13.07.2015 Views

INSTALLATION GUIDE - Hubbell Power Systems

INSTALLATION GUIDE - Hubbell Power Systems

INSTALLATION GUIDE - Hubbell Power Systems

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Recommended Installation ProcedureStep 21. Pour Concrete and FinishPour concrete and after theconcrete has achieved sufficientcure, remove grates anddiaphragms. Knock off protruding endsof dry wall screws(a hammer works well for this).NOTE: Do not radius the edge of theconcrete adjacent to the drain.NOTE: Concrete encasement can beplaced in a single lift.Step 22. Clean UpAfter excess screw threads have been removed, unwrapgrates and place in frames. If locking devices arerequired, install them at this time(see Detail 22A).PROCEDURE- 13 -

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!