16.12.2015 Views

CIVILS BROCHURE

1I9bRVU

1I9bRVU

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Bespoke Solutions<br />

BESPOKE SOLUTIONS<br />

CASE STUDY<br />

Pillar-box unloading, UK<br />

OVERVIEW: ALE unloaded two pillar-boxes<br />

weighing over 450t each which belong to<br />

the main piles of the new Forth Replacement<br />

Crossing in Scotland.<br />

SERVICES REQUIRED: Before work began,<br />

a test was conducted on the loading of the<br />

mast. It was carried out with a 5% overload<br />

and 36m radius.<br />

ALE utilised a lifting system connected to<br />

the main mast with a capacity to lift 560t at<br />

a radius of 36m. The mast was supported at a<br />

distance of 64m to the rear by two HLS5000<br />

units, which allowed for lifting or lowering.<br />

The retaining units and the main boom were<br />

placed onto resistant bulkheads on the barge.<br />

Over the bulkheads, a structure was installed<br />

to spread the load along the barge’s reinforced<br />

bulkheads.<br />

To lift and lower each piece, two HLS5000<br />

units were installed at the top end of the mast.<br />

A modular adjustable lifting beam with a<br />

capacity to lift 250t was also installed.<br />

ALE then assembled the mast on the barge in<br />

a horizontal position over temporary supports.<br />

An auxiliary crane was used to perform the<br />

vaulting of the main mast.<br />

CASE STUDY<br />

Bridge uprighting over<br />

the Cuarto River,<br />

Argentina<br />

OVERVIEW: Two steel towers that make<br />

up the new 190t bridge over the Cuarto<br />

River in Argentina have been successfully<br />

uprighted by ALE.<br />

SERVICES REQUIRED: The operations<br />

began with ALE utilising a swivelled gantry,<br />

which incorporated an axis of rotation at<br />

the base to enable simultaneous rotation<br />

as the tower was lifted.<br />

In addition to this, five lifting units were<br />

required for the elevation of the tower and<br />

a final 70t unit was used for retaining as<br />

the centre of gravity passed over the axis<br />

of rotation.<br />

Together, we are Smarter, Safer, Stronger<br />

43

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!