GEORGIAN MANOR REDEVELOPMENT PROJECT STATUS REPORT ISSUE 2 | SPRING | <strong>2011</strong><br />
SITE SERVICING<br />
NEARING COMPLETITION<br />
• <strong>Georgian</strong> <strong>Village</strong> Underground works<br />
have been ongoing since last October.<br />
Site forces have pushed forward despite<br />
having been held up by severe weather<br />
last winter.<br />
• Now that it appears <strong>Spring</strong> is upon us,<br />
construction teams have started the<br />
building’s foundation. <strong>Georgian</strong> <strong>Village</strong>’s<br />
first foundation pour occurred on March<br />
16th at “Block A”, the <strong>Village</strong>s main<br />
Rendezvous area. Foundation excavation<br />
work and pouring of footings and piers will<br />
continue through to the Fall.<br />
CIVIL WORK STATUS<br />
Storm Sewer<br />
• Main is largely completed<br />
• Site SWM pond has been roughly excavated and is currently functioning<br />
• Swales on the West side of the site are rough graded and functioning to collect site runoff<br />
• Temporary access culverts for Thompsons Rd are in place and permanent access culvert at Edward St is in place<br />
Sanitary Sewers are complete with the exception of Building D).<br />
Water Main is largely complete with the exception of connection to Building B<br />
April <strong>2011</strong>
<strong>Georgian</strong> <strong>Village</strong><br />
Relax, You’re Home<br />
<strong>Georgian</strong> Gardens<br />
(Life Lease Homes)<br />
<strong>Georgian</strong> Suites<br />
(Life Lease Apartments)<br />
SPRING EXPECTATIONS<br />
<strong>Georgian</strong> Residences<br />
(Assisted Living)<br />
Below Grade Construction<br />
The footings, foundations, and pier Excavation is underway<br />
at Block A — The <strong>Georgian</strong> Rendezvous (<strong>Village</strong> Centre)<br />
and <strong>Georgian</strong> Manor Administration Services. Once<br />
completed near April’s end, this crew will continue to Block<br />
B — <strong>Georgian</strong> Manors Facility Services, then Block C —<br />
<strong>Georgian</strong> Manor’s North Resident Wings, and finally, Block<br />
D– <strong>Georgian</strong> Manor’s South Resident Wings.<br />
Simultaneously, by mid-April, a second crew will begin<br />
below Grade Construction at Block G — The <strong>Georgian</strong><br />
Residences (Assisted Living), then Block F — The<br />
<strong>Georgian</strong> Suites (Life Lease Apartments), and finally Block<br />
E—<strong>Georgian</strong> Terraces (Affordable Housing).<br />
Foundation walls were slated to begin April 11, and similarly<br />
<strong>Georgian</strong> Rendezvous<br />
(<strong>Village</strong> Centre)<br />
<strong>Georgian</strong> Terraces<br />
(Affordable Housing)<br />
<strong>Georgian</strong> Manor<br />
(Long Term Care)<br />
<strong>Georgian</strong> Gardens<br />
(Life Lease Homes)<br />
<strong>Georgian</strong> <strong>Village</strong> Redevelopment<br />
Penetanguishene, Ontario<br />
follow the schedule above after footings, foundations, and<br />
pier Excavations are completed.<br />
Also slated to start this <strong>Spring</strong> and early Summer, are:<br />
1. underground electrical and mechanical services<br />
starting with Block A and following the same general<br />
sequence as above.<br />
2. Above Grade Superstructure & Building Envelope<br />
Structural Steel<br />
3. Masonry Block<br />
4. Exterior Windows<br />
<strong>Georgian</strong> <strong>Village</strong>’s Internal Ring Road will begin receiving<br />
it’s base course asphalt as plants opening this May and<br />
complete by Mid-June.
<strong>Georgian</strong> <strong>Village</strong><br />
Relax, You’re Home<br />
Winter Works 2010<br />
March 16, <strong>2011</strong> - First Foundation concrete pour<br />
Work on foundations continue
<strong>Georgian</strong> <strong>Village</strong><br />
Relax, You’re Home<br />
The Project Sign is scheduled to be installed on site as weather permits.<br />
PROJECT BREAKDOWN<br />
Long Term Care<br />
132,017 GSF<br />
(Blocks B, C, & D and part of Block A)<br />
Assisted Living<br />
40,642 GSF (Block G)<br />
Affordable Housing<br />
44,356 GSF (Block E)<br />
Life Lease Housing<br />
52,720 GSF (Block F)<br />
Common <strong>Village</strong> Centre<br />
8,615 GSF (Block A part)<br />
Community Program Space<br />
4,434 GSF (Block A part)<br />
WEBSITE AND COMMUNITY UNDATES<br />
OPEN<br />
MON-WED<br />
10AM-4PM<br />
Sales Centre<br />
23 Harriet St.,<br />
Penetanguishene<br />
Mon to Wed, 10AM - 4PM<br />
or call Bob Klug<br />
at 705-549-9292 to book<br />
an appointment<br />
Visit our Progress Page online at www.georgianvillage.ca and experience our newly posted VIRTUAL TOUR or peruse our<br />
previously issued <strong>Status</strong> <strong>Report</strong>s and Newsletters. Also available are specific building layouts and <strong>Village</strong> grounds, as well as<br />
suite and room layouts.<br />
TIME CAPSULE<br />
These exciting <strong>Georgian</strong> Manor redevelopment days will be represented in the Time Capsule intended to be interred at our<br />
Grand Opening in 2013. All suggestions are welcome for inclusions to the Time Capsule and you can visit our website,<br />
<strong>Georgian</strong> Manor, or our Sales Centre in Penetanguishene to obtain submission forms.<br />
Visit our Progress Page online at www.georgianvillage.ca and experience our newly posted VIRTUAL TOUR or to enjoy<br />
previously issued <strong>Status</strong> <strong>Report</strong>s and community oriented Newsetters.