27.04.2017 Views

OCL_Group_Capability_Profile_27.4.17_LR

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

BUiLDiNG DiviSiON<br />

BUiLDiNG DiviSiON<br />

The <strong>OCL</strong> building division has proved itself to be a fast growing dynamic division within the group providing the very best in service and quality.<br />

We have so far retained many happy clients and have recently won a number of 5 year framework contracts which is testament to our hard<br />

work and successful project deliveries over the years coupled with our management systems.<br />

Over the past 10 years we’ve worked on both many residential, domestic, commercial and large infrastructure building projects across the UK.<br />

We pride ourselves on our honest quoting process and providing a good finish that matches the highest standards to suit your budget.<br />

We are a fully accredited building contractor and hold £10m of full comprehensive insurances. Our building team are friendly, reliable and highly<br />

experienced. Our stores / warehouse department are able also to source high quality and good value building and roofing materials from across<br />

the UK and Europe, with accredited installer status.<br />

At <strong>OCL</strong> ensure we deliver our promises we make throughout every stage of your projects and provide you with full project lifecycle end-to-end<br />

delivery support for all our clients, services include fully planned and reactive building works covering complete installations, upgrades, minor<br />

repairs and maintenance services across all building disciplines within our operating market sectors<br />

kEY SERviCES<br />

• PROJECT MANAGEMENT<br />

• DOMESTIC RESIDENCES<br />

• ROOFING & WATERPROOFING<br />

• GENERAL BUILDING<br />

• BRICK WORK<br />

• PLASTERING<br />

• ROOFING<br />

• FENCING<br />

• TILING<br />

• LANDSCAPING<br />

• HOME EXTENSIONS<br />

• 1ST AND 2ND FIX CARPENTRY<br />

• LOFT CONVERSIONS<br />

• PLUMBING SERVICES<br />

• OUTBUILDINGS<br />

• POOL INSTALLATIONS<br />

PROJECT<br />

ipswich Temp Works<br />

CLiENT<br />

Giffen – aGa<br />

<strong>OCL</strong> were contracted to install multiple specialist temporary works, for new openings within ipswich Station structures.<br />

The works are part of the aGa station modifications.<br />

Due to the complex nature of the works, a design was created to install UC needles at close spacing’s. The slimshore supports<br />

were installed to an agreed design, with all ground enhancements completed prior.<br />

The <strong>OCL</strong> <strong>Group</strong> were able to offer experienced managers and operatives to deliver the project<br />

BREakDOWN OF WORkS UNDERTakEN aT iPSWiCH<br />

• Carry out all pre surveys, ground surveys and cat scans of areas<br />

• Core drill & install UC needles<br />

• install RC ground support where required<br />

• install slimshore supports and cross bracing<br />

• Grout and load the temporary works<br />

• Break through new openings<br />

• install new permeant UC lintel<br />

• Reinstate opening perimeters<br />

• Completion and submission of all required documentation for iTP and relevant site paperwork<br />

iNSTaLLaTiON TEaM<br />

• Project Manager x 1<br />

• Site Managers x 1<br />

• Foreman x 2<br />

• Operatives x 15<br />

• Compliance Manager - HSE auditor x 1<br />

EXaMPLE BUiLDiNG CaSE STUDiES<br />

PROJECT<br />

Upminster Depot Buildings Framework<br />

CLiENT<br />

SWiP / LU<br />

PROJECT<br />

Grange Hill – Buildings Framework<br />

CLiENT<br />

SWiP<br />

<strong>OCL</strong> were awarded the package of works, as part of our 5 year buildings framework agreement.<br />

Breakdown of works undertaken on project to date;<br />

SEQUENCiNG aDvaNCE WORkS<br />

Prior to commencing installation works the following activities were completed:<br />

• Survey of existing asset to confirm others had built to standard and spec.<br />

• Co-ordination meetings with SWiP<br />

• Order long lead items<br />

• Delivery of key materials into the allocated storage areas<br />

• Co-ordinate and plan access and depot traffic management arrangements as required<br />

• Completion & approval of Method Statements, Quality Plan & iTP<br />

install the ground floor blockwork walls.<br />

• Blockwork was 1400 solid lightweight ready blocks with a minimum 7N/mm3 and tenon bonded at joint intersections<br />

install soffit insulation<br />

• at ground floor level, a 75mm thick kingspan k10FM kooltherm was installed in the chemical storage area<br />

install window openings<br />

• New steel members were installed around new window openings to provide fixing points for new windows.<br />

install Levelling compound<br />

• Training and staff room areas that required carpet or vinyl, will have a levelling screed by Flowcrete installed in 2 layers,<br />

prior to the installation of carpet or vinyl flooring<br />

install Gypframe plasterboard walls and corridors<br />

• kingspan insulating boards and plaster skim finishes were installed in to internal corridors created and within the proposed<br />

training room soffits.<br />

Painting<br />

installation Team<br />

• Walls and ceilings were painted within the ancillary building<br />

• Exposed steel members and doors were prepared and painted<br />

• Project Manager x 1<br />

Post installation Works<br />

• Site Managers x 1<br />

• Operatives : x 15<br />

• Removal of all surplus materials from storage<br />

• Compliance Manager/HSE auditor x1<br />

• Final as built drawings including all redline drawings<br />

• Submit all required testing data and material data sheets<br />

• Completion of all iTPs for SWiP O&M requirements<br />

• Carry out meeting SWiP team regarding lessons learnt and feedback forum<br />

<strong>OCL</strong> was awarded this project due to our ability to provide an all-inclusive, multi experienced team package for bespoke works.<br />

The works package was to install a new suspended steel walkway, around the perimeter of the new SER room. The steel supports<br />

were installed so bearing was within the new brickwork and the existing retaining wall. These penetrations had to be carefully<br />

“toothed” out, to ensure the new and existing structures were not damaged outside the area of penetration required. These<br />

areas were then repaired and re built to create an apathetically pleasing end product.<br />

BREakDOWN OF WORkS UNDERTakEN ON PROJECT TO DaTE;<br />

• Remove all bird guano, contaminants, vegetation, debris, and friable materials from existing coverings.<br />

• Thoroughly clean all surfaces of roof with a fungicidal wash.<br />

• Flush through and test existing rainwater gully and associated pipework.<br />

• Carefully remove defective areas of asphalt, to roof’s a, B, C, D, E & F, repair blisters, smooth out slump/sags.<br />

• apply new kemperol roof system or equal approved.<br />

• Broadcast grit onto roof finish to achieve a minimum SRv of 0.36.<br />

• Re-instate safe walking route to match existing footprint.<br />

• Produce CDS and Form C for scaffold edge protection<br />

• Delivery of key materials into the allocated storage areas<br />

• Co-ordinate and Plan access and traffic management arrangements as required<br />

• Completion & approval of Method Statements, Quality Plan & iTP<br />

iNSTaLLaTiON TEaM<br />

• Project Manager x 1<br />

• Site Managers x 1<br />

• Operatives : x 15<br />

• Compliance Manager / HSE auditor x 1<br />

Page 18<br />

RaiSiNG THE STaNDaRDS • 01702 479 091<br />

ELECTRiCaL • CiviLS • MECHaNiCaL • BUiLDiNG • LaBOUR SUPPLY<br />

Page 19

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!