______________________________________________ Fig. 15.1<br />

INSTALLING THE INSULATION BOARD ON<br />

COMMERCIAL DRAINAGE EIFS PROJECTS<br />

The previous section of this guide has shown the preliminary<br />

tasks of wrapping rough openings, backwrapping, installing<br />

tracks, water-resistive barriers and flashing required for<br />

the different Parex USA Commercial Drainage EIFS Systems.<br />

One system requires mechanical attachment of the EPS<br />

board and the other, liquid applied barrier system, makes<br />

use of adhesive attachment. The layout and application of<br />

the EPS board is the same for each system even though the<br />

attachment method may differ. Information regarding those<br />

differences is listed here:<br />

When the adhesive is used in the WaterMaster System:<br />

The ribbons of adhesive must be made with a 1/2 x 1/2 x 2 in.<br />

(13 x 13 x 51mm) spacing U-notched trowel. The ribbons<br />

of adhesive must run vertically when positioned on the<br />

substrate (parallel to the 2 ft. [61cm] board dimension).<br />

(Fig 15.1)<br />

The rules for insulation board installation have been<br />

described and shown with the Standard System, beginning<br />

on page 4 and continuing through the finish and sealant<br />

application on page 15.<br />