17.03.2016 Views

SUPREME COURT OF QUEENSLAND

QSC16-055

QSC16-055

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

9<br />

promised. In this way, the measure of damages captures for the purchaser the<br />

benefit of the bargain and so compensates the purchaser for the loss of that<br />

benefit. (footnote omitted)<br />

[31] The defendant relies on a statement made by Leeming JA (with whom the other members<br />

of the court agreed) in Mainteck Services Pty Ltd v Stein Heurtey SA (2014) 310 ALR<br />

113 in dealing with what the plaintiff in a building case must prove to establish damages<br />

for breach of contract where there is a “global claim” for damages. Leeming JA<br />

confirmed at [186] that “there are no special legal principles that mean the plaintiffs in<br />

‘building cases’ win or lose differently from plaintiffs in other classes of contractual<br />

case”. Leeming JA then stated at [187]-[188]:<br />

“[187] A plaintiff seeking damages will fail unless he, she or it establishes<br />

breach, causation and loss.<br />

[188] True it is that some decisions on breach of contract in building cases<br />

have used the language of ‘global claim’. Contrary to what was at<br />

the forefront of Mainteck’s written and oral submissions, this does<br />

not involve any special principles of fact or of law.”<br />

[32] There is nothing in these general observations by Leeming JA in Mainteck which detract<br />

from the authority of Bellgrove and Tabcorp in the application of the ruling principle to<br />

the assessment of damages for breach of contract.<br />

Are all material facts pleaded in the statement of claim?<br />

[33] The plaintiffs are not required to plead that they are seeking for the damages to be<br />

assessed by the application of the ruling principle, as that is law that applies to the<br />

plaintiffs’ claim in accordance with the relevant authorities. A subsidiary complaint<br />

which the defendant’s solicitors had made in the r 444 letter dated 12 November 2015<br />

was that for the costs of rectification work to be recoverable as damages for breach as the<br />

plaintiffs had pleaded in their statement of claim “the dam must have been deficient in<br />

some way as a result of the alleged breaches” and asserted that the plaintiffs need to plead<br />

that each of those breaches created a deficiency in the dam and what the deficiency was.<br />

In similar vein, the defendant submitted on this application that no practical consequence<br />

from any defect in the dam, such as the dam not being reasonably fit for its purpose, is<br />

pleaded. The subsidiary point raised by the defendant is not supported by the relevant<br />

authorities.<br />

[34] In a claim for damages for breach of a construction contract in reliance on Bellgrove, the<br />

statement of claim must plead the relevant provisions of the contract, identify the breaches<br />

and then plead the action the plaintiffs assert must be taken to rectify the breaches to<br />

achieve conformity with the contract. This must be followed by the specification of the<br />

loss and damage arising from the costs of rectification.<br />

[35] The defendant’s submission which is critical of paragraph 20 (and also paragraph 21) of<br />

the statement of claim asserts that these are the paragraphs alleging loss and damage<br />

arising from the alleged breaches and that no attempt is made by the plaintiffs to identify<br />

or plead the causal nexus between breaches and the alleged loss and damage.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!