SUPREME COURT OF QUEENSLAND
QSC16-055
QSC16-055
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
9<br />
promised. In this way, the measure of damages captures for the purchaser the<br />
benefit of the bargain and so compensates the purchaser for the loss of that<br />
benefit. (footnote omitted)<br />
[31] The defendant relies on a statement made by Leeming JA (with whom the other members<br />
of the court agreed) in Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 310 ALR<br />
113 in dealing with what the plaintiff in a building case must prove to establish damages<br />
for breach of contract where there is a “global claim” for damages. Leeming JA<br />
confirmed at [186] that “there are no special legal principles that mean the plaintiffs in<br />
‘building cases’ win or lose differently from plaintiffs in other classes of contractual<br />
case”. Leeming JA then stated at [187]-[188]:<br />
“[187] A plaintiff seeking damages will fail unless he, she or it establishes<br />
breach, causation and loss.<br />
[188] True it is that some decisions on breach of contract in building cases<br />
have used the language of ‘global claim’. Contrary to what was at<br />
the forefront of Mainteck’s written and oral submissions, this does<br />
not involve any special principles of fact or of law.”<br />
[32] There is nothing in these general observations by Leeming JA in Mainteck which detract<br />
from the authority of Bellgrove and Tabcorp in the application of the ruling principle to<br />
the assessment of damages for breach of contract.<br />
Are all material facts pleaded in the statement of claim?<br />
[33] The plaintiffs are not required to plead that they are seeking for the damages to be<br />
assessed by the application of the ruling principle, as that is law that applies to the<br />
plaintiffs’ claim in accordance with the relevant authorities. A subsidiary complaint<br />
which the defendant’s solicitors had made in the r 444 letter dated 12 November 2015<br />
was that for the costs of rectification work to be recoverable as damages for breach as the<br />
plaintiffs had pleaded in their statement of claim “the dam must have been deficient in<br />
some way as a result of the alleged breaches” and asserted that the plaintiffs need to plead<br />
that each of those breaches created a deficiency in the dam and what the deficiency was.<br />
In similar vein, the defendant submitted on this application that no practical consequence<br />
from any defect in the dam, such as the dam not being reasonably fit for its purpose, is<br />
pleaded. The subsidiary point raised by the defendant is not supported by the relevant<br />
authorities.<br />
[34] In a claim for damages for breach of a construction contract in reliance on Bellgrove, the<br />
statement of claim must plead the relevant provisions of the contract, identify the breaches<br />
and then plead the action the plaintiffs assert must be taken to rectify the breaches to<br />
achieve conformity with the contract. This must be followed by the specification of the<br />
loss and damage arising from the costs of rectification.<br />
[35] The defendant’s submission which is critical of paragraph 20 (and also paragraph 21) of<br />
the statement of claim asserts that these are the paragraphs alleging loss and damage<br />
arising from the alleged breaches and that no attempt is made by the plaintiffs to identify<br />
or plead the causal nexus between breaches and the alleged loss and damage.