encountered in the drillingenvironment has largely kept the industry from entering into the age of information andconnectivity. Present drilling communications technologies are analogous to sendingsmoke signals, which prevents much-needed information from being relayed to the top ofthe well with the necessary speed and completeness.Certainly, high-speed data transmission inthe drilling environment would be a keyenabling technology for the energy industry.However, this technology has eluded theindustry for many years. As far back as 1939,technology had been proposed to provide datafrom down-hole to the surface. The stumblingblock in most instances was bridging the tooljoints connecting segments of drill pipetogether. Corrosion, shorting, and otherdamage to electrical connections at thesehundreds of tool joints, or intrusiveness orunreliability of the data transmission system,have effectively prevented commercializationof such data transmission systems.12/25/2003 INTELLISERV, INC. 2185 SOUTH LARSEN PARKWAY PROVO, UT 84606


and connection; and 4) full scale cantilever beam drill pipe fatigue testing. Results ofthese testing programs are provided below:1) Axisymmetric FEA of XT57connection – the figure showsVon Mises stress for thestandard XT57 connection atits maximum make-up torque(MUT) of 56,600 ft-lbs. Thegradual thread root radius of0.042″, slow taper 0.75 in/ftand double shoulder featuremake the XT connection thebest fatigue performing drillpipe connection offered byGrant Prideco.2) Axisymmetric FEA ofIntelliPipe® modified XT57connection – the figure to theright shows Von Mises stressfor the IntelliPipe® modifiedXT57 connection at a MUT of56,600 ft-lbs. A groove ispositioned in the internalsecondary torque shoulder ofthe connection. Localizedstress is present at the face ofthe secondary shoulder deemednot detrimental to theperformance of the connectionby Grant Prideco. Yielding ofthe pin nose at this MUT andhigher has not been observedduring field-testing.3) 3D FEA modeling of the IntelliPipe® modified internal upset geometry andconnection – the next figure shows 3D von mises stress of the IntelliPipe® modifiedinternal upset geometry under severe loading conditions (759,861 lbf tension load(90% of the new tube’s tensile capacity), 30,000 psi bending stress and 7,500 psiinternal pressure). Generally considered extreme and difficult analysis, IntelliServhas conducted a full three dimensional FEA analysis to illustrate the IntelliPipe®modified internal upset geometry does not produce stress concentrations that maylead to fatigue cracking in the modified region. The results of this analysis prove that92/25/2003 INTELLISERV, INC. 2185 SOUTH LARSEN PARKWAY PROVO, UT 84606


the internal modifications maintain the region of highest stress on the outside andinside diameter of the pipe rather than the localized modified internal region. Thisresult is consistent with Grant Prideco’s standard upset product. Further evidence ofthis is provided in the full-scale fatigue-testing program presented below.4) Full scale cantilever beam drill pipe fatigue testing – To support the results of the3D FEA modeling, IntelliServ has conducted full scale cantilever beam drill pipefatigue testing. The drill pipe tested had all IntelliPipe® modifications present. Tentest samples including box and pin ends of the drill pipe were tested to failure. Toexpedite the fatigue testing, large bending moments equivalent to 32 degrees per 100ft dogleg severity and high rotational speeds have been used to generate the cyclicloads. All samples have failed from fatigue in typical locations expected of standarddrill pipe designs. No samples have generated any cracking in the modified region ofthe internal upset geometry. These conclusions have been determined through visualexaminations and further detailed analyses through the Grant Prideco MetallurgicalDepartment.Further Developments. Development efforts are now underway to improve theflexibility and capabilities of the IntelliServ® drilling network software and hardware. Akey area of focus is integration of existing down-hole measurement and logging deviceswith the IntelliPipe® hardware and network system. Cooperative efforts with major toolmanufacturers are presently underway. Other completely new tools and applications forthe network are also being developed.A second key area of present focus is improving the passive transmission range of thesystem. As mentioned above, the present system has demonstrated transmission of 1000ft. prior to needing a boost in signal level. Improvements to transmission line efficiencyand electronic module sensitivity are expected to bring as much as a five-fold increase inthis passive range. Work to bring about these improvements has already begun.102/25/2003 INTELLISERV, INC. 2185 SOUTH LARSEN PARKWAY PROVO, UT 84606


A third area of focus is to extend the transmission line to other drillstring elementsincluding jars, drill collars, and miscellaneous subs. Work in each of these areas ispresently progressing. As a matter of particular interest, IntelliServ is working closelywith a major manufacturer of drilling jars, and a design for a wired jar is expected to betested during 2 nd quarter of 2003.Finally, further work is needed to increase the high pressure and high temperaturecapabilities of the IntelliCom components and the network electronics, so that thesecomponents may be used in the deepest wells and under the most severe drillingconditions.SCHEDULEMilestones. Commercial introduction of the IntelliServ® system is anticipatedduring 4 th quarter 2003. In order to prepare the technology adequately forcommercialization, several milestones have been set, including:• Demonstration of initial third party tool interface – Q1’03• Demonstration of wired jar and drill collars – Q2’03• Completion of deep well robustness tests – Q2’03• Testing of full drill string network – Q3’03• Field demonstrations and initial commercial applications – Q4’03A major effort and a major key to all of this work is field qualification of the system.IntelliServ is presently seeking opportunities to field test the data transmission system inlow risk applications. Such testing, though not without risk, is seen to be fairly benign tonormal drilling operations since the test will largely consist of handling drill pipe.System failures encountered in the testing, if any, are expected to have minimal impacton the drilling process, and can be corrected during normal tripping of the string. Fieldtesting of the system can commence during late 1 st quarter 2003 and is expected tocontinue throughout the year.COMMERCIALIZATION EFFORTSNovatek and Grant Prideco have formed a company named IntelliServ, Inc., which willbe the primary sales and service entity for IntelliPipe® and other drill string elementssuch as IntelliLinks, “data swivels,” drillstem and web servers, and subs that interfacewith 3 rd party measurement, logging, and control tools.112/25/2003 INTELLISERV, INC. 2185 SOUTH LARSEN PARKWAY PROVO, UT 84606


A primary function ofIntelliServ will be to modifyand assemble drill pipe andother drillstem elements. Inpreparation for this function,specialized machinerycapable of productionvolumepipe modification hasbeen built. Facilities havebeen acquired with sufficientlaboratory and warehousespace to handle the remainingdevelopment work, as well asinitial commercializationefforts. In addition,substantial land has beenpurchased, which offers suitable accommodation for a full-scale production and servicingplants and shipping facilities.CONCLUSIONThe IntelliServ® network is a key enabling technology for the energy industry, whichwill undoubtedly result in revolutionary improvements in the accessibility andcommerciability of energy resources. Certainly, bringing “information age” technologyto the drilling environment has long been an industry priority. IntelliServ is committed tobringing this industry dream to fruition.For further information please contact:David R. Hall 2185 South Larsen Parkway, Provo, UT 84606 USAEmail: dhall@intelliserv.net122/25/2003 INTELLISERV, INC. 2185 SOUTH LARSEN PARKWAY PROVO, UT 84606

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!