02.03.2016 Views

assets

1OQRNnt

1OQRNnt

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Straits the ship arrived in Souda Bay,<br />

Crete on 12 March and moored on the<br />

east end of Marathi Pier, starboard-sideto,<br />

at K14; see Figure 1. The Advance<br />

Party ensured there was adequate space<br />

between the quay wall and the ship’s<br />

skin by breasting out the ship nearly 20<br />

ft. using a combination of barges and Yokahoma<br />

fenders. Breasting out the ship<br />

allowed for ample space to extract and<br />

install the hub/cofferdam combo without<br />

the danger of exceeding the cranes reach<br />

and lifting capacity. Additionally, in anticipation<br />

of the 48Klbs CPP Hub and<br />

Figure 2<br />

Cofferdam combo heavy lift, great care<br />

was given to crane placement and ship<br />

position relative to one another to ensure<br />

the lifting capability of the 200Klbs<br />

capacity crane was not exceeded.<br />

Upon arrival and shifting colors, the<br />

vessel was immediately unloaded. Its<br />

entire cargo, including both the NRFI<br />

and RFI blades (10 total), were removed<br />

from the ship and staged appropriately<br />

on the pier. The dive side was set up<br />

and fully geared for 24/7 operations; as<br />

seen in Figure 2 , several<br />

tents were erected to protect<br />

critical gear, all diving<br />

support systems were<br />

made functional, support<br />

service ordered, to include,<br />

external lighting for night<br />

time operations, back up<br />

air and power sources, etc.<br />

Lastly, Phoenix dive team<br />

integrated into the repair<br />

effort. A total of three 10<br />

man dive teams working<br />

Figure 1<br />

on a 24/7 basis was the<br />

corps work ethic. More<br />

specifically, it was decided<br />

that each dive team would work a 10<br />

hour day with 1 hour overlap<br />

with each on-coming<br />

and off-going shift. This<br />

work schedule supported<br />

8 hours of in-water diving<br />

and allowed the teams set<br />

up and break down periods<br />

with minimal work<br />

stoppages between shifts.<br />

The first Souda Bay<br />

dive was conducted on 13<br />

March following<br />

pier lay-down completion<br />

at approximately 0100L, the<br />

evening of the ship’s arrival<br />

in port. The team immediately<br />

went to work successfully<br />

removing 1A Blade port<br />

cover and installed the hub<br />

davit that would be used to<br />

help remove the rope guard.<br />

At the same time, both port<br />

and starboard rigging beams<br />

installation started, as well Figure 4<br />

as the de-oiling operation of<br />

the hub and shaft; approximately 1100<br />

Gallons of oil required removal. Unfortunately,<br />

none of these events went according<br />

to plan. For instance, the rigging<br />

beams had to be removed after being<br />

fully installed because the Delrin spacers<br />

of both beams were not flush to the<br />

hull due to interferences with the strut<br />

pads. Both beams were removed, the<br />

Delrin spacers tailored to fit and then reinstalled.<br />

As seen in figure 3, the rigging<br />

beams are attached directly above the<br />

hub and are attached to the ship’s hull by<br />

two U-bolts in the 8 inch lifting tunnels.<br />

It proved to be very challenging<br />

to fully de-oil the ship’s CPP system<br />

through the damaged hub. The seals on<br />

the hub were completely<br />

compromised making isolation<br />

for the surrounding<br />

water extremely challenging.<br />

To mitigate oil leakage<br />

from the damaged hub Souda<br />

Bay Oil Spill Response<br />

Team, led by LT Johnathan<br />

“Chris” White, was called<br />

into action to fully contain<br />

and clean up any oil spilled.<br />

In an attempt to mitigate oil<br />

Figure 3<br />

loss and promote collection<br />

of the oil, the PA system<br />

was plugged with expansion<br />

bolts. Also, a 13’ x 11’ x 1.5’ Inverted<br />

Drip Pan (IDP) System was designed,<br />

fabricated, and installed directly over the<br />

CPP Hub to collect oil. As seen in figure<br />

4, this pan, constructed of mild steel, was<br />

essentially a drip pan turned upside down<br />

and suspended from a series of chainfalls<br />

directly attached to the belly bands<br />

that were surrounding the hull of the ship.<br />

This prevented nearly 500 gallons of oil<br />

release into the surrounding environment.<br />

January 2016 18

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!