<strong>Earned</strong> Schedule Calculation• ES (cumulative) is the:Number of complete PV time increments EVequals or exceeds PV + the fraction of theincomplete PV increment• ES = C + I where:C = number of time increments <strong>for</strong> EV(BCWP BCWS)PVI = (EV – PV C ) / (PV C+1 – PV C )