31.07.2018 Views

August 2018

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Insurance Focus<br />

PROJECT POLICIES: CONTRACTORS,<br />

MAKE SURE YOU’RE COVERED...<br />

By Ian Hollingworth, Head of Claims for ECIC.<br />

The High Court’s recent decision that a<br />

roofing firm that caused a fire at a high<br />

school in London was not protected by a<br />

project policy has raised some serious questions<br />

over the reliance by sub-contractors on these<br />

types of insurance policies. This could expose<br />

contractors and subcontractors to higher risks –<br />

in particular smaller sub-contractors working on<br />

large contracts could be vulnerable as a result of<br />

this ruling.<br />

Traditionally, employers on larger construction<br />

projects take out a project policy to cover damage<br />

to the existing structure and possibly the contract<br />

works being undertaken by the sub-contractors<br />

appointed to work on site.<br />

“The project policy<br />

insurer dealt with the<br />

property loss, but then<br />

sought to recover their<br />

outlay from the<br />

contractor that caused<br />

the loss”<br />

As this type of policy would usually provide<br />

protection to named contractors and sometimes<br />

all contractors in the contractual chain, it<br />

provides peace of mind that in the event of a fire<br />

or some other damage caused by contract<br />

workers on site, the project policy would step in.<br />

In the event of damage to the property, the project<br />

policy insurer would simply cover the loss rather<br />

than each sub-contractor going to their own<br />

insurers to recover the cost of their own damaged<br />

contract works.<br />

This avoids lengthy and often costly litigation<br />

between various contractors who could be<br />

blamed for causing the damage<br />

to the building.<br />

The project policy avoids all of<br />

this and ensures the property<br />

and works are adequately covered<br />

to avoid lengthy delays in the<br />

completion of the construction.<br />

Terms of the sub-contract<br />

However, in a recent case, (Haberdashers’ Aske’s<br />

Federation Trust Ltd v Lakehouse Contracts Ltd<br />

and others [<strong>2018</strong>] EWHC 558 (TCC)), the High<br />

Court found roofing firm CPR wasn’t protected by<br />

the project policy because the terms of the subcontract<br />

required that they should maintain their<br />

own insurance.<br />

Usually a construction contract would contain an<br />

insuring clause requiring the individual subcontractor<br />

to take out insurance to cover their<br />

own contract works along with Employers Liability<br />

and Public Liability. This is even if there is a<br />

project policy in place.<br />

The difference with this case was that the project<br />

policy insurer dealt with the property loss, but<br />

then sought to recover their outlay from the<br />

contractor that caused the loss.<br />

This was unusual as a project policy is usually<br />

taken out in joint names – the policyholder and all<br />

sub-contractors; this previously meant the project<br />

policy insurer could not seek a recovery as<br />

essentially all sub-contractors would be considered<br />

a policyholder and covered under the policy.<br />

Notably in this instance, the Court allowed the<br />

project insurer to recover the loss from the subcontractor.<br />

This was on the basis that the main<br />

construction contract had required that the subcontractor<br />

take out their own insurance. In addition,<br />

the sub-contractor was not named at the<br />

commencement of the<br />

construction project and therefore<br />

not factored into the cover by the<br />

project policy insurer when the policy was<br />

taken out.<br />

This ruling has really called into question the<br />

effectiveness of project insurance. It has wide<br />

ramifications for contractors as they can no longer<br />

rely upon a project insurer to pick up a loss in the<br />

event of damage they have caused to a property.<br />

It’s essential, therefore, that they ensure adequate<br />

cover is taken out to cover their potential<br />

liabilities. Seeking the advice and support of an<br />

insurance broker is highly recommended.<br />

Additionally, the insurers of sub-contractors can<br />

no longer rely on the existence of a project policy<br />

to cover a loss. This could mean higher insurance<br />

claims which may have a knock-on effect in<br />

premium increases.<br />

Now, more than ever, it is important for subcontractors<br />

to understand the risks attached to<br />

their works and the potential losses they could<br />

face if they don’t ensure adequate insurance<br />

cover is in place for any eventuality.<br />

Contact ECIC<br />

0330 221 0250<br />

www.ecic.co.uk<br />

Left: Ian Hollingworth, Head of Claims<br />

for ECIC.<br />

“The insurers of subcontractors<br />

can no<br />

longer rely on the<br />

existence of a project<br />

policy to cover a loss”<br />

24 TC AUGUST <strong>2018</strong>

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!