623-625 Bath Rd, Brislington<br />

The demolition of a substantial worship hall followed by the Design & Construction of<br />

52new dwellings for Sovereign Housing Association Ltd<br />

Duration<br />

Value<br />

Contract Type<br />

Client<br />

Address<br />

Sector & Expertise<br />

100 Weeks<br />

£5.85m<br />

JCT Design & Build 2011<br />

Sovereign Housing Association<br />

623-625 Bath Rd, Brislington, Bristol, BS4 3LF<br />

Affordable Housing<br />

• Demolition of a substantial worship hall<br />

• Refurbishment & Conversion of Grade II Listed Building to provide<br />

four new dwellings<br />

• Comprehensive Archaeological investigative works and watching<br />

brief during Construction Phase<br />

• 2 No five storey timber frame blocks adjacent to main road fronting<br />

site<br />

The Construction of two large timber frame structures in close proximity<br />

to both existing and new dwellings presented logistical challenges<br />

which required detailed consideration during the procurement stages of<br />

the project. These constraints influenced the sequence of works on site<br />

to ensure that the potential risks were managed.<br />

EG Carter & Co Ltd played a leading role in the procurement of this<br />

project on behalf of Sovereign HA.<br />

The site came to market in 2012 and we promptly engaged with<br />

Sovereign HA to assemble a robust bid for the site acquisition. We<br />

played a leading role in this process by identifying the key risk factors<br />

effecting viability to inform the Conditionality of the subsequent bid.