MP ROAD DEVELOPMENT CORPORATION LTD. BHOPALREPLY OF PRE-BID MEETING HELD ON 16.04.2007 AT 11. 00 AM REGARDING SELECTION OFINDEPENDENT CONSULTNT FOR JAORA ROAD PROJECT.S.No. Query <strong>Reply</strong> <strong>of</strong> MPRDC1. As per clause-7 <strong>of</strong> LOI at page 12 pertaining to Performance Security,the Consultant shall furnish within 15 days <strong>of</strong> issue <strong>of</strong> letter <strong>of</strong>acceptance an unconditional Bank Guarantee equivalent to 10% <strong>of</strong> thetotal contract value to be received by him, while as per clause 18 <strong>of</strong> ToRat Page 30 the consultant shall be required to submit acceptable bankguarantee for an amount <strong>of</strong> equal to 5% <strong>of</strong> the acceptable consultancycost towards performance security. Since the percentage <strong>of</strong> contractamount towards performance security is not the same at two places. Theclient may kindly indicate the correct figure. Since we will be furnishingpr<strong>of</strong>essional liability insurance, performance security need not be thereor at best only 5%.2 As per clause 3.5(c) <strong>of</strong> general con <strong>of</strong> the contract at page 53, it is statedthat the consultant shall provide pr<strong>of</strong>essional liability insurance (PlI)with a minimum coverage equal to the total amount <strong>of</strong> the contract validfor a period <strong>of</strong> 5 years after completion <strong>of</strong> the services.In this regard, it is pointed out that based on <strong>pre</strong>vailing practice <strong>of</strong>NHAI, ADB and World Bank funded projects <strong>of</strong> <strong>Independent</strong>Consultant and Construction Supervision, the validity period <strong>of</strong> PLI isup to the period <strong>of</strong> contract. In view <strong>of</strong> the above, the client may kindlyconsider to modify this clause stating that the consultant may providePLI valid up to the period <strong>of</strong> services.Performance Security stands revised to 5%in clause 7 <strong>of</strong> LOI – page 12.The period <strong>of</strong> Pr<strong>of</strong>essional LiabilityInsurance is modified to 3 years postcompletion <strong>of</strong> services.3 As per clause 12 <strong>of</strong> ToR at Page 26 the designation <strong>of</strong> leader <strong>of</strong> the teamhas been indicated as Team Leader-cum-Highway Engineer, while hisdesignation in Annex-II at page 37 has been indicated as Team Leadercum-Highway/BridgeEngineer. The client may kindly indicate theIt is Team Leader-cum- Highway Engineer.1


S.No. Query <strong>Reply</strong> <strong>of</strong> MPRDCcorrect designation <strong>of</strong> the leader <strong>of</strong> the team.4 As per Annexd-1 pertaining to Abstract <strong>of</strong> Cost at Page 36 <strong>of</strong> RFP themiscellaneous cost has been indicated as “reimbursable”. It appears thatthe client is referring the miscellaneous cost to the equipments indicatedat Annexure-IV at page 39. If that is so, then this cost should be Fixedand not reimbursable as the consultants are to indicate their rentalcharges per month. The client may kindly look into this aspect andclarify the position.Yes. It refers to the miscellaneous cost.Rest no change.5 We would like to request that the date <strong>of</strong> the submission <strong>of</strong> the proposalis extended at least two weeks. This will help us to <strong>pre</strong>pare acom<strong>pre</strong>hensive proposal after incorporating the clarifications receivedfrom the client.6 Para 10 <strong>of</strong> Data Sheet -,Page 15 <strong>of</strong> RFP documents:The time for submission <strong>of</strong> proposals is too short. As per standardspractice followed by other <strong>pre</strong>mier organization like NHAI, State PWDetc. reasonable time <strong>of</strong> at least a fortnight after receipt <strong>of</strong> the minutes <strong>of</strong><strong>pre</strong>-<strong>bid</strong> <strong>meeting</strong> may kindly be allowed for submission <strong>of</strong> proposals. Assuch the last date <strong>of</strong> submission <strong>of</strong> proposals may kindly be extendedup to 9th May, 2007/7 Para 3(a) <strong>of</strong> Data Sheet – Page 14 <strong>of</strong> RFP documents> In risk andcoverage third party motor vehicle liability insurance has been included.Since consultant will hire vehicles for the consultancy service, dulyinsured by the owner, separate insurance is not considered necessaryfrom the consultant. This may kindly be confirmed.8 Para-12.1(ii) <strong>of</strong> Data Sheet Page 15.-16 <strong>of</strong> RFP document : Experiencefor <strong>Independent</strong> ConsultancyThe following modification is required <strong>of</strong> experience is recommended.i) Experience <strong>of</strong> independent consultant for 2 lane road shouldalso be acceptable by converting into equivalent 4 lane roadlength.ii)Experience in providing consultancy service in associationwith Prime Consultants should also be acceptable.Last date <strong>of</strong> submission is extended up to4 th May, 2007 up to 3.00 PMExtended up to 4 th May, 2007 up to 3.00PM.Yes. The vehicle deployed must be dulyinsured by owner.No changeNo change2


S.No. Query <strong>Reply</strong> <strong>of</strong> MPRDCiii) As regards experience in supervision <strong>of</strong> Flyover/ElevatedRoad/Bridge more than 300 m length where the construction<strong>of</strong> such structure has been done along with 4 laning <strong>of</strong> road,separate certificate <strong>of</strong> experience from Principal Employermay not be insisted upon.9 Para 12.1(vi): If consultants furnish details <strong>of</strong> projects whereconsultancy service has been rendered as per Tabular Statement <strong>of</strong> para12.1(vi) along with copy <strong>of</strong> agreement with Prime Consultant thisshould be acceptable.10 Key Personnel:Para 12 <strong>of</strong> Data Sheet (Page 26-27 <strong>of</strong> RFP documents).The composition<strong>of</strong> <strong>Independent</strong> Consultancy Team as laid down in Data Sheet includesfollowing: (a) Highway Design Engineer and Bridge Design Engineerfor limited period <strong>of</strong> 10 monthsIt is recommended that these experts should function based on HeadOffice instead <strong>of</strong> being located at Project site. The experts will visitsproject site as and where required spending several days each time.Actual time <strong>pre</strong>sent in project site spent by them can be charged toconsultancy fee.b) Environmental Specialist/BOT contract specialist and CADEngineer: Para 12 <strong>of</strong> data sheet page 26.-27 <strong>of</strong> RFPdocuments: Similarly, these experts also should be permittedto operate from Home <strong>of</strong>fice and actual time spent by themshould only be charged to consultancy fee.c) Material and pavement Engineer: Qualification <strong>of</strong> Graduate inCivil Engineering with 15 years experience has been laiddown. Diploma holder with 20 years experience should alsobe acceptable for these 2 categories in 2 laning <strong>of</strong>Hoshangabad-Harda-Khandwa, and Hoshangabad-Piparia-Pachmarhi road under MPRDC such qualification wasaccepted.Agreed, but the certificate should clearlymention the same.Certificate from client is mandatory.AgreedAgreedNo change3


S.No. Query <strong>Reply</strong> <strong>of</strong> MPRDC11 Junior Technical Staff:Asstt. Highway Engineer, Asstt. Bridge Engineer, Asstt. MatgrialEngineer: para 2 <strong>of</strong> data sheet page 27& 35 <strong>of</strong> RFP.The following recommendation are made:a) Qualification <strong>of</strong> Diploma in Civil Engineering with 7/8 years No changeexperience should be accepted as approved by NHAI in similarprojectb) Nos. <strong>of</strong> such support personnel particularly for Asstt. Highway No changeEngineer and Asstt. Bridge Engineer should be at least 3 Nos. each.12 Age limit 65 years has been laid down for all personnel: Para No change3.2.3(vii) <strong>of</strong> LoI.: It is recommended that age limit <strong>of</strong> 70 years shouldbe accepted for key personnel. For support personnel this can be 65years.13 Letter <strong>of</strong> Invitation (LoI) Page 4 & 5 : While there is a mention shouldparticipation by Joint Venture, the LoI is silent about Association .No changePlease clarify if association with other firms are permissible.14 Methodology: Para 3.3 (iii) <strong>of</strong> LOI: Page 8 :The number <strong>of</strong> pages for the proposed methodology has not beenindicated. Normally in such cases a limit <strong>of</strong> 5 to 8 pages is indicated.You are requested to indicate the limit <strong>of</strong> the number <strong>of</strong> pages for theproposed methodology for execution <strong>of</strong> the assignment.15 Submission <strong>of</strong> proposal : Para 4.1 and 4.1.2. <strong>of</strong> LOI : Page 9 :In para 4.1 it is mentioned that the <strong>bid</strong>der must submit one originalproposal duly signed on every page . In para 4.1.2 it is mentioned thatthe original and each copy <strong>of</strong> the technical and financial proposalsmust be <strong>pre</strong>pared in indelible ink and must be signed by the authorizedre<strong>pre</strong>sentative. It is further mentioned that all pages <strong>of</strong> the technical andfinancial proposals must be initialed by the person signing he proposalThe requirements given in these para are contradictory. Normally, theoriginal proposals are <strong>pre</strong>pared in indelible ink and the covering letter(letter <strong>of</strong> transmittal) is signed by the authorized re<strong>pre</strong>sentative and allother pages are initialed. Thereafter, photo copies are taken <strong>of</strong> the dulyIt will be adjudged on the basis <strong>of</strong> quality<strong>of</strong> work rather than quantity <strong>of</strong> pages.Agreed.4


S.No. Query <strong>Reply</strong> <strong>of</strong> MPRDCsigned/initialed pages <strong>of</strong> the original proposals and submitted asrequired number <strong>of</strong> copes. You are requested to amend the provisions <strong>of</strong>these two paras accordingly .16 Performance Security : Para 7 <strong>of</strong> LOI Page 12 and Para 18 <strong>of</strong> Terms <strong>of</strong>Reference (TOR) page 30:In para 18 <strong>of</strong> TOR the Performance Security is indicated as an amountequal to 5% <strong>of</strong> the accepted consultancy cost. In para 7 <strong>of</strong> LOI howeverit is mentioned as 10% <strong>of</strong> the total contract value. It is requested thatReduced to 5%para 7 <strong>of</strong> LoI be modified in line with para 18 <strong>of</strong> TOR.17 Commencement <strong>of</strong> assignment: Clause 2.3 <strong>of</strong> General Conditions <strong>of</strong>contract (GCC) and Para 17 <strong>of</strong> Data Sheet: Page 45 & 18.The time period for commencement <strong>of</strong> the assignment may please bekept as 30 days after the effective date <strong>of</strong> contract in accordance withClause 2.3 <strong>of</strong> GCC and para 17 <strong>of</strong> Data Sheet be amended accordingly.,18 Conduct <strong>of</strong> Test: Para 7.10 and 7.11 <strong>of</strong> TOR : Page 24”It appears that the reference is intended to be made in respect <strong>of</strong> para 7.9and not 7.5 as stated . Please clarify.19 Expected inputs <strong>of</strong> support staff: Table 2 under para 12 <strong>of</strong> TOR ( Page27):It is seen from para 12 that while the implementation <strong>of</strong> the project isorganized in terms <strong>of</strong> single package, the road has been split into twohomogeneous section for the purpose <strong>of</strong> construction. However, it isseen from Table – 2 that only one each <strong>of</strong> Asstt. Highway Engineer andAstt. Bridge /engineer have been provide for both the constructionsection. It is suggested that these be increased to two each.20 Bridge Design Expert : Table <strong>of</strong> Minimum Qualification: Page 32:It is seen that experience in bridge project has been indicated as“Minimum 10 years in Planning, Project Preparation , Design andSupervision <strong>of</strong> Bridge Project./ It is submitted that the position is for adesign expert for bridges. It is therefore requested that the requirement<strong>of</strong> supervision <strong>of</strong> projects be deleted.Time for commencement <strong>of</strong> services willbe 30 days after the effective date <strong>of</strong>contract.- Period <strong>of</strong> consultancy cl. 18 at page 18 isrevised from 30 months to 22 months.Cross reference <strong>of</strong> clause 7.5 in para 7.10and 7.11 be read as 7.9No changeNo change5


S.No. Query <strong>Reply</strong> <strong>of</strong> MPRDC21 Highway Engineer: Table <strong>of</strong> Minimum Qualification : Page 32: No changeIt is seen that experience in highway projects has been indicated asminimum 10 years in planning, project <strong>pre</strong>paration, design <strong>of</strong> highwayprojects, It is submitted that this position is for supervision. It istherefore requested that the requirement <strong>of</strong> design be deleted.22 Bridge Engineer: Table <strong>of</strong> minimum qualification Page 32It is seen that experience in bridge projects has been indicated as No changeminimum 10 years in planning, project <strong>pre</strong>paration, design,construction./supervision <strong>of</strong> bridge project. It is submitted that thisposition is for supervision. It is therefore requested that the requirement<strong>of</strong> design be deleted.23 BOT contract specialists: Table <strong>of</strong> minimum qualification: page 34The essential educational qualification may please be corrected asGraduate in law or chartered accountant.Agreed. Word “<strong>of</strong>” be read as “or”.6