HVDC P3 Project<strong>CIAG</strong> <strong>Update</strong><strong>29</strong> <strong>January</strong> <strong>2013</strong>1


Agenda -<strong>29</strong> Jan <strong>2013</strong>•Progress and schedule update. –A.Gard•System Test Plan. –G.Spence2


Project Progress –<strong>Update</strong>•AC Switchyards - complete•HAY Switchyard C & 220KV bus extensions A,B,C•BEN 220KV bus extensions C,B•BEN F/B 5 -F/B 6,7 & HAY F/B 5 in progress•11Kv and auxiliary supply systems –complete•Market Contracting Trial -complete•Remote AC stations work – BPE, WIL, LTN mostly complete• RPC Transition HAY and BEN•HAY transition commenced (T2,C2)•BEN G3-6 control tests complete•Pole 2 outage 11-16 Feb• Pole 2 / Pole 3 temporary interface• P3 DC switchyard primary connections and new plant• Cable stations –control and protection cutover• Electrode line protection and monitoringAndrew Gard3


System Test ProgrammeActivity Start FinishPole 3 Project Section 1Pole 1 De-commissioning 1 Aug 2012 -Equipment installation testing 1 Jul 2012- 30 Oct 2012Bipole shutdown I 31 Oct 2012 8 Nov 2012Bipole shutdown II 14 Dec 2012 16 Dec 2012Pole 3 plant installation tests and pre-commissioning 17 Dec 2012 7 Jan <strong>2013</strong>Bipole shutdown III 8 Jan <strong>2013</strong> 10 Jan <strong>2013</strong>Bipole shutdown IV (Temp Interface) 11 Feb <strong>2013</strong> 16 Feb <strong>2013</strong>RPC Commissioning 17 Feb <strong>2013</strong> 25 Feb <strong>2013</strong>Pole 3 Station & Low/Med System tests 26 Feb <strong>2013</strong> 21 Mar <strong>2013</strong>Repeat tests buffer 22 Mar <strong>2013</strong> 30 Mar <strong>2013</strong>Bipole shutdown V –cable 5 change 31 Mar <strong>2013</strong> 2 Apr <strong>2013</strong>Pole 3 System tests –High power 3 Apr <strong>2013</strong> 16 Apr <strong>2013</strong>Repeat tests & Mkt constraints buffer 17 Apr <strong>2013</strong> 6 May 2012Pole 3 Trial operation 7 May <strong>2013</strong> 24 Jun <strong>2013</strong>Pole 3 Commercial takeover 25 Jun <strong>2013</strong> -Note: Dates are subject to change. Changes notified via P3 website andmarket contracting group emailGreg Spence4


System Test Plan update• P2 and RPC testsSystem Test Programme– Pole 2 return to service - temporary interface confirmation (4)– HAY & BEN RPC commissioning -manual control tests (12 HAY, 5 BEN)– Some restrictions on P2 capacity ( 7 tests). Remainder of tests P2 available.• P3 energisation and low power tests– P3 open line test manual only– Station under voltage and under frequency ride through tests bought forwardfrom medium power test section• P3 medium and high power tests– P2 energisation tests with P3 on load– Electrode line staged fault testsGreg Spence5


• P3 Secondary risk requirementsP3 Secondary Risk– Refer column test plan column “Secondary Risk Reference” and test planuser guide.Risk DefinitionRisk EventSystem Frequency Minimum(Hz)SINISystemVoltageRange(NI & SI)Riskref noFrequency primary risk System frequency CE 48 48 +/-10% 1System frequency ECE 45 47 +/-10% 2Pole 3 secondary risk tofrequency events & frequencyCE thresholdPole 3 secondary risk tofrequency events & frequencyECE thresholdPole 3 + System frequencyCEPole 3 + System frequencyCE48 48 +/-10% 345 47 +/-10% 4Voltage primary risk System voltage CE 48 48 +/-10% 5Bipole secondary risk tovoltage events & frequencyCE thresholdBipole + System voltage CE 48 48 +/-10% 6Bipole secondary risk tovoltage events & frequencyECE thresholdBipole + System voltage CE 45 47 +/-10% 7Greg Spence6


Risk ProfileSecondary RisksP3 Secondary Risk -updatePole 3 Commissioning – Secondary RisksRev 7 1 December 2012V= voltage coupledsecondary risk= frequency coupledsecondary riskVP2 Trip for loss of filtersafter voltage disturbanceVAfter pole trip, temporary interface fails to transfer power tohealthy poleVIncorrect RPC control ofWellington Voltage aftervoltage disturbanceVVP3 Trip for loss of filters after voltage disturbanceIncorrect RPC control of Wellington Voltageafter voltage disturbanceVP3 Trip for AC Faults up to 350 MW NorthwardVP3 Trip for AC Faults up to 1000 MW NorthwardVP2 Trip for Pole 3 commutation failureVP3 Trip for auxiliary ride-throughIncorrect modulation control response for generator tripsRPC ManualRPC AutoP3 OffvoltageP3EnergizationP3 Low Load P3 Medium Load P3 Full Load P3 OverloadCommissioning ProgressPole 2 risk for Voltage eventsCEPole 3 Secondary risk to Frequency events CE(risk ref no 3)Bipole Secondary risk to Voltage events CE(risk ref no 6)P3 Secondary risk to Frequency events ECE(risk ref no 4)Bipole Secondary risk to Voltage events ECE(risk ref no 7)Greg Spence7


OtherPole 3 availability during Trial operation period (49 days).Removed at short notice if defects/issues ariseRole of <strong>CIAG</strong> during testingTesting planned and managed via BAU process<strong>CIAG</strong> point of communication / discussion if issues ariseMarket communications during testingMarket contracting email listWebsite updateCANWider industry communicationsTP Account exec emailWebsite updateCAN8