You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
CASE STUDY<br />
Installation of the Carl-Urich<br />
Bridge, Germany<br />
Bridge Launching<br />
OVERVIEW: The installation of the Carl-Ulrich<br />
Bridge in Offenbach am Main, Germany, has<br />
been successfully completed by ALE.<br />
SERVICES REQUIRED: Jacking up the bridge<br />
and preparing the transportation<br />
Weighing 1,100t and measuring 150m long,<br />
the new bridge was built on the quayside.<br />
The bridge was jacked up 1.6m using four<br />
500t capacity climbing jacks. 48 axle lines<br />
of SPMT were prepared with supporting<br />
construction and positioning underneath the<br />
bridge. Hydraulic jacks were placed on top of<br />
the frame to be able to compensate for the<br />
deformation of the bridge.<br />
BRIDGE LOAD-OUT: The bridge was loaded<br />
out onto the SPMTs and driven onto two, 66m<br />
x 11.5m barges. Each barge was fitted with a<br />
bespoke combination of four winches and four<br />
fairleads to guide the winch wires, along with<br />
a hydraulic powerpack and generator to power<br />
the winches.<br />
BRIDGE INSTALLATION: The bridge was<br />
transported from the quayside to its final<br />
location across the river Main by rotating<br />
the bridge 90 degrees and connecting each<br />
barge to the river bank with four winches,<br />
which were then used to guide the bridge,<br />
SPMT and barges to the installation position<br />
of the bridge. During this process, the anchor<br />
points of some winches were changed in<br />
between phases. When the final position was<br />
reached, the bridge was then lowered into its<br />
foundations by ballasting the barges.<br />
BRIDGE JACKING<br />
CASE STUDY<br />
Rail bridge<br />
replacement, UK<br />
OVERVIEW: ALE replaced a 500t railway bridge<br />
in Liverpool as part of a track upgrade.<br />
SERVICES REQUIRED: The bridge decks which<br />
were adjoined to Liverpool Sandhills station<br />
were removed using twenty eight axles of<br />
SPMT. ALE integrated sixteen 100t capacity<br />
climbing jacks into the transport arrangement,<br />
to ensure height requirements over the<br />
abutment wall.<br />
To complete the project the old and<br />
replacement bridge decks were required to<br />
be manoeuvred around the station platform<br />
and beneath a temporary walkway bridge.<br />
ALE used various configurations of SPMT to<br />
achieve the limited space manoeuvres, ALE<br />
also had to ensure that no loading was applied<br />
to the large section of pavement that needed to<br />
be crossed, this was achieved by transporting<br />
them across bridging mats. The decks were<br />
then offloaded to high level trestles where they<br />
would then be jacked down for demolition.<br />
The 270t replacement bridge decks which were<br />
previously jacked up to installation height in<br />
preparation were removed from the trestles<br />
using sixteen axles of SPMT complete with<br />
high level trailer steelwork.<br />
Together, we are Smarter, Safer, Stronger<br />
21