17.03.2016 Views

SUPREME COURT OF QUEENSLAND

QSC16-055

QSC16-055

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

5<br />

[13] The defendant’s main complaint about paragraphs 19 to 23 of the statement of claim is<br />

that there is a failure to assert a causal nexus linking each alleged breach of contract in<br />

paragraphs 14 to 18 of the statement of claim with the loss and damage flowing from each<br />

breach.<br />

[14] The plaintiffs rely on Bellgrove v Eldridge (1954) 90 CLR 613 to assert in response that<br />

no further facts need be pleaded as the first plaintiff is entitled to insist upon performance<br />

of the contract and adherence to the standards of construction required by the contract<br />

and the loss for a failure to comply with those standards is the sum of money required to<br />

make the work conform with the contractual standard.<br />

[15] On the strike out application, the issue is whether, in respect of a cause of action for<br />

damages for breach of a contract, it is necessary for the plaintiffs to plead any additional<br />

material facts in the statement of claim showing the causal link between the acts<br />

complained of and the loss claimed.<br />

[16] Both parties’ submissions addressed authorities relevant to identifying the material facts<br />

to be established to recover damages for breach of contract. It is appropriate therefore to<br />

consider the effect of these authorities.<br />

The relevant authorities<br />

[17] In Bellgrove the defendant owner counterclaimed against the plaintiff builder for breach<br />

of the building contract and claimed damages on the basis the house was worthless. The<br />

trial judge had found that there had been “a very substantial departure from the<br />

specifications” that resulted “in grave instability in the building”. The issue before the<br />

trial judge was whether there was available for remedying the defect in the construction<br />

of the foundations any practical solution other than the demolition of the building and its<br />

re-erection in accordance with the plans and specifications. Judgment was given for the<br />

defendant for the amount that represented the cost of demolishing and re-erecting the<br />

building in accordance with the plans and specifications together with certain<br />

consequential losses less the demolition value of the house and moneys unpaid under the<br />

contract.<br />

[18] The court observed at 617:<br />

“In the present case, the respondent was entitled to have a building erected<br />

upon her land in accordance with the contract and the plans and specifications<br />

which formed part of it, and her damage is the loss which she has sustained<br />

by the failure of the appellant to perform his obligation to her. This loss<br />

cannot be measured by comparing the value of the building which has been<br />

erected with the value it would have borne if erected in accordance with the<br />

contract; her loss can, prima facie, be measured only by ascertaining the<br />

amount required to rectify the defects complained of and so give to her the<br />

equivalent of a building on her land which is substantially in accordance with<br />

the contract.”<br />

[19] It is apparent from the discussion by the court of the assessment of damages in Bellgrove<br />

that it was a question of fact as to what work was necessary to remedy the defects in the

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!