Publications
DEL Custom Built Bodies - Equipment Review Magazine
DEL Custom Built Bodies - Equipment Review Magazine
- No tags were found...
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
PROJECT PROFILE: EMCO Waterworks<br />
ZCL Tanks Provide the Solution<br />
for ATCO/Siemens Project<br />
“…making the<br />
logistics of electrical<br />
transmission a reality<br />
for Albertans.”<br />
By Chad Placsko, Water Management<br />
Specialist, EMCO Waterworks, Calgary<br />
With sustainable power consumption on<br />
the rise, ATCO and Siemens have teamed<br />
up to meet this ever growing demand. The<br />
Newell ATCO site near Brooks, Alberta<br />
has been a beehive of activity this year<br />
creating a convertor station that changes<br />
AC power to DC power, making the<br />
logistics of electrical transmission a reality<br />
for Albertans.<br />
The project itself was an exciting challenge<br />
for the owners, the engineers working on<br />
the system, and the contractor that was<br />
hired to make this plan a reality. As the<br />
location of the site was remote, each aspect<br />
of the project needed to be calculated<br />
carefully. EMCO Waterworks in Calgary<br />
was charged with the responsibility to<br />
“Project Manage” the purchasing and<br />
supply of most of the project items<br />
required, including twelve large ZCL<br />
Fiberglass tanks. ZCL tanks were<br />
chosen for a variety of reasons. They are<br />
watertight, lightweight, easy to install, and<br />
corrosion resistant. ZCL’s unique outside-in<br />
fabrication process and fully integrated rib<br />
structure result in tanks that can withstand<br />
the pressures of being submerged in water<br />
to grade while empty with simultaneous<br />
H-20 traffic loads. Being underground these<br />
tanks don’t take up valuable land space<br />
and eliminate concerns relating to frost and<br />
freezing. Unlike above-ground tanks that<br />
can create a negative visual impact, the<br />
ZCL tanks also make the property more<br />
aesthetically pleasing.<br />
Seven of the ZCL tanks were used as part<br />
of the project’s fire suppression system - a<br />
holding tank system allowing for nearly<br />
a million liters of emergency and fire<br />
suppression water to be pumped through<br />
almost a kilometer of IPEX pipe. The<br />
system creates a fire loop that feeds eight<br />
separate hydrants. The largest of the tanks<br />
measures over 70 feet long and 10 feet in<br />
diameter. Using a trombone trailer, Spruce<br />
Valley Carriers transported the tanks<br />
which were delivered to the site and then<br />
craned into place. The tanks are connected<br />
through a header system that feeds a 16”<br />
pump that pressurizes the system, on<br />
standby and ready for usage as required.<br />
Two of the remaining five tanks were<br />
designed for both a potable water holding<br />
system and a centralized septic holding<br />
tank, and three of the tanks were designed<br />
to handle the septic drainage associated<br />
with individual buildings around the site.<br />
The ZCL tanks are anchored to the ground<br />
with an engineered system of precast<br />
concrete anchors and specially fabricated<br />
fiberglass straps allowing them to stay in<br />
place after backfill, even when empty. The<br />
fourteen straps holding down the largest<br />
of the tanks are attached to the concrete<br />
anchors with turnbuckles. The tanks<br />
themselves are a single-walled design,<br />
fabricated with vents and “manways” to<br />
allow access and entry if needed. The grid<br />
of seven tanks is tied together with a header<br />
to equalize the levels as well as to drain<br />
them evenly if needed in an emergency.<br />
Water is a growing concern for many<br />
projects such as this. The ability to be<br />
self-sufficient in this regard was of vital<br />
interest to ATCO and Siemens. The ZCL<br />
tanks allow each water-related step of this<br />
project to be maintained and sustained for<br />
years to come.<br />
PROJECT PARTNERS<br />
Owner: ATCO Electrical<br />
Prime Contractor: Siemens Canada<br />
Electrical / Civil General: Black &<br />
McDonald, ON<br />
Civil Contractor: Four Season Site<br />
Development, ON<br />
Tank Supplier: EMCO Calgary<br />
For more information on this project or the<br />
tanks shown, contact your local EMCO<br />
Waterworks location.<br />
20 EQUIPMENT REVIEW<br />
ALL NEW www.equipmentreview.ca<br />
Fall 2013 EQUIPMENT REVIEW 21