SUPREME COURT OF QUEENSLAND
QSC16-055
QSC16-055
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
5<br />
[13] The defendant’s main complaint about paragraphs 19 to 23 of the statement of claim is<br />
that there is a failure to assert a causal nexus linking each alleged breach of contract in<br />
paragraphs 14 to 18 of the statement of claim with the loss and damage flowing from each<br />
breach.<br />
[14] The plaintiffs rely on Bellgrove v Eldridge (1954) 90 CLR 613 to assert in response that<br />
no further facts need be pleaded as the first plaintiff is entitled to insist upon performance<br />
of the contract and adherence to the standards of construction required by the contract<br />
and the loss for a failure to comply with those standards is the sum of money required to<br />
make the work conform with the contractual standard.<br />
[15] On the strike out application, the issue is whether, in respect of a cause of action for<br />
damages for breach of a contract, it is necessary for the plaintiffs to plead any additional<br />
material facts in the statement of claim showing the causal link between the acts<br />
complained of and the loss claimed.<br />
[16] Both parties’ submissions addressed authorities relevant to identifying the material facts<br />
to be established to recover damages for breach of contract. It is appropriate therefore to<br />
consider the effect of these authorities.<br />
The relevant authorities<br />
[17] In Bellgrove the defendant owner counterclaimed against the plaintiff builder for breach<br />
of the building contract and claimed damages on the basis the house was worthless. The<br />
trial judge had found that there had been “a very substantial departure from the<br />
specifications” that resulted “in grave instability in the building”. The issue before the<br />
trial judge was whether there was available for remedying the defect in the construction<br />
of the foundations any practical solution other than the demolition of the building and its<br />
re-erection in accordance with the plans and specifications. Judgment was given for the<br />
defendant for the amount that represented the cost of demolishing and re-erecting the<br />
building in accordance with the plans and specifications together with certain<br />
consequential losses less the demolition value of the house and moneys unpaid under the<br />
contract.<br />
[18] The court observed at 617:<br />
“In the present case, the respondent was entitled to have a building erected<br />
upon her land in accordance with the contract and the plans and specifications<br />
which formed part of it, and her damage is the loss which she has sustained<br />
by the failure of the appellant to perform his obligation to her. This loss<br />
cannot be measured by comparing the value of the building which has been<br />
erected with the value it would have borne if erected in accordance with the<br />
contract; her loss can, prima facie, be measured only by ascertaining the<br />
amount required to rectify the defects complained of and so give to her the<br />
equivalent of a building on her land which is substantially in accordance with<br />
the contract.”<br />
[19] It is apparent from the discussion by the court of the assessment of damages in Bellgrove<br />
that it was a question of fact as to what work was necessary to remedy the defects in the