17.03.2016 Views

SUPREME COURT OF QUEENSLAND

QSC16-055

QSC16-055

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

2<br />

rectify the defendant’s breaches of the contract specified in the<br />

statement of claim and claims the costs of rectification as loss<br />

and damage – where the defendant applies to strike out<br />

paragraphs of the plaintiff’s statement of claim on the basis<br />

that the paragraphs failed to assert a causal nexus between the<br />

alleged breaches and the items of loss or damage – where the<br />

plaintiff relies on the application of the “ruling principle” for<br />

the assessment of damages for breach of contract – whether<br />

sufficient material facts are pleaded by the plaintiff to support<br />

the cause of action for damages for breach of contract<br />

COUNSEL:<br />

SOLICITORS:<br />

Bellgrove v Eldridge (1954) 90 CLR 613, considered<br />

Clark v Macourt (2013) 253 CLR 1; [2013] HCA 56,<br />

considered<br />

Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 310<br />

ALR 113, considered<br />

Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009)<br />

236 CLR 272; [2009] HCA 8, considered<br />

Willshee v Westcourt Ltd [2009] WASCA 87, considered<br />

G Beacham QC with B O’Brien for the plaintiffs<br />

R A Holt QC with L Clark for the defendant<br />

Herbert Smith Freehills for the applicants<br />

McCullough Robertson Lawyers for the defendant<br />

[1] The defendant applies to strike out paragraphs 19 to 23 of the plaintiffs’ statement of<br />

claim filed on 23 April 2015 or, in the alternative, for an order that the plaintiffs provide<br />

further and better particulars in respect of paragraphs 19(d) and 20 to 22. The application<br />

is opposed on behalf of the plaintiffs. There is a dispute between the parties as to what<br />

material facts must be pleaded in respect of the plaintiffs’ claim for damages for breach<br />

of contract arising from works performed by the defendant (an earthworks contractor) in<br />

constructing an earthworks dam and associated works at Goonyella Riverside Mine near<br />

Moranbah.<br />

Background to plaintiffs’ claim<br />

[2] The plaintiffs are joint venture parties which own the mine and the first plaintiff is the<br />

management company which operates the mine for them. The relevant contract was<br />

entered into between the first plaintiff and the defendant in December 2010. In December<br />

2011 the first plaintiff terminated the contract. At the time the termination took effect in<br />

January 2012, the construction of the dam was incomplete.<br />

[3] This proceeding was commenced by the plaintiffs in July 2013 claiming damages for<br />

breach of contract and repudiation. The breaches alleged in paragraphs 14 to 18 of the<br />

statement of claim are the placement of “lots” of soil in the embankment of the dam which<br />

do not comply with the specifications in the contract, along with the late delivery or nondelivery<br />

of the test results and reports required under the contract which were required to

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!